Item 8BAGENDA ITEM: SUBMITTED BY: DATE: BACKGROUND: CITY OF ATlANTIC BEACH CITY COMMISSION MEETING STAFF REPORT AGENDA ITEM # 8B JANUARY 12, 2015 Seminole Road Drainage lmp?Jments Douglas E. layton, P.E. M_( f ~ L __ . Public Works Director u J December 29, 2014 Seminole Road is budgeted to be reconstructed from Atlantic Blvd to 5 points. Features desired in the project were stormwater, water and streetscaping improvements. Genesis was selected as the design firm and the Commission awarded a design contract to them early in 2014. On September 30, 2014 a neighborhood meeting was held to obtain input from the public on the conceptual design. Approximately 30% of the neighborhood attended the 9/30 meeting. On October 13, 2014, the Commission discussed some of the design features contained in the conceptual design. Public Works was asked to hold the design at the conceptual stage and come back to the Commission with more illustrative graphics and further consideration of design options. The presentation accompanying this report is in response to the Commission request of 10/13/14 and contains additional graphics and a list of design options with recommendation for each option. These documents are provided for discussion by the Commission BUDGET: $1,600,000 is contained in the FY'15 budget for these improvements. RECOMMENDATION: Obtain a consensus of the Commission to move forward with design of the project utilizing the recommended design options. ATTACHMENTS: Graphics and Design option ' REVIEWED BY CITY MANAGER: ·--;?r, V~ / U-=u Seminole Road-View Looking North 11.18.2014 Seminole Road-View looking North-With Parking -WI Oak Tree "" 11.18.2014 Seminole Road-View Looking North-With Parking I Miami Curb-WI Oak Tree 11.18.2014 Seminole Road -View Looking North-No Parking .--v --11 CABBAGE PALM LIRIOPE I BULBINE I AGAPANTHUS DWARFFAKAHATCHEE I SAND CORD GRASS I MUHL Y GRASS DWARFFAKAHATCHEE /SAND CORDGRASS I MUHLY GRASS ORNAMENTAL PEANUT I ASIATIC JASMINE MUSCOGEE CRAPE MYRTLE SAGO PALM ORNAMENTAL PEANUT I ASIATIC JASMINE LIRIOPE I BULBI E I SHORE JUNIPE T AS RED FLAX L1 Y ' . / --------------------------------~ --------------------------------I~, T I ,~0 ~r B'"GlE N E ;.~ ... __ ,.. _____ ...__ ...... ~-IKJ'ID,J'I· ...... .... ~ . ..._. ~- -'\) ~<'I ? ~ u·~ A>~ --0 ·~ ~ ~ 0 PLANT MATERIAL OPTIONS FOR SEMINOLE ROAD Native Grasses Muhly Grass Dwarf Fakahatchee Grass Evergreen paspalum grass Sand Cord Grass Flowering G round Cov er Bulbin e Sh o r e Juniper Liriope Tasred Flax Lily Ground Cover Ornamental Peanut Asiatic Jasmine Flowering Understory Tree Muskogee Crape Myrtle Seminole Road Conceptual Streetscape 00.18.14 Des91Sectioo I aG.. PH. s .. ~ s Jl l~t=r.Q" Cio'.DICIDI:' W ~-..o City of Atlantic Beach Seminole Road Improvements Feature Options Recommended Current Design Pro Con PWComment Project Build No Build Commission level Decision Replacement of aged storm Cost. Neighborhood concerns Old water & storm piping replacement, nusiance &water Piping. Beautification. flooding, beautify City entrance Reduce nusiance flooding Stormwater Treatment Bios wales Build Large Pond Bioswales Landscaping allowed in bioswales Pond reduce park space Stormwater treatment required by SJRWMD if road reconstructed Curbing Standard Miami Standard Protects swales. Extends S point Concern expressed about appearance of standard curb. Standard curb important to reduce swale look Reduces ability to park on swales/grass maintenance Parking Minimize Eliminate Minimized Allows current use. Beautifies and Neighborhood concern. Odinance currently prohibits. Reduced to S spaces per block to balance organizes parking. Replaces Enforcement issues. Concern about opening door into traffic current use and neighborhood concern. Plus parking eliminated by ped path additional parking at Russell/Howell Park. Some residents in favor. Parking width is 9-1/2'. Midsize car is 6' wide Swale Landscaping Plantings Grass Plantings Plantings improve beautfication Grass reduces maintenance and increases ability to park Plantings will increase maintenance budget approx $8,500/yr 8' Ped Path -West side Construct Replace existing 4' 8' ped path Improved path use & safety. Loss of 4' driveway parking on west side & greenspace 8" ped path in this location meets an unfunded sidewalk w/ 4' or 6' Reduced cost portion of the safe path to school plan 4" Raised Crosswalks Construct Eliminate Construct Increased safety. Speed reduction "Bumpy" traffic calming on through road Included for pedestrian safety and traffic calming Irrigation Construct Native Species Native Species Will help maintain landscaping Cost. Water usage Not in current project budget. Approx $30K appearance and allow non-native initial cost. species Bike Path Construct Not Construct Not Construct Allows on street bike traffic Increases road width 8'. Loss of "yard.11 & greenspace. Ped path allows biking by casual bikers. Increased cost about $30K. Serious bikers currently use East Coast. Not in current budget. treet Lights Construct Not Construct Design Neighborhood desired. Safety Current cost estimate is $240 Street lights for ped path are currently being enhancement designed. Plan is to minimize cost and bid as alternate for funding decision at award. SZ40K current estimate Tree Islands-minimum 12' Construct Not Construct Not Construct Ability in include Oaks in project. Concern with safety and driveway access. Loss of "yard." Not 3 potential locations identified. Not currently in W x 70' length Lighted tree would beautify in budget design. Adds desirable City entrance feature near Atlantic Wider Driveways Widen Replace existing Replace existing Minimize parking loss due to Not in budget 10' x 2Z' is approximately $1,600 per widened increased s/w width drive to r/w. Resident would have additional cost. 3'x 3' Driveway Cart Pads Construct Not Construct Construct Minimal cost Ususual This is an unusual, low cost feature to assist citizens access driveways on trash days