Agenda Item 8CAGENDA ITEM # 8C SEPTEMBER 26, 2011 CITY OF ATLANTIC BEACH CITY COMMISSION MEETING STAFF REPORT AGENDA ITEM: Change Order No.I for Bid 10 11- 16 Contract Time Extension SUBMITTED BY: Donna Kaluzniak, CEP, Utility Director DATE: September 2, 2011 BACKGROUND: The contract awarded to WPC Industrial Contractors, LLC for completing the Sludge and Odor Control project at WWTP #1 included a 270 -day timeframe to substantially complete the project. Based upon the contractor's discussions with the major sludge treatment equipment manufacturer, the equipment delivery schedule will delay the project completion by approximately 2 months. In the current economy, many equipment suppliers are not keeping parts and equipment in stock, but awaiting confirmed orders before they begin to manufacture items. Staff has experienced similar delays in other projects and in replacing plant and lift station equipment recently. The contractor is not requesting additional funds, only time. The time extension will affect the construction engineering and inspection (CE &I) contract with our engineer, J. Collins Engineering Associates, LLC (JCEA). JCEA has agreed to waive the engineers' additional time for construction administration, but is requesting additional funds to cover the cost of the onsite inspector's time. JCEA also reduced by half the profit and overhead that was included in their contract, making the total additional costs $21,015.60 for the two months of additional inspection. BUDGET: Funds are available for the additional engineering costs under account number 410- 5508- 535 -63 -00 due to the TMDL projects coming in under budget. RECOMMENDATION: Authorize the City Manager to execute Change Order No. 1 for WPC Industrial Contractors, LLC for additional time at no added costs. Approve additional funds for J. Collins Engineering Associates, LLC for onsite inspection in the amount of $21,015.60. ATTACHMENTS: 1. Change Order No. 1 2. Fee Proposal from JCEA for Extended Construction Administration and Inspection Services. REVIEWED BY CITY MANAGER: Fi A Mam 7 - i kbd i I r I 12 wf M 6 ' f . 'v . 7, .-- lL'—L*Tp.. W • Imp I AE6� �;! i kl "C ". Zq i.: W. Ing in p"I I ' r u TIM T T. ko i . . Z r; n=4 I IL AL ZVI F)l Z2" ILI, AGENDA ITEM # 8C SEPTEMBER 26, 2011 Page 2 of 2 D. Kaluzniak —City of Atlantic Beach September 2, 2011 If you have any question, please contact me at the office. Very truly yours, John E. Collins, Jr PE Project Manager J. Collins Engineering Associates, LLC ��. w A . � rt