AGENDA ITEM #3C
APRIL 12, 2004
CITY OF ATLANTIC BEACH
CITY COMMISSION MEETING
STAFF REPORT
AGENDA ITEM: Additional Brick in Town Center Project
SUBMITTED BY: Donna Kaluzniak, Utility Director
DATE: Apri15, 2004
BACKGROUND: The Town Center Project was originally designed by R. Glen Mitchell &
Associates, Inc. in 1999, and the portion from Atlantic Boulevard to Ahern Street constructed
~, and paid for by the City of Jacksonville. The City of Atlantic Beach approved funding for the
remainder of the project for last fiscal year, and the construction of the area from Ahern Street to
15` Street recently completed. The original design for the project was used for this construction.
During a recent Commission meeting a request was made to investigate the possibility of adding
some brick accent to match the first block of Town Center. Staff determined some potential areas
for brick accent and obtained estimated costs for the work. The potential areas include:
Item Cost
Brick around electric ole on east side $ 200
Brick stri alon west side $ 6,444
Brick around BellSouth box $ 320
Brick ed es of lanted areas $ 2,000
Remove sidewalk & re lace with brick east side $11,000
Remove sidewalk & re lace with brick west side $11,000
BUDGET: No contingency funds are left in this project, and there are no monies currently
available in other accounts for this work. Funding would have to be approved as part of the mid-
year budget modification process.
RECOMMENDATION: City Commission to provide direction to staff with regards to
additional brick work in Town Center.
ATTACHMENTS:
REVIEWED BY CITY MANAGER:
~-