Loading...
Exh 8DAGENDA ITEM #8D APRIL 28, 2003 CITY OF ATLANTIC BEACH CITY COMMISSION MEETING STAFF REPORT AGENDA ITEM: Change Order #7 SUBMITTED BY: Robert S. Kosoy, P.E. Director of Public Works DATE: April 15, 2003 BACKGROUND: Work on the Core City Improvements Project on various streets required that 5 "time and material" items be added to the contract, 2 of which were adjustments to original contract quantities. The items were required due to existing utility conflicts and incomplete information on the design plans. These items are described in the Change Order Item Summary Sheets. The proposed Change Order work for these items added 8 days to the construction contract. The total for Change Order #7, as summarized in the attached documents, is $44,365.80, with a total of 8 days added to the contract, and a grand total of 76 days added thru Change Order #7. We will have expended 55% of the contingency with this Change Order, however only 54% of the contingency has been expended without the decorative crosswalks which will be covered by other funding at a later date. This percentage tracks well with the money spent through monthly payments ending in March 31, 2003, which are 63% of the-total project funds. BUDGET: The original contingency amount, as approved by the Commission is $627,623.09. The seven change orders will reduce the contingency by $346,665.16 to $280,957.93. RECOMMENDATION: Approve Change Order #7. ATTACHMENTS: Two signed originals (one to be signed and returned to Contractor). of Change Order #7 with Item Summary Sheets (3 pages total). REVIEWED BY CITY MANAGER: AGENDA ITEM #8D APRIL 28, 2003 City of Atlantic Beach Construction Change Order Change Order No: 7 Date: 8-Apr-03 Description of Project: Core City Improvements Project Name of Contractor: Petticoat Contractin4, Inc. Contractor's. Address: 11025 Blasius Rd., Jacksonville. FL 32226 Bid No.: 0102-13 Original Contract Amount: $ 4,184,153.91 Original Contingency Previous Change Orders: $ 302,299.36 Amount: Change Order No.: 7 $ 44,365.80 Less Total C.O. To Date: Revised Contract Total thru C.O. No.: 7 $ 4,530,819.07 Remaining Contingency: Original Contract Time: Contract Time Added thru C.O. No.: Revised Contract Time Projected Completed Date: 540 Davs 7 76 Davs 616 Davs 22-Mar-04 In compliance with the General Conditions of the above the referenced contract, PETTICOAT CONTRACTING, INC. and THE CITY OF ATLANTIC BEACH do both hereby agree that PETTICOAT CONTRACTING, INC. shall make the following changes, additions or deletions to the work specified in the specifications and plans. ' See attached summary The cost of the changes under this Change Order will increase the initial Contract in the amount of: $ 44.965.80 PETTICOAT CONTRACTING, INC. 6 Patticnat Cnntrartinn Inr._ Date ~'~~ Title City Manager CITY OF ATLANTIC BEACH Date $ 627,623.09 $ (346,665.16) $ 280,957.93 0 n AGENDA ITEM #8D APRIL 28, 2003 Change Order No. 7 Item Summary Sheet No. Description 1. 12 & Selva Marina Circle: Additional grading required to eliminate various drainage problems adjacent to the roadway on 12t" Street. Total Cost: $3,600.00 Days Added: 1 2. Additional Sidewalk on 10t" Street: 165 SY of existing sidewalk on 10t" Street was replaced due to revisions to adjacent roadway grades. Costs include removal and replacement. Direct costs shown are extended from unit prices established in the bid documents. Total Cost: $5,115.00 Days Added: 0 3. 9t" Street Drainage Revisions: In order to eliminate conflicts between the proposed storm drainage and existing sanitary sewer service laterals on 9t" Street, several modifications were required. Three conflict structures were added. Approximately 380' of the existing 24" RCP was substituted for 19"X30" elliptical pipe.. Two "V" inlet structures needed to be field modified in order to accommodate the revised drainage line. Three service laterals were modified to eliminate conflict with the proposed drainage. Direct costs shown are extended from unit prices established in the bid documents, costs for similar work approved under previous change orders, or actual labor, equipment and materials utilized for the work.. Total Cost: $21,506.21 Days Added: 5 4. Plowable Fill at old Lift Station: An abandoned lift station was discovered near 7t" Street and East Coast Drive. To secure the station, the existing top was demolished and the structure was filled with. flowable Fill. Costs include labor, equipment and materials for partial demolition and filling of the structure. Total Cost: $5,575.00 Days Added: 1 5. 12" WM Case 'B' on East Coast and 5t" Street: It was discovered that an existing sanitary sewer crossing at 5th street was not as deep as indicated on the plans. In order to avoid conflict between the new waterline and the existing sanitary line, a `Case B' must be installed at this location. Direct costs shown are based on similar work approved under previous change orders. Total Cost: $7,364.64 Days Added: 1 AGENDA ITEM #8D APRIL 28, 2003 Item Description 1 12th & Selva Marina Backfill 3c Grade FH Extension 2 Additional Sidewalk on 10th Street 3 9th Street Drainage Revisions 4' X G Conflict Manholes Modify Yazd Drain Laterals "]9" X 30" Pipe Premium Modify 5-910 & 920 4 Plowable Fill at old Lik Station Crew Time -Remove Top 5 IZ" WM Case 'B' ' Based on Original Contract Item. Atlanric Beach Core Ciry Improvements Project Petticoat Contracting, Inc. Change Order #7 Summary Qty Uni t Price 1 LS $2,800A0 1 LS (800.00 165 SY $31.00 3 EA $3,608.00 1 EA $5,388.81 380 LF $11.30 2 EA $500.00 35 CY ;125.00 4 HR $300.00 1 LS $7,364.64 Subtotal: General Conditions and Bond on Original Items at 12.8%: Total: Extension Totals Days 1 $2,800.00 b800.00 $3,600.00 $5,115.00 $5,115.00 5 $1 Q,824.00 $5,388.81 $4,294.00 $1,000.00 $21,506.81 $4,375.00 1 $1,200.00 $5,575.00 $7,364.64 $7,364.64 1 $43,161.45 $1,204.35 $44,365.80 8