2233 Seminole Rd COMM23-0031 COAB Permit Form with ConditionsOWNER:ADDRESS:CITY:STATE:ZIP:
OCEAN VILLAGE
ASSOCIATION INC
C/O SIGNATURE REALTY &
MANAGEMENT JACKSONVILLE FL 32257
COMPANY:ADDRESS:CITY:STATE:ZIP:
Pool Builder Services LLC 4014 Ringneck DR JACKSONVILLE FL 32226
TYPE OF
CONSTRUCTION:
REAL ESTATE
NUMBER:ZONING:BUILDING USE
GROUP:SUBDIVISION:
169519 0144 OCEAN VILLAGE ONE
CONDO
JOB ADDRESS:PERMIT TYPE:DESCRIPTION: VALUE OF WORK:
2233 SEMINOLE RD COMMERCIAL ALTERATION
COMMERCIAL
RESURFACE POOL, PAVER
DECK OVER CONCRETE &
SIGNAGE
$84800.00
LIST OF CONDITIONS
Roll off container company must be on City approved list . Container cannot be placed on City right-of-way.
1 PUBLIC WORKS EROSION CONTROL INSTALLATION INFORMATIONAL
Notes:
Full erosion control measures must be installed and approved prior to beginning any earth disturbing activities. Contact the Inspection Line (904-247-
5814) to request an Erosion and Sediment Control Inspection prior to start of construction.
NOTICE: In addition to the requirements of this permit, there may be additional restrictions applicable to this property
that may be found in the public records of this county, and there may be additional permits required from other
governmental entities such as water management districts, state agencies, or federal agencies.
WARNING TO OWNER: YOUR FAILURE TO RECORD A NOTICE OF COMMENCEMENT MAY RESULT
IN YOUR PAYING TWICE FOR IMPROVEMENTS TO YOUR PROPERTY. A NOTICE OF
COMMENCEMENT MUST BE RECORDED AND POSTED ON THE JOB SITE BEFORE THE FIRST
INSPECTION. IF YOU INTEND TO OBTAIN FINANCING, CONSULT WITH YOUR LENDER OR AN
ATTORNEY BEFORE RECORDING YOUR NOTICE OF COMMENCEMENT.
MUST CALL INSPECTION PHONE LINE (904) 247-5814 BY 4 PM FOR NEXT DAY INSPECTION.
ALL WORK MUST CONFORM TO THE CURRENT 6TH EDITION (2017) OF THE FLORIDA BUILDING
CODE, NEC, IPMC, AND CITY OF ATLANTIC BEACH CODE OF ORDINANCES .
ALL CONDITIONS OF PERMIT APPLY, PLEASE READ CAREFULLY.
1 of 2Issued Date: 5/17/2023
PERMIT NUMBER
COMM23-0031
ISSUED: 5/17/2023
EXPIRES: 11/13/2023
COMMERCIAL PERMIT
CITY OF ATLANTIC BEACH
800 SEMINOLE ROAD
ATLANTIC BEACH, FL 32233
FEES
DESCRIPTION ACCOUNT QUANTITY PAID AMOUNT
BLDG 2ND PLAN REVIEW FEE 455-0000-322-1006 0 $50.00
BUILDING PERMIT 455-0000-322-1000 0 $420.00
BUILDING PLAN CHECK 455-0000-322-1001 0 $210.00
STATE DBPR SURCHARGE 455-0000-208-0700 0 $10.20
STATE DCA SURCHARGE 455-0000-208-0600 0 $6.80
TOTAL: $697.00
2 PUBLIC WORKS ON SITE RUNOFF INFORMATIONAL
Notes:
All runoff must remain on-site during construction.
3 PUBLIC WORKS DUMPSTERS/ROLL-OFF CONTAINERS INFORMATIONAL
Notes:
Dumpsters and roll-off containers must be used in compliance with Section 16-8 and must comply with all standards, per City code.
4 PUBLIC WORKS RIGHT OF WAY RESTORATION INFORMATIONAL
Notes:
Full right-of-way restoration, including sod, is required.
5 PUBLIC WORKS CONSTRUCTION SITE MANAGEMENT INFORMATIONAL
Notes:
Provide construction site management plan, including location of silt fence, dumpster, portable toilet. Right-of-Way Permit is required if using right-of-
way for construction parking.
6 PUBLIC WORKS GRASS INFORMATIONAL
Notes:
Full site to be grassed.
7 PUBLIC WORKS REVISION INFORMATIONAL
Notes:
Any plan change must be submitted as a Revision to the Building Department.
8 PUBLIC WORKS DEBRIS REMOVED INFORMATIONAL
Notes:
All construction debris must be removed from job site by Contractor.
9 PUBLIC WORKS INFRASTRUCTURE INFORMATIONAL
Notes:
Any damage done to infrastructure must be repaired by Contractor.
10 PUBLIC WORKS IMPERVIOUS AREA INFORMATIONAL
Notes:
No additional impervious square footage area can be added to this property.
Must match existing footprint.
2 of 2Issued Date: 5/17/2023
PERMIT NUMBER
COMM23-0031
ISSUED: 5/17/2023
EXPIRES: 11/13/2023
COMMERCIAL PERMIT
CITY OF ATLANTIC BEACH
800 SEMINOLE ROAD
ATLANTIC BEACH, FL 32233
Final Plumbing
Final Electrical
Final HVAC
CC Final
Final Building*
Swimming Pool Steel
Swimming Pool Safety
Electrical Grounding & Bonding
Swimming Pool Final (Bldg)
Swimming Pool Final (PW)
Formed Columns/ Beams*
Masonry Cell Fill
Structural Steel*
OTHER:
OTHER:
OTHER:
OTHER:
OTHER:
Power Pole
Silt Fence
Piers/ Stem Walls
Underground Plumbing
Underground Electric
Foundation/ Footing
Slab**
Retaining Wall Footing
Driveway
Sewer (Building Dept)
Sewer Tap (Utilities Dept)
Rough Electric*
Rough Plumbing/ Top Out*
Rough Mechanical*
House Wrap
Wall Sheathing
Roof Sheathing
Tie-down Framing Connections
Rough Framing
Roofing In Progress
Window/Door In-Progress
Insulation Ceiling
Insulation Wall
Exterior Lath
Stucco Scratch Coat
Exterior Siding In-Progress
Brick Flashing & Ties
Early Power
Gas Rough
Gas Final*
* When all rough electric, plumbing, mechanical are complete but before any work is
covered up.
* When all gas piping is complete and wallboard is installed but before gas is
attached to any appliance. All outlets must be capped and pipe pressurized at a
minimum of 15 lbs.
* For new living space: When all construction work including electrical, plumbing,
mechanical, exterior finish, grading, required paving and landscaping is complete
and the building is ready for occupancy, but before being occupied
Additional inspections may apply to your project if your project
contains these elements:
INSPECTIONS REQUIRED FOR BUILDING PERMITS
To verify compliance with building codes, inspections of the work authorized are required at various points of the construction.
The following inspections are typically required for residential projects:
Date: Initial: Date: Initial:
_____________________________________________________
Permit Type
____________________________________________________
Permit No.
__________________________________________________________
Job Address
____________________________________________________
Contractor
POST THIS CARD WITH PERMITS AND PERMIT
DOCUMENTATION IN FRONT OF BUILDING
Construction Hours per City Code: 7am—7pm Weekdays; 9am—7pm Weekends
Building Department Public Works/Utilities Fire Department
Phone: 904-247-5826 Phone: 904-247-5834 Phone: 904-630-4789
Fax: 904-247-5845 Fax: 904-247-5843 Fax: 904-630-4203
* When forms and reinforcing steel, anchor bolts, sleeves and inserts, and all
electrical, plumbing and mechanical work is in place, but before concrete is poured.
* When all structural steel members are in place and all connections are complete,
but before such work is covered or concealed.
** FORM BOARD ELEVATION CERTIFICATE MUST BE ON-SITE FOR SLAB INSPECTION
RESURFACE POOL, PAVER DECK OVER CONCRETE & SIGNAGE
2233 SEMINOLE RD
Pool Builder Services LLC
COMM23-0031
169519-0144
COMM23-0031
COMM23-0031