BACKGROUND: The City's 2001 Water Master Plan included a
recommendation to replace Well No. 2, located at the Wastewater Treatment
Plant at 1100 Sandpiper Lane. Geophysical and video inspection in 2001 showed
the well to be in very poor condition.
Request for Proposals No. 0203-2 was issued in 2003 to complete site selection,
design and permitting of this well (We112R), and the top-ranked firm was CH2M
Hill.
CH2M Hill completed the design of the new well and associated pipe work in
2004. However, we asked the engineer to delay the permitting and construction
engineering work, as funding for the well's construction was not available.
Staff verbally negotiated with CH2M Hill to perform the permitting, bidding and
construction engineering work, but could not reach an agreement, as their
proposal was for approximately $100,000.
Therefore staff requested a proposal from the City's General Engineering
Consultant, Bowen Civil Engineering, the only one of the City's annual contract
engineers that included this type of work in their scope.
Staff has reached an agreement on the Scope of Services and Fee Proposal
attached to this staff report.
The Scope of Services includes preparing the permit applications for the Florida
Department of Environmental Protection (FDEP) and assisting with the permit
application for the St. Johns River Water Management District (SJRWMD). Also
included are bidding assistance, construction engineering and inspection services,
Certification of Construction Completion for FDEP, and the Construction Report
and Aquifer Performance Testing Report for SJRWMD. The fee proposal is
$41,775.
BUDGET: Funds for the construction of We112R, including these engineering
services, are budgeted in the Water Fund in the amount of $800,000 under
account number 480-0000-533-63-00.
AGENDA ITEM # 8A
MARCH 9, 2009
RECOMMENDATION: Staff recommends Commission approval of the Scope
of Services and Fee Proposal for Permitting, Bidding and Construction
Engineering Services for We112R in the amount of $41,775, and to authorize the
City Manager to sign the contract with Bowen Civil Engineering, Inc.
ATTACHMENTS: 1. Scope of Work for Permitting, Bidding and
Construction Engineering Services for We112R
2. Engineering Proposal for Permitting, Bidding and
Construction Services for We112R.
REVIEWED BY CITY
MANAGER:
2
AGENDA ITEM # 8A
MARCH 9, 2009
CITY OF ATLANTIC BEACH
NEW WELL 2R
PERMITTING, BIDDING AND CONSTRUCTION PHASE ENGINEERING
SCOPE OF WORK
I. PROJECT DESCRIPTION:
A. The project consists of permitting, construction engineering, and certification
of a new 16-inch diameter Floridan Aquifer well cased to approximately 490 feet
below land surface. Well will be constructed with open-hole construction to
approximately 900 feet below land surface. Design pumping rate of the well is 1,SOq
gallons per minute. Also included is approximately 9131inear feet of 16-inch
transmission main.
II. PERMITTING:
A. Engineer's responsibilities will include
1. Preparing and submitting the permit applications for construction of
the wellhead and transmission main to the Florida Department of
Environmental Protection (FDEP) as required. All permit application fees will
be paid by the City.
2. Draft and final APT testing plan submittal to the St Johns River Water
Management District (SJRWMD).
3. Assisting the contractor in securing the well construction permit as
necessary.
III. BIDDING AND CONSTRUCTION ENGINEERING
A. Coordinate bidding and award of the project. Engineer shall be
responsible for answering questions that may arise during the advertisement
period, attending the pre-bid meeting, and issuing addenda as needed. The
Owner shall be responsible for advertising the project in a local newspaper
and providing bid sets to prospective bidders via the Internet or paper
copies. The Owner shall maintain the plan holder list. After the bid opening,
the Engineer shall review the bids and provide the Owner with a
recommendation for award not more than five 5 working days after the bid
opening.
AGENDA ITEM # 8A
MARCH 9, 2009
B. Provide construction phase services including:
(1) Prepare Contract Documents
(2) Attend Preconstruction conference
(3) Review and process Shop Drawings and 0&M Manuals
(4) Review and process Pay requests
(5) Conduct regular site visits to review the work progress.
The City's Public Work Inspector will perform daily inspection
on the transmission main portion of the project.
(6) Provide oversight of construction of the well by the
hydro-geologist to include field inspections during drilling and
testing to assure compliance with the project technical
specifications. Hydro-geologist shall compile the
hydrogeologic report, construction and testing report on the
well. City will pay costs for all laboratory analyses required by
the SJRWMD.
(7) Answer Contractor or Owner questions
(8) Review Change Order requests and prepare Change
Order(s) if required
(9) Conduct Pre-final and final inspections and generate
punch lists
(10) Review As-built drawings and Record Drawings
obtained from contractor
(11) Certify project completion and prepare FDEP
Certification of Completion forms.
AGENDA ITEM # 8A
MARCH 9, 2009
sowl:~ Ctvl~. ;~v ~tN::l:~t~v ~, IPic,
8075 Gate Parkway W, Suite 204
Jacksonville, Florida 32216
Telephone: 904-737-0090
Fax: 904-737-0040
E-mail: cbeng~boweneng.com
February 27, 2009
Donna Kaluzniak, CEP
Utility Director
City of Atlantic Beach
1200 Sandpiper Lane
Atlantic Beach, FL 32233-4318
Re: Proposal for Engineering Services for the City of Atlantic Beach -Permitting, Bidding
Services and Construction Administration Services for New Well
Dear Ms. Kaluzniak:
Bowen Civil Engineering, Inc. (BCE) is pleased to submit our fee proposal to continue to
provide assistance to the city in the area of public works/utility projects. This project is
Permitting, Bidding and Construction Administration Services for a new well.
The project to be permitted, bid and constructed was designed by Ch2M Hill -Project #184483
dated October 2004. Bowen Civil Engineering, Inc will be performing the Permitting, Bidding
and Construction Administration Services for a new well designed by others and will not be
responsible for the design. All services will be based on the current plans and specifications
provided by the city.
The scope of work provided by the city is detailed below
Scope of Work
CITY OF ATLANTIC BEACH
NEW WELL 2R
PERMITTING AND CONSTRUCTION PHASE ENGINEERING
SCOPE OF WORK
PROJECT DESCRIPTION:
The project consists of permitting, construction engineering, and certification of a new 16-inch
diameter Floridan Aquifer well cased to approximately 490 feet below land surface. Well will be
constructed with open-hole construction to approximately 900 feet below land surface. Design
pumping rate of the well is 1,500 gallons per minute. Also included is approximately 913 linear
feet of 16-inch transmission main.
PERMITTING:
Engineer's responsibilities will include:
• Preparing and submitting the permit applications for construction of the wellhead and
transmission main to the Florida Department of Environmental Protection (FDEP) as
required. All permit application fees will be paid by the City.
Roadway & Drainage Environmental Permitting Land Development
Ms. Kaluzniak
February 27, 2009
Page 2
AGENDA ITEM # 8A
MARCH 9, 2009
Draft and final APT testing plan submittal to the St. Johns River Water Management
District (SJRWMD).
Assisting the contractor in securing the well construction permit as necessary.
BIDDING AND CONSTRUCTION ENGINEERING
Coordinate bidding and award of the project. Engineer shall be responsible for preparing bid
documents for prospective bidders, answering questions that may arise during the
advertisement period, attending the pre-bid meeting, and issuing addenda as needed. The
Owner shall be responsible for advertising the project in a local newspaper and providing bid
sets to prospective bidders via the Internet or paper copies. The Owner shall maintain the plan
holder list. After the bid opening, the Engineer shall review the bids and provide the Owner with
a recommendation for award not more than five 5 working days after the bid opening.
Provide construction phase services including:
• Incorporate contract documents prepared by CH2M Hill.
• Attend Preconstruction conference
• Review and process Shop Drawings and O&M Manuals
• Review and process Pay requests
• Conduct regular site visits to review the work progress. The City's Public Work Inspector
will perform daily inspection on the transmission main portion of the project.
• Provide oversight of construction of the well by the hydro-geologist to include field
inspections during drilling and testing to assure compliance with the project technical
specifications. Hydro-geologist shall compile the hydrogeologic report, construction and
testing report on the well. City will pay costs for all laboratory analyses required by the
SJRWMD.
• Answer Contractor or Owner questions
• Review Change Order requests and prepare Change Order(s) if required
• Conduct Pre-final and final inspections and generate punch lists
• Review As-built drawings and Record Drawings obtained from contractor
• Certify project completion and prepare FDEP Certification of Completion forms.
BCE and our sub consultants, J. Collins Engineering Associates, LLC and Douglas J. Hearn,
P.G. of Yovaish Engineering Sciences, Inc. will perform this work for the City.
Fee Proposal
The fee or the scope of work is $41,775.
If you have any questions about the fee proposal, please contact me at (904) 737-0090.
Sincerely,
Randy Do~lvni g
Vice President
Bowen Civil Engineerin ,Inc.
AGENDA ITEM # 8A
MARCH 9, 2009
MANHOUR & REIMBURSEABLES BREAKDOWN
February 12, 2009, Rev February 24, 2009
City of AtlauHc Beacb. Fi. _ WyMr w.u v......:.s:..- n:.,.,:_,. n_ ..___~
'-'' . ui~ Y~ ii3
LABOR COSTS
WORK BREAKD Man Hours/L,abor Rates
OWN
Hou Rate PM
S40.00 ENG
534.55 SEN ENG
$40.00 PG
530.91 DES/CAD
527.30 Clerical
513.00 TOTAL
Task I -Well Permitting
FDEP Permit
Draft 8 Final APT 1 6 2 0 0 I $340.30
Assist Well Drifter wMleli Construction Pe
it 1 0 2 50 0 1 $1,678.50
rm 0 0 1 2 0 0 $101.82
Task II -Well Bidding
Coordinate Bidding 8 Award
dress Contractor Questions 2 6 8 0 0 1 $620.30
Issue up to (2) Addendums 0 12 8 0 0 I $747.60
Review Bids 8 Prepare Recommend
ti 2 t6 8 0 0 1 $965.80
a
on 1 8 5 2 0 1 $591.22
Task III-Construction Administrati
S
i
on
erv
ces
Proparo Contract Documents
Attend Preconatruction coherence 1 8 6 4 2 4 $786.64
Shop Drawings Review 8 08M Manual 0 0 3 3 0 1 5225.73
s
Review and process Pa
re
uests 1 IS 6 12 0 1 $1,285.82
y
q
Conduct ate visits to roview the work
r l 4 10 4 0 1 $714.84
p
ogress
Oversight of well wnstruct
b
h
d
l
i
/E 1 8 24 8 0 1 $1,536.68
.
y
y
ro-geo
a
og
ngineer
Hydro-geologist com
ile the well & h
d
l t 0 I 85 0 1 $2,720.35
p
y
rogeo
ogic reports
Answer Contractor or Owner
uesti 0 0 1 18 0 1 $609.38
q
ons
Review 8 Praceas Chan
e Orders 1 2 8 2 0 1 $503,92
g
Conduct Pro-finai and final ins
ecti 1 2 4 4 0 4 $444.74
p
ons
Review Aa-built drawin
s obtained fi
t 0 0 6 6 0 I 5438.46
g
rm con
ractor
Certifications 8 Prepare FDEP Certa
ti
f C 1 3 3 4 0 1 5400.29
ca
on o
ompletion 1 3 3 4 0 1 5400.29
Totals
16 96 109 208 2 24 $15,112.68
Project Manager
Engineer
Senior Engineer
Professional Geologist/I-Iydrogeologist
Senior Designer/CAD Technician
Clerical 5640 ~
$3,316.80
$4,360.00
56,429.28
$54.60
$312.00
SUBTOTAL DIRECT LABOR COSTS
OVERHEAD at 2.5
PROFIT ON OH/DL - 10%
TOTAL LABOR FEE _+$15,112.68
$37,781.70
$3,778.17
541,559.87
REIMBURSABLE COSTS Quantity Unit Price
Mileage
Courier & Postage
Copying 300
1
250 MI
LS
SHTS 50.50
$40.00
$0.10 $150.00
$40.0p
$25.00
SUBTOTAL REIMBURSABLE COSTS 521500
TOTAL ENGINEERING COST S41,775