Item 4GAGENDA ITEM # 4G JANUARY 14, 2008 CITY OF ATLANTIC BEACH CITY COMMISSION MEETING STAFF REPORT AGENDA ITEM: Proposed Chan~e Order No. 4 to Ocean Blvd. Drainage Improvements Project (14~'-16 Streets) SUBMITTED BY: Rick Carper, P.E., Public Works Director DATE: January 2, 2008 BACKGROUND: At the September 10th meeting, the Commission awarded a contract to Walling Company for construction of Ocean Blvd. Drainage Improvements Project (PW0708) in the amount of $258,594.00 far the base bid and both additive alternates. Because bids for construction of the project came in under budget, staff proposed to add work to the project. This additional work consisted of milling and resurfacing Ocean Blvd. from the patch at 13th Street installed during last year's drainage upgrade project to the planned southern end of paving just south of 14th Street (about 350 feet). This additional paving removed the substantial bump on both sides of the patch, making Ocean Blvd from 13th Street to the northern end a single surface instead of unconnected patches. This segment of road had an Overall Condition Index of 43 and would have required resurfacing in the next year or two. Also included in this change order are additional upgrades /repairs to water systems in the project area. Total cost for Change Order No. 4 is $17,383.00. Previous Change Orders were under the $10,000 threshold and were approved by the City. Change Order No.1 added 5 new 2a services w/ corporation stops ($6,175.00), No. 2 added an 8° water valve and 31 LF of sanitary sewer replacement ($2,560.59), and No. 3 added an additional catch basin and mitered end section to the south end of the Seminole Ditch ($7,500.00). RECOMMENDATION: Authorize the City Manager to execute Change Order No. 4 to the Walling Company contract to add the additional paving on Ocean Blvd. The total conrtract price with this change order will be $292,212.59. BUDGET: This project is funded from the Stormwater Fund, Account No. 470-0000-538-6300 -with $310,800 allocated for construction of the Ocean Blvd. Drainage Improvements (PW0708). ATTACHMENT: (1) Proposed Change Order No. 4 REVIEWED BY CITY MANA~~: January 14"', 2008 Regular Meeting