Loading...
Item 8IAGENDA ITEM # 8I NOVEMBER 23, 2009 STAFF REPORT City of Atlantic Beach Commission Meeting AGENDA ITEM: ArchitecturaVEngineering Contract for Police Building DATE: November 17, 2009 SUBMITTED BY: David E. Thompso~i, Asst City Manager BACKGROUND: Earlier this year, the City Commission approved the selection of Architect Design Group (ADG) to provide architectural services for the design of a new law enforcement building. City Commissioners had agreed that the existing public safety building was obsolete and inadequate, and the best course of action was for the City to pursue the design and construction of a new facility to house police operations. ADG was authorized to conduct an assessment relative to the amount of space needed in a new police facility for Atlantic Beach. ADG was also authorized to provide a minimum of three (3) concepts for the City Commission to review and consider for the new law enforcement building. The results of these initiatives will be presented at a workshop at 5:00 PM on Monday, November 23, 2009. Over the past month, City staff has been engaged in negotiations with ADG relative to providing a master plan and design for a new law enforcement facility. The proposed contract is approximately forty (40) pages in length, and it provides five (5) development options for the City Commission to consider. For the purpose of this staff report, only the five (5) pages that describe the development options are attached. The full proposed contract, which is in a standard AIA format, may be obtained from the City Clerk or on-line on the City website. Each of the five (5) options has a different estimated project cost associated with it. As expected, the larger buildings have higher costs. The standazd azchitecture and engineering fees are listed under #6 on each option. When the City Commission provides direction as to which option to pursue, then the contract will be finalized with the corresponding costs. BUDGET: A budget of $415,000 for this project is included in the General Capital Improvement fund of the current City budget. RECOMMENDATIONS: To select one of the proposed options, and to authorize staff to complete the necessary contractual agreement for ADG to proceed with the standard azchitect and engineering services for a new law enforcement facility. ATTACHMENTS: Development Options A, B, C, D, and E as proposed by ADG REVIEWED BY CITY MANAGER: ENDA ITEM NUMBER: AGENDA ITEM # 8I NOVEMBER 23, 2009 ATTACHMENT "E" Estimated Development Costs Atlantic Beach Police Department City of Atlantic Beach, Florida ADG Project No. 821-09 November 3, 2009 Development Option "A" 1. Building Cost to the Year 2015 on City Hall Campus 13,279 SF @ $235.00/SF .......................................................................... $ 3,120,565.00 2. Site Development Cost: 2.1 Parking/Paving 60 estimated need @ 100% surface parking 60 surface spaces @ $2,800/space ...................................... $ 168,000.00 2.2 Grading, Drainage, Landscaping, and Irrigation 1.2 acres @ $130,000/acre .................................................. $ 156,000.00 2.3 Site Security Enhancements (Planters/bollards, access control, site walls and fencing) Lump Sum (allowance) ....................................................... $ 20,000.00 2.4 Subtotal Site Development Cost ..................................................... $ 344,000.00 3. Telecommunications/Computer Access Allowance: 13,279 SF @ $5.50/SF .............................................................................. $ 73,035.00 4. Security Systems Allowance: (access control, CCTV, recording devices) 13,279 SF @ $5.00/SF .............................................................................. $ 66,395.00 5. Project Cost Subtotal (Construction) .................................................... $ 3,603,995.00' 6. Standard Architecture & Engineering Fees ......................................... $ 384,210.002 7. Furnishings Allowance: (furniture and moveable equipment) 13,279 SF @ $15.00/SF ............................................................................ $ 199,,185.00 8. Total Estimated Project Cost ................................................................. $ 4,187,390.003 ' This figure does not include any estimated costs associated with the potential demolition/renovation to the existing Public Safety Facility. s This figure does not include any fees associated with the potential demolition/renovation to the existing Public Safety Facility. s This figure does not include any costs associated with permitting, impact fees, or off-site work. H:\ADMINUOB\821\Contract\Phase Two\Current Attachments\Attachment E 1103.9.doc AGENDA ITEM # 81 NOVEMBER 23, 2009 ATTACHMENT "E" Estimated Development Costs Atlantic Beach Police Department City of Atlantic Beach, Florida ADG Project No. 821-09 Page 2 Development Option "B" 1. Building Cost to the Year 2015 on City Hall Campus w/ Shell Space for Year 2020 13,279 SF @ $235.00/SF .......................................................................... $ 3,120,565.00 1,071 SF @ $165.00/SF .......................................................................... $ 176,715.00 $ 3,297,280.00 2. Site Development Cost: 2.1 Parking/Paving 63 estimated need @ 100% surface parking 63 surface spaces @ $2,800/space ...................................... $ 176,400.00 2.2 Grading, Drainage, Landscaping, and Irrigation 1.3 acres @ $130,000/acre .................................................. $ 169,000.00 2.3 Site Security Enhancements (Planters bollards, access control, site walls and fencing) Lump Sum (allowance) ...................................................... $ 20,000.00 2.4 Subtotal Site Development Cost ..................................................... $ 365,400.00 3. Telecommunications/Computer Access Allowance: 13,279 SF @ $5.50/SF .............................................................................. $ 73,035.00 4. Security Systems Allowance: (access control, CCTV, recording devices) 13,279 SF @ $5.00/SF ............................................................................. $ 66,395.00 5. Project Cost Subtotal (Construction) .................................................... $ 3,802,110.004 6. Standard Architecture & Engineering Fees ......................................... $ 400,554.005 7. Furnishings Allowance: (furniture and moveable equipment) 13,279 SF @ $15.00/SF ............................................................................ $ 199,185.00 8. Total Estimated Project Cost ................................................................. $ 4,401,849.006 a This figure does not include any estimated costs associated with the potential demolition/renovation to the existing Public Safety Facility. s This figure does not include any fees associated with the potential demotition/renovation to the existing Public Safety Facility. e This figure does not include any costs associated with permitting, impact fees, or off-site work. H:\ADMINUOB\821\Contract\Phase Two\Current Attachments\Attachment E 1103.9.doc AGENDA ITEM # 81 NOVEMBER 23, 2009 ATTACHMENT "E" Estimated Development Costs Atlantic Beach Police Department City of Atlantic Beach, Florida ADG Project No. 821-09 Page 3 Development Option "C" 1. Building Cost to the Year 2020 on City Hall Campus 14,350 SF @ $235.00/SF .......................................................................... $ 3,372,250.00 2. Site Development Cost: 2.1 Parking/Paving 63 estimated need @ 100% surface parking 63 surface spaces @ $2,800/space ...................................... $ 176,400.00 2.2 Grading, Drainage, Landscaping, and Irrigation 1.3 acres @ $130,000/acre .................................................. $ 169,000.00 2.3 Site Security Enhancements (Planters/bollards, access control, site walls and fencing) Lump Sum (allowance) ....................................................... $ 20,000.00 2.4 Subtotal Site Development Cost ..................................................... $ 365,400.00 3. Telecommunications/Computer Access Allowance: 14,350 SF @ $5.50/SF .............................................................................. $ 78,925.00 4. Security Systems Allowance: (access control, CCTV, recording devices) 14,350 SF @ $5.00/SF .............................................................................. $ 71,750.00 5. Project Cost Subtotal (Construction) .................................................... $ 3,888,325.00 6. Standard Architecture & Engineering Fees ......................................... $ 407,667.008 7. Furnishings Allowance: (furniture and moveable equipment) 14,350 SF @ $15.00/SF ............................................................................ $ 215.250.00 8. Total Estimated Project Cost ................................................................. $ 4,511,242.009 ' This figure does not include any estimated costs associated with the potential demolition/renovation to the existing Public Safety Facility. s This figure does not include any fees associated with the potential demolitionlrenovation to the existing Public Safety Facility. 9 This figure does not include any costs associated with permitting, impact fees, or off-site work. H:WDMINVOB\821\Contrdct\Phase Two\Current AttachmentsWttachment E 1103.9.doc AGENDA ITEM Ik 8I NOVEMBER 23, 2009 ATTACHMENT "E" Estimated Development Costs Atlantic Beach Police Department City of Atlantic Beach, Florida ADG Project No. 821-09 Page four Development Option "D" 1. Building Cost to the Year 2015 on Off-Site Property (TBD) 15,092 SF @ $235.00/SF .......................................................................... $ 3,546,620.00 2. Site Development Cost: 2.1 Parking/Paving 40 estimated need @ 100% surface parking 40 surface spaces @ $2,800/space ...................................... $ 112,000.00 2.2 Grading, Drainage, Landscaping, and Irrigation 1.2 acres @ $130,000/acre .................................................. $ 156,000.00 2.3 Site Security Enhancements (Planters/bollards, access control, site walls and fencing) Lump Sum (allowance) ....................................................... $ 20,000.00 2.4 Subtotal Site Development Cost ..................................................... $ 288,000.00 3. Telecommunications/Computer Access 15,092 SF @ $5.50/SF .............................................................................. $ 83,006.00 4. Security Systems (access control, CCTV, recording devices) 15,092 SF @ $5.00/SF ............................................................................. $ 75.460.00 5. Project Cost Subtotal (Construction) .................................................... $ 3,993,086.00 6. Standard Architecture & Engineering Fees ......................................... $ 416,305.0010 7. Furnishings Allowance: (furniture and moveable equipment) 15,092 SF @ $15.00/SF ............................................................................ $ 226.380.00 8. Total Estimated Project Cost ................................................................. $ 4,635,771.00" to This figure does not include any fees associated with the potential demolition/renovation to the existing Public Safety Facility. " This figure does not include any of the following potential development costs: land acquisition, utility improvements or extensions, permitting, impact fees, flood mitigation, or off-site work. H:\ADMINUOB\821\Contract\Phase Two\Cunent AttachmentsWttachment E 1103.9.doc AGENDA ITEM # 81 NOVEMBER 23, 2009 ATTACHMENT "E" Estimated Development Costs Atlantic Beach Police Department City of Atlantic Beach, Florida ADG Project No. 821-09 Page five Development Oation "E" 1. Building Cost to the Year 2020 on Off-Site Property (TBD) 16,163 SF @ $235.00/SF .......................................................................... $ 3 798,305.00 2. Site Development Cost: 2.1 Parking/Paving 40 estimated need @ 100% surface parking 40 surface spaces @ $2,800/space ...................................... $ 112,000.00 2.2 Grading, Drainage, Landscaping, and Irrigation 1.2 acres @ $130,000/acre .................................................. $ 156,000.00 2.3 Site Security Enhancements (Planters/bollards, access control, site walls and fencing) Lump Sum (allowance) ....................................................... $ 20.000.00 2.4 Subtotal Site Development Cost ..................................................... $ 288,000.00 3. Telecommunications/Computer Access 16,163 SF @ $5.50/SF .............................................................................. $ 88,897.00 4. Security Systems (access control, CCTV, recording devices) 16,163 SF @ $5.00/SF .............................................................................. $ 80.815.00 5. Project Cost Subtotal (Construction) .................................................... $ 4,256,017.00 6. Standard Architecture & Engineering Fees ......................................... $ 438,001.OOlz 7. Furnishings Allowance: (furniture and moveable equipment) 16,163 SF @ $15.00/SF ............................................................................ $ 242,445.00 8. Total Estimated Project Cost ................................................................. $ 4,936,463.0013 12 This figure does not include any fees associated with the potential demolition/renovation to the existing Public Safety Facility. 13 This figure does not include any of the following potential development costs: land acquisition, utility improvements or extensions, permitting, impact fees, flood mitigation, or off-site work. H:\ADMINUOB\821\Contract\Phase Two\Current AttachmentsWttachment E 1103.9.doc