Loading...
Item 10B AGENDA ITEM # 10B OCTOBER 25, 2010 CITY OF ATLANTIC BEACH CITY COMMISSION MEETING TMDL COST ESTIMATE REPORT AGENDA ITEM: Request for current, complete and accurate cost estimates and report for the TMDL project prior to bid submittal and issuing a notice to proceed. SUBMITTED BY: Carolyn Woods, Commissioner DATE: October 25, 2010 BEST PRACTICE: The need for updating and providing current accurate and complete cost estimates is summed up very well in this excerpt. "Cost estimating is one of the most important steps in project management. A cost estimate establishes the base line of the project cost at different stages of development of the project. Generally, the accuracy of a cost estimate will reflect the information available at the time of estimation." http://pmbook.ce.cmu.edu/ Chris Hendrickson, Department of Civil and Environmental Engineering, Carnegie Mellon University, Pittsburgh, PA 15213 Copyright C. Hendrickson 1998. BACKGROUND: The Atlantic Beach TMDL Project has been ongoing since 2004 when the State of Florida announced it would be implementing Total Maximum Daily Loads, TMDL, of nitrogen that would be permitted to be pumped into the St. Johns River by, among others, municipal utilities. The City initiated a study which was completed by ATM, Inc. This report tried to identify the City's needs, ability and anticipate costs to meet the State - mandated TMDL requirements. The assumptions, recommendations and cost analysis reports were based on the current information at the time. The 2006 ATM report was followed by a more comprehensive report done jointly by HDR, Inc. and John Collins Engineering (JCEA) and presented in December 2008. The old data used in the ATM report was reexamined, new data was reviewed, the equipment and infrastructure abilities further scrutinized, new assumptions were made, the costs were expanded and refined, and ultimately new cost estimates and recommendations were made that should have been based on a synthesis of new and old information. Once again 2 years have passed and there has naturally been new data come to light, equipment has been bid and chosen, existing infrastructure limitations exposed, past assumptions have been challenged, and future costs have been exposed and unaccounted for. In short, important information has not been incorporated into the working plan and new and future costs were not included in the initial working cost estimate which served as the basis for all decisions made for this project. 1 of 3 AGENDA ITEM # 10B OCTOBER 25, 2010 INCOMPLETE COST ANALYSIS LEADS TO WRONG ASSUMPTIONS W WTP #a Flows to W WTP #1 Transmission Alternatives - New Pipe TABLE 9.1 Known Costs that were not included * Transmission Alternatives - New Pipe Route Rank Alternative Rank Low to Flow Shed Year 10 Low to Number Cost High (piping) construction Cost High 1 $3,609,000 7 $690,000 $291,000 $4,299,000 7 $3,3 6 $690,000 $291,000 $4,010,000 6 1 Revision 1 $2,777,000 1 $690,000 $291,000 $3,758,000 4 1B $3,283,000 5 $690,000 $3,758,000 5 1B Revision 1 $2,820,000 2 $690,000 $291,000 $4,663,000 8 1C $2,915,000 3 $690,000 $291,000 $4,491,000 10 2 $3,7 9 $3,723,000 3 3 $3,680,000 8 $3,680,000 2 3 (Directional Drill) $4,514,000 10 $4,5 9 4 $3,003,000 4 *3,003,000 1 *Note -t. Capitol Costs are for New Pipeline Construction only - no costs included for pumping. 2. From HDR(JCEC 2008 report This updated chart shows that had these known costs been included in the evaluation at the I beginning of the project, all the routes that went to the west of Mayport Rd. through Hanna Park and west of Oceanwalk would have been eliminated from further consideration. This Commission has a moral and fiscal responsibility to insure this project is the best plan and the right plan for the long -term future to meet the state mandated requirements. This can only be done by allowing the data to drive the development decisions. A decision based on accurate cost estimates is the cornerstone of meeting these fiscal and management responsibilities. OTHER FINDINGS: Through the process of designing a route through Hanna Park, as problems arose to threaten the viability of this route, the decision was made to postpone, until year 10, facing those issues. Of primarily concern are tree mitigation in Hanna Park and easement acquisition along 5,300 feet of pipeline and an ongoing lawsuit concerning another 1,950'. These issues would be irrelevant had the correct decision been made at the beginning of the process. That decision should have been to not run the pipes to the east of Mayport Rd. because of cost. INCOMPLETE COST ESTIMATE: Now we have reached a stage where documents are being prepared to send this project out to bid. As discussed, it is best management practice to update and evaluate cost estimates as a project progresses, primarily to control costs. Because the Commission is charged with the financial responsibility of the City's funds it is necessary that all of these 2 of 3 AGENDA ITEM # 10B OCTOBER 25, 2010 issues and the resulting costs be accounted for in the cost estimates for this project provided to the Commission. When asked to provide a detailed cost estimate the City Manager submitted the following. Current Cost Estimate provided by City Manager on October 1, 2010: Water and Wastewater Financing Engineering Buccaneer Phase out $326,435 Main Plant $566,125 Construction Services $460,000 Construction of Buccaneer line, other misc. $3,500,000 Construction of main plant upgrades $6,169,000 Water main; Ocean $150,331 Lift Station upgrades $342,000 Replace Well #1 $752,456 Total Cost $12,266,347 Ball park estimates are not appropriate to base decisions on for appropriation of funds. It is not too late to correct these wrongs and make an appropriately informed decision. BUDGET: Based on updated Table 1 potential savings start at $760,000. RECOMMENDATION: Direct staff to prepare a detailed explanation for these cost discrepancies and generate a new current, complete and accurate cost estimate for the TMDL project, including previously dismissed routes, that compares all relevant costs, not selected costs, so the comparison will be as "apples to apples ", for the Commission's review and consideration at the next Commission meeting and prior to bid submittal and issuing a notice to proceed. 3 of 3 r 't BEACH HOV38 ., - H w BEACH W EAI'l a OCEAN GROVE - z - OC _ AUCIA F BEACH3IDE EA ST COAST d z m l- r _..__ SEMINOLE .. --._ °' m - I $EA OATS SELVA MARINA e ONDEWp00 O IDOLERS i SEA OATS 1 P ARK & a m g s`. W O0MN �" S IVO 3S 0 i K 30113A VAN31 O PARK � Sµ - 3BWO 2 RK 444 PIONEER I 0 30NVN0 55-135 PP r 10033LVB m NV. OR E LV AM ARt NP V.LSIA VNOO HICKORY j MVO 3AIT g S pARK 510E CaSNA 153ZIOjNV30p 3J210N Vl3A NORT SHERRY 4 HICKORY �� __ > ' • it SANDPIPER O E ND1NG LWK SIDE $ANDPtPE SAILFISH J FI.E T y �' /� 5 ____ _.... JORDAN W L .ONOf Q 0 m Z-. 7Z) J (.9 w - FRANCIS m S w DEFENDER S � w ok, m W 7 r' w ARGO o o VD3A S � do m :1 z f SKATE �I 4iRMAYJ I L .E m o DdAtlW 1,09a V O 1MU . 3011 ANDRE� y NN3A JACOB y f J 1 N m t. U GEORGE w ▪ ,13 Fi m PARK .,. N, P O m .t pY N CECIL 3 N30NV3Tp 9 �' < qp = o a ILLUSION w JT' ly y ROSE S ? YO 4' PALM LANDING ALLEY 3{, MEALY SHAN - - z MEALY q VIOLET 04,0,v0 'JI CYPRESS LANDING ,....-, ,---------.. 1 HIBISCUS w FANTASY BLA w CP8 D MN3Hltl3d SALLAS STOCK$ STOCKS a - SUNKER HILL ' q$PE N RIDGE �, SPOKANE O a o MAIN a' L X „ w CONCORD i CAMELIA CAMELIA iX30MV�N y 3 3 MONTREAL O CONSTITUTION i Z 0 C '2' JASMINE JASMINE 5 o . a m 8 H m j , AN/MAYS '� N BEGONIA 5< v o F N 2 U N P ARADISE LAUREL TULIP E d_ o * - ti - I U ¢ Q S W 0. e.e ..0 . = (J P CARNATION m E;-.2 .5 z H m S U Hln by k w y & < m m U 2 Q OWNOW NIdT M3IAHSNYR ¢ z O w dSV/H VOW 51010510 ON3 1S3 n a`I K 1 a K g O d V SEAWAY .04,6,04, .04,6,04, STEP h1 y iP