Item 8C- Waterwary Park and Welcome Center Opportunity- Johnston Island~
~
~
~ •
fJf:
~
"" • • • w • .,
• • • • • •
$~====~:;;;:;~~~--·--~~~--~ :
;;:; . ~-. • • • • • • • • •
I ~
AGENDA ITEM 8C
OCTOBER 10, 2016
Existing Boat Ramp Facilities
Ramp Name Lanes Spaces
M.B. Scanlan 6 75
Facility Comparative
Cost-Funding
McCue 4 37
Oak Harbor 1 28
Total 11 140
Johnston Island: 4 Lanes ·60 Spaces, Increase Public Accessibility 43%
Funding and Grant Options
Multiple public and private funding options area available
including:
Florida Inland Navigation District: Waterways Assistance Program
U.S. Department of the Interior, Fish and Wildlife Service: Boater Infrastructure Grant Program
FDEP: Florida Recreational Development Assistance Program (FRDAP)
FDEP: Land and Water Conservation Fund Program (LWCF)
Florida Fish and Wildlife Conservation Commission: Florida Boater Improvement Fund
Preliminary Estimate of Capital Costs
Item
Mobilization:
Description Estimates Cost
Site Work:
Paving & Drainage:
Water & Sewer:
Electrical:
Boat Ramps & Docks:
Buildings and Structures:
Landscaping
SUB-TOTAL:
CONTINGENCY 20%:
Mobilization, Temp. Facilities, Permits, Survey
Erosion Control, Excavation, Fill, Disposal
Pavement, Curbing, Parking, Walks, Underground Drainage
Well & Septic, Fire Protection
Site Electrical and Site Lighting
Ramps, Bulkhead, Docks, Piles and Signage
Welcome Center & Picnic Pavilions
Tree, Shrubs and Groundcovers, Irrigation
$ 50,000
$ 350,000
$675,000
$ 100,000
$ 100,000
$ 600,000
$ 1,800,000
$,100,000
$ 3,775,000
$750,000
PROJECT$ RANGE: 3.75-4.5 Million, Plus Site Costs and Design/Permitting Fees