ABCC site plans - 4Doug, Freddie says the outfall pipe from Public Works to the SW pond (new pond designation SWMF 5) is completely buried and the Supervisor working piping installation in the vicinity
didn’t know it existed. Please have pipe exposed and extended if necessary to reach new pond site.
Alex, any progress on easements discussed at the Feb. 6th meeting (expanding the north side water line easement to 20’ and adding a 20’ easement for this outfall pipe)? Will this be
included in the Plat submission discussed a couple of weeks ago?
Thanks, Rick
Ricky L. Carper, P.E.
Public Works Director/City Engineer
City of Atlantic Beach
1200 Sandpiper Lane
Atlantic Beach, FL 32233
rcarper@coab.us<mailto:rcarper@coab.us>
PH: (904) 247-5834
Fax: (904) 247-5843
Florida Public Works - First to Respond, Last to Leave
www.apwaflorida.com<http://www.apwaflorida.com>
From: Carper, Rick
Sent: Thursday, February 06, 2014 1:27 PM
To: Kaluzniak, Donna; Lyon, Mark
Cc: Walker, Chris; Brown, Emmanuel
Subject: RE: 24" water main
Donna & Mark, discussed expanding this easement to 20’, and adding a 20’ easement along the storm sewer for the PW outfall at the meeting with Rick Woods and Glynn Taylor. They said
should not be a problem and Alex Acree would look into it.
Rick
Ricky L. Carper, P.E.
Public Works Director/City Engineer
City of Atlantic Beach
1200 Sandpiper Lane
Atlantic Beach, FL 32233
rcarper@coab.us<mailto:rcarper@coab.us>
PH: (904) 247-5834
Fax: (904) 247-5843
Florida Public Works - First to Respond, Last to Leave
www.apwaflorida.com<http://www.apwaflorida.com>
Thanks, Donna
From: Alex Acree [mailto:Alex.Acree@taylorandwhite.com]
Sent: Friday, February 14, 2014 10:31 AM
To: Kaluzniak, Donna
Cc: Doug Maier; john@jcollinsengineering.com<mailto:john@jcollinsengineering.com>; Glynn Taylor; Townsend, Tim
Subject: RE: ABCC site plans
Donna,
Per COAB as-builts of the utilities along the western property line there should not be a conflict with the construction of SWMF-2, however additional fiber optic lines have been located
outside of the existing 20’ Utility Easement that are not depicted on the as-builts. Further information may be needed in this area.
COAB is currently locating the 24” Water Main that runs along the northeast property line as it was also not located on the as-builts. If the treatment basins are in conflict with the
existing 24” WM we will reshape as necessary to avoid conflict.
Thanks,
Alex R. Acree, P.E.
Project Engineer - Taylor & White, Inc.
9556 Historic Kings Road S., Suite 102 - Jacksonville, Florida 32257
t: (904) 346-0671 - f: (904) 346-3051 - m: (904) 874-2307
www.TaylorandWhite.com<http://www.taylorandwhite.com/> - Alex.Acree@TaylorandWhite.com<mailto:Alex.Acree@TaylorandWhite.com>
From: Kaluzniak, Donna [mailto:dkaluzniak@coab.us]
Sent: Friday, February 14, 2014 8:42 AM
To: Alex Acree
Cc: Doug Maier; john@jcollinsengineering.com<mailto:john@jcollinsengineering.com>; Glynn Taylor; Townsend, Tim
Subject: FW: ABCC site plans
Alex, I am not expert at reading these drainage maps or golf course design, but need to ensure there is no conflict with the utility easements on the west and north for the force mains
and 24” water main. Would you check please?
Thanks, Donna
Donna Kaluzniak, Utility Director
City of Atlantic Beach
902 Assisi Lane
Atlantic Beach, FL 32233
(904) 270-2535
dkaluzniak@coab.us<mailto:dkaluzniak@coab.us>
From: Townsend, Tim
Sent: Friday, February 14, 2014 8:25 AM
To: Kaluzniak, Donna
Subject: ABCC site plans
Donna,
FYI.
If I’m reading correctly, on Sheet #4 of the Taylor & White prints the excavations SWMF-2, and TB-11, TB-12 pose potential conflicts with either are force mains or the
24” water main from #2 WTP. TNT