Handout - Michael and Marian FoggMichael and Marian Fogg
michaelfogg@bellsouth.net
10/2.eft9
366 Plaza
Topic: - Reimbursement for replacing the City's cracked
sidewalk and crumbling curb.
1. I inquired about having the City repair/replace their defective
concrete in the city right of way in front of our home.
2. I was directed to the head of Public Works; Scott Williams. He
came by to inspect my concern and AGREED that the curb
needed to be replaced, and yes, it would be advantageous to tie
it in with the two new houses adjoining the east of our property.
3. Mr. Williams said that he had already committed his 2019
budget and did not have the money to do the repair. He said
that I could repair it at my own cost and submit my receipt to
the City Manager and request reimbursement, if any monies
were available.
4. Mr. Williams told me that there were NO plans for spending
money on the sidewalks in the 300 block of Plaza for at least
FIVE years. He did not intentionally mislead me.
5. With the information that we would have to live with crumbling
concrete for five years, in July 2019, I paid for a permit and
paid to have the work done, at the same time that the two new
constructions next to us were replacing the concrete they had
demoed.
6. Behold ! Three weeks ago (NOT 'five years' later) the entire
300 block of Plaza was receiving parcels of sidewalk and curb
demolition and replacement.
7. Since the former and exiting City Manager appropriated the
money to do 49 repairs in our 300 block, I think that the City of
Atlantic Beach should pay for my much needed repair of a city
sidewalk, on City right of way.
49 Repairs \ 300 Block of Plaza
Our curb,
Before
repair -
Our curb,
After I paid
for repair -
Our Curb, tied in with
two New Homes to
produce continuous
drainage -
North Jax Concrete
July 8,2019
Bill to: Michael Fogg
Address: 366 Plaza
Atlantic Beach, FL
Replace 50 feet of city's cracked and broken gutter and curb
to meet city's specifications
950
Replace 30' of city's sidewalk in front of east driveway to
alleviate ponding on sidewalk
1,125
2,075 - Total for labor and materials
eLIFF