PROJECT DESCRIPTION PROJECT NO.AND INFORMATION STATUS ON 11/19/12
1 TMDL Wastewater Project (D)=J. Collins Engineering Assoc. Substantial completion inspection held on 11/19/12.
Forcemain Construction = 100% (VE)=ATM Contractor finishing punch list items.
WWTP#1 Construction =100% (C)=TB Landmark(Forcemain)
Sludge & Odor Control =100% WPC Industrial Contractors(WWTP and
Sludge&Odor Control)
(CE&I)=J. Collins Engineering Assoc.
2 FY 12 Water Main Project (D)=Bowen Civil Engineers Bids received 5/2/12. Commission awarded entire project to
Design = 100% (Survey)=L.D. Bradley Gruhn May, contingent upon approving Budget Modification
Construction =90% (C)=Gruhn May Ordinance,approved 6/25/12. Preconstruction meeting held
(CE&I)=Public Utilities 7/9/12. Completed replacement of water main on 12th St.
from Ocean Blvd. to Beach Ave., 15th St.,and Ocean Blvd.
from 14th to 16th St. Contractor replacing services.
3 FY 13 Sewer Rehabilitation (D)=Public Utilities Contracts awarded by Commission on 11/13/12.
Project (C)=Insituform, CCI, Gruhn May
Design=100% (CE&I)=Public Utilities/PW
Construction = 0%
4
Donner Park Community Development Grant Projects
a. New lighting for basketball (C)=Limbaugh Electric Complete
courts
b. Security lighting for Donner (C)=Limbaugh Electric Complete
Community Center
c. Grade and sod baseball field Complete C z
d. Top Grade southern end Complete -
of soccer field p
N �
(D)=ATM o
e. Add paved parking (C)=ACD Marine d/b/a Complete N a
A&E General Contractors