Item 3A - Saltair Drainage & Sidewalk ImprovementsAGENDA ITEM: CITY OF ATLANTIC BEACH CITY COMMISSION MEETING STAFF REPORT Saltair Drainage and Sidewalk Improvem ents AGENDA ITEM #3A MARCH 9,2015 SUBMITTED BY: Douglas E. Layton , PE ~ (. e' .CJ Public Works Director ~ C c::::;;,.t:.) l._ __ _ DATE: February 9, 2 015 BACKGROUND: 4 bids for the Saltair project were received on 1/20/15. The base bids ranged from $375,540.50 to $952,930 , excluding co ntingency . The base bid includes drainage improvements along Magnolia Street (from Sturdivant to David) and Poinsettia Street (from Sturdivant to Seaspray) and s idewalk improvem ents along Sturdivant (from Magnolia to Sherry). BUDGET: $380,000 including contingency RECOMMENDATION: Approve the award of th e subject project at the budget amount of $380,000 including $4,459.50 in contingency. ATTACHMENTS: Project Bid Tabulation City of Atlantic Beach Salt Air Drainage Improvements January 23, 2015 BID 1415-02 Callaway Contracting, Inc. G&H Underground J.B. Coxwell Miranda Contracting Required Documents Submission in Triplicate (All Documents) X X X X Document Requirements Checklist X X X X Bid Form X X X X Bid Bond (5% of bid) X X X X Drug Free Workplace X X X X Public Entity Crimes Statement X X X X W-9 Form X X X X Proof of Experience (5 years) Included with Prequal Pkg Included with Prequal Pkg Included with Prequal Pkg Included with Prequal Pkg Trench Safety Affidavit X X X X New Vendor Information Form X X X X Documentation of Receipt of Any Addenda/Updates 1. Regarding Requirements X X X X 2. Bid Bond X X X X 3. Revised Bid Form X X X X Other: Q & A, Revised Pre-bid Minutes lump Sum Bid Plus 10% Contingency (1-29) $589,973.84 $413,094.55 $1,048,223.00 $499,081.00 Deductive Alternate A-Paving & Drainage David Street(+ 10%) $73,851.60 $62,922.75 $73,436.00 $48,511.65 Deductive Alternate B-Paving & Drainage Sylvan Drive (+ 10%) $73,896.63 $50,352.50 $65,958.20 $44,841.50 Award of Bid based on Department Analysis and Commission Approval