Item 4A Public Works Project Status ReportCity of Atlantic Beach
Major Public Works Projects
FY14/15 -Status 9/28/15
Project Name Project No. FY15 Budget Project Activity Notes
Utilities
Reclaimed Water Facility PU0805 $135,399 Project complete
In line Valve Installation PU1404 $36,515 Complete
Design complete. DEP & ACOE permits
PU1408 & received. Awaiting permit from Coast PU 1408-Design/Perm itting,
Effluent Outfall Replacement PU1504 $331,625 Guard -Work joint for 3 Beach Cities PU1504-Construction
Connect Water Main across AlA to
Mallard Cove PU1410 $126,662 Project complete Final inspection 6/17
Update Water Models PU1502 $30,000 Consultant putting system into model
Project delayed. Will complete modeling
Well Logging PU1501 $30,000 project first In FY 15/16 Budget
Replace Water Main on Seminole Rd. Design underway-part of Seminole Road
From Atlantic Blvd. to S-Way PU1503 $700,000 Streetscape project Design 95% complete
Lining of wetwell at Mimosa Cove lift
station PU1505 $19,505 Complete
Lining of wetwell at Fairway Villas lift
station PU1506 $20,341 Complete
Clean & Televise Gravity Outfall to
ICW PU1507 $15,218 75% Complete
Fence/Wall at WWTP PU1508 $80,000 Bids received on 7/15 were over budget. Researching
Replace irrigation system with reuse
system at WWTP PU1509 $20,000 Performing with City forces. 75% complete
Parks Projects
Russell Tennis Courts 1&2 PM1401 $98,136 Complete
Swale savings allowed the following in this
year budget.
1. Fencing awarded 7/13. Wooden fence
near completion. Backstops after Baseball
season.
2. Multipurpose trail bids awarded 7/27 3.
Concession stand concrete replacement Drainage swales complete by City
Russell Park Renovation PM1501 $250,000 awarded 7/27. Concrete removed. forces saving approx $2SOK.
Bull Park Playset PM1504 $75,000 Complete
Dutton Island Road Improvements PM1505 $25,000 Will not need. Combined with FllS/16 project
Marsh Multipurpose Path PW1408 $97,220 80% complete-permitting underway Design only FY 14/15
Construction started 7/6. Completion
Marsh Overlook & Kayak Launch PW1409 $300,000 scheduled 9/18. 50% FIND Funding
Public Works Projects
Roberts Street Ditch PW1404 $14,213 Construction completed by DOT Funded for design only
Construction started 4/20. Completion Sturdivant sidewalk, Magnolia &
PW1406 & scheduled 10/16. 8-24-Commission Poinsettia swales substantially
Saltair drainage/Strudivant sidewalk PW1411 $382,700 deleted work on David & Sylvan complete
PW1407
Seminole Streetscape PW 1412 $966,660 Design 95% complete Bidding this fall
Bike Racks & Shower @ Beach
accesses PW1501 $20,000 Complete
Francis Avenue Drainage
Improvements PW1502 $91,386 Complete-Final Inspection 7/22 CDBG funding
Begonia Street W6th to W9th PW1503 $30,000 Design complete. Design only FY 14/15
City Hall Parking Light Improvement PW1504 $10,000 PO issued. Construcion pending