AGENDA ITEM: Budget Modification for Ped Paths
SUBMITTED BY: Rick Carper, P.E., Public Works Director~~.
DATE: December 1, 2005
" BACKGROUND: The Fiscal Year 2005 City Budget contained funds for the construction of
the Plaza Drive Phase 2, (Parkside Drive to Seminole Road) and
Seminole Road (Garden Lane to Oceanforest Drive N.) Ped Paths. These
funds were not rolled over to the new Fiscal year because it was intended
that they would be encumbered when the FY 06 budget was submitted.
The Plaza Drive project was bid as an Additive Alternate to the 5 Points
Intersection Improvements and was not awarded because of excessive
cost. The Seminole Road project was bid separately, and because of
rising construction cost estimates, the project was split into two phases
(Garden Lane to Oceanwalk Drive S. and Oceanwalk Drive S. to Ocean
Forest Drive N.), in hopes of having sufficient funds for at least one phase.
The project was not awarded because all bids exceeded the available
` " budget. Because the funds for both projects were not encumbered or
rolled over, the money was returned to the General Fund and 112 Cent
Sales Tax Fund as shown below.
Account Number Project Title End of Year
Balance
001-5002-541-6300 Ped Path -Plaza Road $72,850
General Fund -Streets Ph 2 PW0504
131-5002-541-6300 Seminole Ped Path $58,101
1/2 Cent Sales Tax PW0404
Total: $131,951
Staff is proposing to re-obligate a portion of these funds for construction of
` Plaza Drive Phase 2, (Parkside Drive to Seminole Road), including
directly contracting for the bridge -estimated cost $30,000, and Seminole
Road Phase 1 {Garden Lane to Oceanwalk Drive S.) -estimated cost
$62,000, using the City's Annual Concrete Repair Contractor (Gruhn
May). The total cost of these two projects is estimated to be $92,000 (see
attached spreadsheet).
RECOMMENDATION: Approve a budget modification to transfer $58,000 from the %Z
Cent Sales Tax Fund and $4,000 from the General Fund to PW0404 -
Seminole Road Ped Path to allow for completion of Phase 1 (Garden
Lane to Oceanwalk Drive S.), and to also approve the transfer of $30,000
from the General Fund for Projects PW0504 -Plaza Drive Phase 2 Ped
Path. As an Additive Alternate to the Seminole Road project, the
. Commission may wish to fund Phase 2 (Oceanwalk Drive S. and
Oceanforest Drive N). This would require approximately $60,000
` ~ additional from the General Fund.
ATTACHMENTS; Cost Estimate /Comparison Spreadsheet
BUDGET: There are no funds budgeted in FY 2006 for these projects.
REVIEWED BY CITY MANAGER•
r1G1;NDA ITIJNI #3D
DECI;MBIJR 12, 2005
Bikepath
Cost Comparison
Estimate
Bikepath Segment Length Concrete Cost Cost 1 Foot Concrete
Quantity Unit Price
Actual Construction Costs (LF) (SY} (31SY)
MaypoR Road to 3650 3000 $154,400.00 $42.30 $26.00
Parkside Drivo
(Welding - FY 2004)
West Pfaza Bikepath 500 421 $24,676.00 $49.35 $37.00
(Hager- under construction)
West 3rd Sidewalk 585 260 $23, 795.00 $40.68 $22.50
(Hager- andor construction)
Costs to construct from FY 2005 Bids (lowest bid shown)
Seminole Road (Hager)
Garden Lane 1700 1243 $118,235.75 $69.55 $45.00
to OceanWalk Drive S.
OceanWalk Drive 1000 1237 $100,133.50 $100.13 $45.00
to Oceanforest Drive
5 Points Additive Alternate #1 ( Callaway}
Parkside Drive to 500 42i $77,000.00 NA
Seminole Road Lump Sum bid, amount inGudes $25,000 bridge allowance.
Costs to construct using City Concrete Contractor
Gruhn May
Parkside Drive to 474 421 $18,94S.00 $39.97 $45.00
Seminole Road Fonn & Pour only , Does not include earthwork, landscape trimming.
Bridge {City Contract) 311,000.00
Total $29,945.00
Garcien Lane
to OceanWalk Drive S. 1550 1243 $55,926.00 $36.06 $45.00
Fonn & Pour only, Does not include earthwork, landscape trimming.
Remove existing sidewalk 35,500.00 $9
Total $61,426.00
Total Cost $91,371.00
Additional Bike path
OceanWalk Drive S. 1000 1237 $55,674.00 $55.67 $45.00
to Oceanforest Drive Form & Pour only, Does not include earthwork, landscape trimming.
Remove existing sidewalk $3,700.00 $9.00
Total $59,374.00
Overall Total Cost $150,745.00
12/512005 BikePathCostComparison.xls