CITY OF ATLANTIC BEACH
~„ CITY COMMISSION MEETING
STAFF REPORT
AGENDA ITEM # 4G
NOVEMBER ]3, 2006
AGENDA ITEM: Oaks of Atlantic Beach Extension -Acceptance of Water and Sewer
Infrastructure far City Ownership and Maintenance
SUBMITTED BY: Donna Kaluzniak, Utility Director
DATE: October 30, 2006
BACKGROUND: Construction on the infrastructure for an extension of the Oaks of Atlantic
Beach Mobile Home Park has been completed by the owner's contractor. This subdivision consists
`~"' of 31 mobile home lots located in the City of Jacksonville off Pioneer Drive.
The contractor completed construction in accordance with approved plans. City staff completed a
final inspection, and the Department of Environmental Protection has cleared the water and sewer
systems for service.
BUDGET: No immediate impact to operating budget. The attached estimated schedule of values
will be added to the City's assets.
RECOMMENDATION: Accept the water and sewer infrastructure in the Oaks of Atlantic Beach
extension for ownership and maintenance by the City of Atlantic Beach.
ATTACHMENTS: 1. Schedule of Values for Oaks of Atlantic Beach extension.
REVIEWED BY CITY MANAGER:
..
~.
AGENDA ITEM # 4 G
NOVEMBER 13, 2006
ss
~~
j j~~J J~j~jry~~/t
~~~ILJLi1~~VC-1~i1 :Vlikc Vallen~ourt frank Vallencaurt F. E. Vallencourt
president Vice-President 5eniar Vice~presidcnr
Cdtritniotloti Cep. Its.
fifty Y~ctrs of 5tn~ic~t• to ~~rtheu.,t I`luriclu
~.
City of Atlantic Beach Thursday, August 24, 2006
~. 1200 Sandpiper Lane
Atlantic Beach, FL 32233
Phone: 904-247-5834
_ Fax:904-247-5843
Re: Schedule of Values for the Oaks of Atlantic MHP project
Watermain Quantity unit Unit Cost Total Cost
~. 8" DR25 PVC Water Main 1226 LF $ 14.75 $ 18,083.50
6" DR25 PVC Water Main 40 LF $ 13.00 $ 520.00
8" Joint Restraints 36 EA $ 120.00 $ 4,320.00
8"x8" Tap Slv. and Valve 2 EA $ 3,198.95 $ 6,397.90
8" Gate Valve 2 EA $ 862.00 $ 1,724.00
6" Gate Valve 3 EA $ 580.51 $ 1,741.53
Sample Point 4 EA $ 201.00 $ 804.00
'~" Valve Box 5 EA $ 160.00 $ 800.00
Flushing Hydrant 2 EA $ 508.00 $ 1,016.00
Fire Hydrant 3 F~ $ 1,527.00 $ 4,581.00
8 x 6" Tee 3 EA $ 375.00 $ 1,125.00
8" 45 Bend 2 EA $ 286.00 $ 572.00
8" Cap 2 F~4 $ 160.00 $ 320.00
1" Single Water Service 32 EA $ 373.83 $ 11,962.56
'"~` Punch Out Water 1 LS $ 3,852.00 $ 3,852.00
Pressure Test 2366 LF $ 1.53 $ 3,619.98
Water Main Total $ 61,439.47
Sanitary Sewer Main
Tie in to existing sewer system 1 ea $ 850.00 $ 850.00
Type A Manhole 6-8' deep 9 EA $ 2,451.00 $ 22,059.00
8" SDR 26 Sewer Main 4-6' Deep 387 LF 22.03 $ 8,525.61
10" SDR 26 Sewer Main 4-6' Deep 834 LF 26.75 $ 22,309.50
6" Cleanouts 32 FA 170.48 $ 5,455.36
Sewer Services 32 EA 550.18 ~ 17,605.76
N Test Sewer Main 1221 LF $ 3.33 $ 4,065.93
Sanitary Sewer Main Total $ 80,871.16
~
Prepared By:
~.
/~a~us /~e~aaraa~
Marcus Mclnarnay -Project Manager