Exh 8BAGEPIDA ITEM #3B JULY 11, 2005 CITY OF ATLANTIC BEACH CITY COMMISSION STAFF REPORT AGENDA ITEM: Change order #2 from C.C. Borden Construction SUBMITTED BY: Don Ford, CBO DATE: July 1, 2005 BACKGROUND: The following is a summary of the change order dated 5/16/05 from C.C. Borden. These changes were due to the additional work required for the conventional return air system over the old section of the building. After opening up the ceiling and walls in the old section we found the design on the approved plans would not work. These changes could not be determined until the walls and attic areas were exposed. BUDGET: Certified Air Contractors -additional duct work $3960.00 Wilkinson Insulation -bulkheads insulated between old and new construction. 755.00 CC Borden -framing labor for addition framing of bulkheads 4320.00 Framing materials 1177.00 Subtotal $ 10212.00 Overhead/Profit 1531.00 TOTAL $ 11743.00 ATTACHMENTS: REVIEWED BY CITY MANAGER: