Attachment C
219 N Newnan Street, 4th Floor •Jacksonville, Florida, 32202
October 15, 2021
Shane Corbin, City Manager
City of Atlantic Beach
800 Seminole Road
RE: COMPLETE STREETS PLANNING & INITIAL DESIGN CONCEPTS, MAIN STREET
Dear Mr. Corbin:
As requested, please see the attached scope of services to provide Complete Streets Planning & Initial
Design to the City of Atlantic Beach for the local road Main Street.
Our firm services include Civil Engineering, Construction Engineering Inspection (CEI), Material
Testing, Planning services with specialized work in Transportation Planning, Strategic Funding
including Grant Writing, Project Management, and Reimbursement/Funding Assistance, Asset and
Infrastructure Maintenance, Permit Inspections, Building Code Inspections, Bridge Coatings, and
Intelligent Transportation System (ITS) inspections.
We are proud to partner with our subconsultant DDEC led by Traffic Engineer Uyen Dang P.E.. DDEC
brings successful, thoughtful and creative approach and design that has led to successful municipal
construction projects.
For this assignment our services consist of:
• Initial planning and concept review
• Alternative corridor concepts, stakeholder engagement, commission presentation
• Planning Grant Application narrative development
AE Engineering is excited to provide support services to the City of Atlantic Beach on this contract and
future opportunities. Please feel free to contact me to discuss the details of the proposal at your
convenience. Thanks again for this important opportunity.
Sincerely,
Roderick Myrick, P.E., President
Attachement C
10-16-21 Town Hall Minutes
Continuing Services Contract
1
Scope of Services
The scope of services for this contract includes providing Planning and Engineering staff to assist the
City of Atlantic Beach on tasks (outlined below), on an hourly basis. Please see below an outline of our
expected services followed by associated hours and fees for consideration and approval. We strive to
meet expectations on time and under budget. Should funds be available, other tasks can be performed
as identified.
Scope of Services: City of Atlantic Beach Complete Streets Targeted Planning & Preliminary Design
Project Location: Main Street
Task 1: Review existing conditions of existing planning documents, traffic analysis, comprehensive plan, bicycle
network, parking policy and other functionality of the corridor.
• Review existing and future land used of the Main Street neighborhood boundaries
• Review census data and identify mode priority
• Conduct a site visit and parking counts for daytime, night time and weekend along the project limits
• Identify business and residential stakeholders adjacent to the corridor
• As-builts research
• Collect traffic data
• Review available commentary, commission minutes or other available public input regarding Main Street
and community mission regarding Complete Streets
Deliverables: Existing conditions memo
Task 2: Provide alternative corridor analysis for complete streets, intersection improvements and connectivity
nodes
• Provide circulation and cut through pattern of Main Street
• Prepare traffic calming alternatives and strategy that align with adopted community objectives
• Prepare and implement public engagement strategy for target stakeholders
• Prepare exhibits and conduct a corridor workshop for commission leadership
Deliverables: Initial design alternatives and workshop presentation materials
Task 3: Provide preliminary planning document
• Prepare preliminary design concept
• Prepare typical sections and rendering
• Identify funding sources for short-term and long-term
• Prepare NFTPO project scope and/or grant support documentation and submittal package as identified
and agreed upon by local staff and leadership where required
Deliverables: Planning document, typical sections and rendering
Other tasks:
• Prepare project website and communication strategy to engage stakeholders in Complete Streets
Workshop findings
Attachement C
10-16-21 Town Hall Minutes
Continuing Services Contract
2
Time and Fee Table
Task
ID
Elements Task Detail Estimated Time in
hours
Total Time in
Hours
1 Review existing
conditions
• Review existing and future land
use of the Main Street
neighborhood boundaries
• Review census data and identify
mode priority
• Conduct a site visit and parking
counts for daytime, night time
and weekend along the project
limits
• Identify business and residential
stakeholders adjacent to the
corridor
• As-builts research
• Collect traffic data
• Review available commentary,
commission minutes or other
available public input regarding
Main Street and community
mission regarding Complete
Streets
• Deliverable, Existing Conditions
Memo
2 Provide alternative
corridor analysis for
Complete Streets
• Provide circulation and cut
through pattern of Main Street
• Prepare traffic calming
alternatives and strategy that
align with adopted community
objectives
• Prepare and implement public
engagement strategy for target
stakeholders
• Prepare exhibits and conduct a
corridor workshop for commission
leadership
Attachement C
10-16-21 Town Hall Minutes
Continuing Services Contract
3
3 Provide preliminary
planning document
• Prepare preliminary design
concept
• Prepare typical sections and
rendering
• Identify funding sources for short-
term and long-term
• Prepare NFTPO project scope
and/or grant support
documentation and submittal
package as identified and agreed
upon by local staff and leadership
where required
Deliverables: Planning document, typical
sections and renderings
a. Contract Rate Estimated Fee: $ 44,960
Attachement C
10-16-21 Town Hall Minutes
Continuing Services Contract
4
Professional Services Agreement: Task Order
Client:
City Of Atlantic Beach
Project:
Complete Streets, Main Street
Agreement Date:
10/1/2021
Project number:
Attention: Shane Corbin Email:scorbin@coab.org Contract Title:
Continuing Services Contract
This task order is made between AE Engineering Inc. (Consultant) and the City of Atlantic Beach (City)
for services in connection with the project above. In consideration of the existing agreements with the
City, the City and Consultant agree to the task order as follows:
TOTAL INITIAL AMOUNT ………. $44,960
A. SCHEDULE
Job
Description
Amount
Complete Streets Planning & Initial
renderings, Main Street
Task 1 Review existing conditions
Task 2 Provide alternative
corridor analysis for complete
streets
Task 3 Provide preliminary
planning document
B. CORRESPONDENCE To ensure prompt response, email all correspondence to the appropriate contact
listed below.
Signed contracts, Notices, Correspondence:
Attn: Heather Neville, AICP
Email: HNeville@AEEngineeringInc.com
Attn: Catherine McLeod, Contract Manager
Email:CMcleod@AEEngineeringinc.com
C. All terms and conditions of the existing continuing services contract not modified here in shall
remain in force and effect
Consultant
AE Engineering Inc
Client
City of Atlantic Beach
Signed by: Heather Neville
Title: Director of Planning
Email: hneville@aeengineeringinc.com
Signature:
Signed by: Shane Corbin
Title: City Manager
Email: scorbin@coab.com
Signature:
Attachement C
10-16-21 Town Hall Minutes
Senior Principal (Licensed)Principal (Licensed)Senior Professional EngineerSenior Planner (Licensed)Senior DesignerDesignerWeb DeveloperCommunications SpecialistGrants CoordinatorAdministrative Assistant285.00$ 250.00$ 185.00$ 185.00$ 140.00$ 120.00$ 120.00$ 150.00$ 140.00$ 85.00$
Task 1: Review existing conditions of existing planning documents, traffic analysis, comprehensive plan, bicycle network, parking policy and other functionality of the corridor.
Review existing and future land used of the Main Street neighborhood
boundaries 1 1 1
Review census data and identify mode priority 1 1
Conduct site visit and parking counts for daytime, night time and
weekend along the project limits 4 4
Identify business and residential stakeholders adjacent to the corridor 2
Asbuilts research and coordination 2
Collect traffic data 6 5
Prepare Existing Conditions Memo 2 8 8
Sub Total Hours 3 22 0 21 0 0 0 0 0 0
Sub Total Fees 855.00$ 5,500.00$ -$ 3,885.00$ -$ -$ -$ -$ -$ -$
Total Task 1 10,240.00$
Task 2: Provide alternative corridor analysis for complete streets, intersection improvements and connectivity nodes
Provide circulation and cut through pattern of Main Street 2 2
Prepare traffic calming alternatives and strategy 4 2
Prepare and implement public engagement strategy for target
stakeholders 4 8 8
Prepare exhibits and conduct a corridor workshop 4 4 4 4
Project Stakeholder Workshop 4 4 4 4 4 4
Presentation to Commission Meeting 2 2
Sub Total Hours 4 20 0 22 16 0 0 8 0 4
Sub Total Fees 1,140.00$ 5,000.00$ -$ 4,070.00$ 2,240.00$ -$ -$ 1,200.00$ -$ 340.00$
Total Task 2 13,990.00$
Task 3: Provide preliminary planning document
Prepare preliminary typical section concept 8 4 40
Prepare typical sections and rendering 8 40
Identify funding sources for short term and long term (Estimating and
prepare project scope)2 8 4
Prepare MPO grant documentations and submittal package 8
Sub Total Hours 2 24 0 16 80 0 0 0 0 0
Sub Total Fees 570.00$ 6,000.00$ -$ 2,960.00$ 11,200.00$ -$ -$ -$ -$ -$
Total Task 3 20,730.00$
Other Tasks: Prepare project website with marketing strategy to engage
stakeholders 40 40
Sub Total Hours 0 0 0 0 40 0 40 0 0 0
Sub Total Fees -$ -$ -$ -$ 5,600.00$ -$ 4,800.00$ -$ -$ -$
Total Task 1 10,400.00$
Total Fee 44,960.00$
Total Fee and Add Alternate 55,360.00$