Item 4B ~. AGENDA ITEM # 4B MARCH 26, 2007 CITY OF ATLANTIC BEACH CITY COMMISSION MEETING STAFF REPORT AGENDA ITEM: Begonia Street Utility and Roadway Improvements CDBG Project SUBMITTED BY: Donna Kaluzniak, Utility Direct Rick Carper, P.E., Public Works Director~~~ DATE: March 16, 2007 BACKGROUND: Community Development Block Grant funds were designated to extend water and sewer lines on Begonia Street from Levy Road to West 14th Street. The utility construction will require digging up most of the existing roadway, which is currently a substandard (16 feet wide) road. Staff recommends widening the road to a width of 20 feet during reconstruction to meet current City standards (Land Development Regulations Sec. 24-252 (i)). In addition, some minor drainage „~, improvements are needed to connect to an existing cross drain. These costs were not included in the original estimate. Also, after completing the detailed water and sewer design, it also appears that the utility work may exceed the budgeted funding. The total estimated additional cost is approximately ~. $50,000. BUDGET: A total of $100,000 in CDBG grant funds is available for the project. Additional funds are available ($50,000) from the Mandalay Park project (001-5002-541-6300, PW0702). RECOMMENDATION: Approve the transfer of $50,000 from the Mandalay Park project to the Begonia Street project for roadway improvements. ATTACIEIIVVIENTS: 1. Preliminary cost estimates for Begonia Street Project REVIEWED BY CITY MANAGER: AGENDA ITEM # 4B MARCH 26, 2007 PWD Cost Estimate -Begonia Water /Sewer Addition and Street Widening 3/16/07 Item # Est. Qty. Units Description Unit Price Total Price 1 1 LS Mobilization $5,000.00 $5,000.00 2 1 LS Maintenance of Traffic $2,500.00 $2,500.00 3 1 LS Site Preparation /Erosion Control $6,000.00 $6,000.00 4 Furnish & Install PVC Water main 393 LF 6" Diameter DR25 PVC $32.00 $12,576.00 5 Furnish & Install Fittings 1 EA 6" 90^ elbow $450.00 $450.00 8 EA 6" 45^ elbow $420.00 $3,360.00 1 EA 6"x8" Tee $380.00 $380.00 2 EA Connect to Existing Watermain $250.00 $500.00 6 11 EA Furnish & Install Water meter, Box & Service $710.00 $7,810.00 7 1 EA Fumish & Install Fire Hydrant Assembly and Fittings $3,200.00 $3,200.00 8 1 LS Quality Control Testing $2,500.00 $2,500.00 9 310 LF Furnish & Install DR35 8" PVC Sewer main $48.00 $14,880.00 10 1 EA Furnish & Install New Sanita Sewer Manhole $5,800.00 $5,800.00 11 1 EA Connect to existing manhole $500.00 $500.00 12 Construct Sewer Cleanouts and Services 7 EA Single $680.00 $4,760.00 2 EA Double $1,400.00 $2,800.00 13 1010 SY 12"Constructed sub base $2.50 $2, 525.00 14 1010 SY 6" limerock base $9.00 $9, 090.00 15 780 SY Pavement Removal $10.00 $7,800.00 16 920 SY 1 1/2" S-3 Asphaltic concrete $25.00 $23, 000.00 17 100 SY Remove and replace 5"Concrete driveway $60.00 $6,000.00 18 300 SY Grassing $4.50 $1,350.00 19 250 LF Regrade Swale $40.00 $10,000.00 20 1 EA Type C Inlet $2, 500.00 $2, 500.00 21 1 EA Mitered End Section $1,000.00 $1,000.00 TOTAL $136,281.00 0.1 Contingency 10% $13,628.10 GRAND TOTAL INCLUDING CONTINGENCY $149,909.10 3/16/2007