Permit Reviews_7Permit Reviews
City of Atlantic Beach
Permit Number: RES022-0036
Applied: 6/22/2022 Approved:
Issued:
Finaled:
Status: AWAITING CORRECTIONS
Parent Permit:
Parent Project:
Details:
OWNER BUIDER
Description: INTERIOR BUILDOUT OF GARAGE
Site Address: 343 PLAZA
City, State Zip Code: Atlantic Beach, FI 32233
Applicant: <NONE>
Owner: LOVE NANCY J
Contractor: <NONE>
LIST OF REVIEWS
SENT DATE
RETURNED
DATE
DUE DATE
TYPE CONTACT
STATUS
REMARKS
Review Group: 2ND REVIEW
8/11/2022
8/11/2022
SUBMITTAL
Permit Tech
APPROVED
COMPLETENESS
Notes:
ONE ATTACHMENT from nancy@coastaladvantagerealty.com
ENERGY FORMS AND DUCT LAYOUT
8/11/2022
8/15/2022
8/25/2022
BUILDING
Building
DENIED
Notes:
1. The energy form R402-2020 was not filled out making it incomplete. Please fill out the needed information and sign the last page. Ceiling and wall
insulation R -Values needed of the existing building. If not insulated it will have to be. The ceiling will have to be R38 unless it is flat, then if will have to
be at least R19. Stick frame wall insulation shall be a minimum of R13, if exterior walls are cmu blockwork the walls shall be inslulated to an R6 value.
7th Edition of the FBC-Existing Building Code; Section R503 ALTERATIONS; R503.2 Change in space conditioning. Also SECTION R505 CHANGE IN
OCCUPANCE OR USE.
2. Resubmittals may generate other review comments.
Review Group: 3RD REVIEW
3/1/2023
3/1/2023
SUBMITTAL
Permit Tech
APPROVED
COMPLETENESS
Notes:
ONE ATTACHMENT
FORM 402-2020 ENERGY SHEET
3/1/2023
3/8/2023
3/15/2023
BUILDING
Building
DENIED
Notes:
1. I was not aware that spray foam insulation was going to be used for insulation. Please contact the vendor/installer/insulation contractor and ask
them to send you the ESR Evaluation Report for the spay foam to be used on this project. This is a Standard Operation Procedure for installation of open
and closed cell insulation here in Atlantic Beach.
2. Resubmittals may generate other review comments.
Printed: Thursday, 09 March, 2023
1 of 2
CENTRALSQUARE
Permit Reviews
City of Atlantic Beach
Review Group: AUTO
6/22/2022
6/22/2022
SUBMITTAL
COMPLETENESS
Permit Tech
APPROVED
Notes:
ONE ATTACHMENT
OPEN DRIVEWAY PERMIT
6/22/2022
7/11/2022
7/7/2022
ZONING
Zoning
APPROVED
Notes:
6/22/2022
6/30/2022
7/7/2022
BUILDING
Building
DENIED
Notes:
1. Resubmit the survey indicating where on the existing building the build out will occur by highlignting that area and writing notes next to that spot.
2. Submit an existing floor plan showing all equipment that is located in the garage and any existing floor elevation differences.
3. Resubmit the proposed floor plan with every proposed newly created space/room/area labeled. Show where attic access will be.
4. From the 7th Edition of the 2020 FBC-Existing Building Code, choose a methode of construction compliance from Chapter 3; and from Chapter 6, the
Classification of Work (Alteration Level). Place this information on the resubmitted proposed floor plan.
5. Please submit documentation from a licensed HVAC contractor that the existing hvac heating and cooling system is sufficient in size to accommodate
the proposed garage build -out space.
6. Submit Energy Form R402-2020 for information needed on this proposed build -out. A pdf of the form will be provided.
7. Submit a ductwork floor plan lay out of the proposed build -out area. Should identify supply and returns as well as bathroom exhaust fan, if required.
8. Is there a door separating the bathroom area from the rest of the build -out area? If so call out that door type and size on the proposed floor plan.
9. Submit the Florida Product Approval Information Sheets for all components and cladding items for this proposed build -out. New doors, windows,
siding material and the Product Approval Numbers. Installation of new doors and windows will be required at the job site when their installation
inspection is requested by you. Siding installation instructions and Evaluation Report, if applicable for this project, are required now at plan review.
10. Submit an electrical floor plan for lighting and receptacle location. Any newly created egress openings will require a switch and exterior lighting at
those egress opening. Please show the location of the required smoke detector.
11. Please give a written narrative of what appliances will be installed at the counter shown on the submitted proposed floor plan. Write in on the floor
plan those appliance locations.
12. Submit signed and sealed engineered structual plans for any wall alterations that will be required to fill in an opening or open up a wall for the
installation of any doors or windows.
13. Please submit the existing elevations of the garage portion of this buiding and the proposed elevations of the walls affected by this proposed garage
build -out.
14. Resubmittals may generate other review comments.
15. The link to the revision/correction form is : http://coab.us/DocumentCenter/View/10495/Revision-Request-Correction-to-Comments-Route-Sheet-
v20181017?bidld=
16. The email address to send resubmittals is : Building-dept@coab.us
6/22/2022
6/22/2022
7/7/2022
PUBLIC WORKS
Public Works
NOT APPLICABLE
TO DEPARTMENT
Notes:
6/22/2022
6/22/2022
7/7/2022
PUBLIC UTILITIES
Public Utilities
NOT APPLICABLE
TO DEPARTMENT
Notes:
Printed: Thursday, 09 March, 2023