Exh 4DAGENDA ITEM #~D
NOVEMBER 14, 2005
' CITY OF ATLANTIC BEACH
CITY COMMISSION MEETING
STAFF REPORT
AGENDA ITEM: Kestner Road and Dutton Island Road Sewer Extensions -
Infrastructure for City Ownership and Maintenance
SUBMITTED BY: Donna Kaluzniak, Utility Director
DATE: November 4, 2005
.. BACKGROUND: Construction on sewer main extensions has recently been completed on
Kestner Road and Dutton Island Road West, as constructed for a private developer by Coastal
Utility Constructors.
The contractor has completed construction in accordance with approved plans, and has submitted
all necessary documentation. City staff completed a final inspection, and the Department of
Environmental Protection has cleared the sewer systems for service.
BUDGET: No immediate impact to operating budget. The attached schedule of values will be
added to the City's assets.
RECOMMENDATION: Accept the sewer infrastructure on Kestner Road and Dutton Island
Road West for ownership and maintenance by the City of Atlantic Beach.
ATTACHMENTS: 1. Schedule of Values that will be added to City's assets.
REVIEWED BY CITY MANAGER:
AGENDA ITEM #4D
NOVEMBER 14, 2005
Schedule of Values -Sewer
Project Name: Kestner Rd Dutton Island Rd Utility Improvements for Kevin Bennett
Contractor: Coastal Utility Constructors of Jacksonville, Inc.
Engineer: J. Lucas and Associates, Inc.
Kestner Road
Sanitry Sewer Collection System
Mains:
a) 362LF 8" PVC SDR 35
Services
1 EA 6" Single
4 EA 6" Double
Manholes
a) 3 EA Type A
Kestner Road Total Sewer
Dutton Island Road
Cost Total
(If or ea) Installed Cost
$ 51.00 $ 18,462.00
$ 432.00 $ 432.00
$ 864.00 $ 3,456.00
$ 2,500.00 $ 7,500.00
$ 29,850,00
Sanitry Sewer Collection System Cost Total
Mains: (If or ea) Installed Cost
a) 307LF 8" PVC SDR 35 $ 47.00 $ 14,429.00
Services
3 EA 6" Single $ 432.00 $ 1,296.00
Manholes
a) 1 EA Type A $ 2,525.00 $ 2,525.00
Dutton Island Road Total Sewer $ 18,250,00