BACKGROUND: Work on the Core City Improvements Project on various streets
required that 5 items be added to the contract, all of which were
adjustments to original contract quantities with minor direct costs
added. The items were required due to existing utility conflicts and
incomplete information on the design plans. These items are
described in the Change Order Item Summary Sheets. The
proposed Change Order work for these items added 6 days to the
construction contract.
The total for Change Order #8, as summarized in the attached
documents, is $33,544.18, with a total of 6 days added to the
contract, and a grand total of 82 days added thru Change Order #8.
We will have expended 61 % of the contingency with this Change
Order, however only 60% of the contingency has. been expended
without the decorative crosswallcs which will be covered by other
funding at a later date. This percentage tracks well with the money
spent through monthly payments ending in Apri130, 2003, which
are 69% of the total project funds:
BUDGET: The original contingency amount, as approved by the Commission
is $627,623.09. The eight change orders will reduce the
contingency by $380,209.34 to $247,413.75.
RECOMMENDATION: Approve Change Order #8.
ATTACHMENTS: Two signed originals (one to be signed and returned to Contractor)
of Change Order #8 with Item Summary Sheets (3 pages total).
REVIEWED BY CITY MANAGER:
AGENDA ITEM #8C
MAY 27, 2003
City of Atlantic Beach
Construction Change Order
Change Order No: 8 Date: 12-May-03
Descriution of Project:
Core City Improvements Project
Name of Contractor: Petticoat Contractino, Inc.
Contractor's Address: 11025 Blasius Rd., Jacksonville. FL 32226
Bid No.: 0102-13
Original Contract Amount: $ 4,184,153.91 Original Contingency
Previous Change Orders: $ 346,665.16 Amount:
Change Order No.: 8 $ 33,544.18 Less Total C.O. To Date:
Revised Contract Totat thru C.O. No.: 8 $ 4,564,363.25 Remaining Contingency:
Original Contract Time: 540 Davs
Contract Time Added thru C.O. No.: 8 82 Davs
Revised Contract Time : 622 Davs
Projected Completed Date: 28-Mar-04
In compliance with the General Conditions of the above the referenced contract, PETTICOAT
CONTRACTING, INC. and THE CITY OF ATLANTIC BEACH do both hereby agree that PETTICOAT
CONTRACTING, INC. shall make the following changes, additions or deletions to the work specified
in the specifications and plans.
' See attached summary
The cost of the changes under this Change Order will increase the initial Contract in the
amount of: $ 33,544.18
PETTICOAT CONTRACTING, INC.
_ ~,.~ ~ i v
Petticoat Con a ing, nc. Date
U1 ~'~
Title
CITY OF ATLANTIC BEACH
City Manager
Date
$ 627,623.09
$ (380,209.34)
$ 247,413.75
AGENDA ITEM #8C
MAY 27, 2003
Change Order No. 8
Item Summary Sheet
No. Description
1. Add inlet to S-761 & Upgrade S-762: Modify proposed drainage at the corner of 7t" Street and
Beach Avenue to improve drainage function. Direct costs shown are extended from unit
prices established in the bid documents.
Total Cost: $3,855.00 Days Added: 1
2. Add Inlet at 12t" Street & East Coast Drive: The plans indicated an existing inlet at the
northeast corner of 12t"Street and East Coast Drive. The plans provided no means of
connecting to or replacing this inlet. Items shown are necessary to activate this drainage
structure. Direct costs shown are extended from unit prices established in the bid documents,
or costs for similar work approved under previous change orders.
Total Cost: $6,293.00 Days Added: 1
3. Add Yard Drain & Modify Inlets on 12th: Miscellaneous items necessary to enhance drainage
function. on 12t" Street. Direct costs shown are extended from unit prices established in the
bid documents, or costs for similar work approved under previous change orders.
Total Cost: $7,633.00 Days Added: 1
4. Miscellaneous Concrete Replacement on 7th Street: Additional driveway, sidewalk and curb
replacements necessary on 7t" Street. Direct costs shown are extended from unit prices
established in the bid documents.
Total Cost: $5,113.00 Days Added: 1
5. Other Items: Eight sanitary sewer services not shown in the plans are needed in order to
complete the sanitary sewer installation on 11t" Street. A conflict manhole was added on 8t"
Street to eliminate a conflict with an existing sanitary service. Direct costs shown are
extended from unit prices established in the bid documents.
Total Cost: $7,576.OG Days Added: 2
AGENDA ITEM #8C
MAY 27, 2003
Atlantic Beach Core City Improvements Project
Petticoat Contracting, Inc.
Change Order #8 Summary
Item Description Qty Unit Price Extension Days
1 Add inlet to S-761 & Upgrade S-763 1
* 12" D.I. Pipe 50 LF $45.00 $2,250.00
* Type'C' Inlet 1 EA $2,025.00 $2,025.00
* Pavement Repair 27 SY $54.00 $1,458.00
* Modify S-761 1 LS $500.00 $500.00
* Yard Drain (1) EA $1,228.00 ($1,228.00)
* 12" HDPE (50) LF $23.00 ($1,150.00)
SUBTOTAL $3,855.00
2 Add Inlet at 12th & East Coast 1
Type 'E' Inlet 1 EA $2,823.00 $2,823.00
* 12" D.I. Pipe 30 LF $45.00 $1,350.00
Connect to Existing 1 LS $500.00 $500.00
* Pavement Repair 30 SY $54.00 $1,620.00
SUBTOTAL $6,293.00
3 Add Yard Drain & Modify Inlets on 12th i
Inlet Adjustments 2 EA $1,779.50 $3,559.00
* Yard Drain 1 EA $1,228.00 $1,228.00
* 8" HDPE 102 LF $23.00 $2,346.00
Modify S-1215 1 LS $500.00 $500.00
SUBTOTAL $7,633.00
4 Miscellaneous Concrete Replacement on 7th Street 1
* Curb and Gutter 33 LF $20.00 $660.00
* Add Sidewalk (Rem & Repl) 7th St 63 SY $31.00 $1,953.00
* Add Driveways (Rem & Repl) 7th St SO SY $50.00 $2,500.00
SUBTOTAL $5,113.00
5 Other Items 2
* Add Sewer Sevices on 11th 8 EA $496.00 $3,968.00
4' x 6' Conflict Manhole on 8th Street 1 EA $3,608.00 $3,608.00
* Based on Original Contract Item
Subtotal: $30,470.00
General Conditions and Bond on Original Items at 12.8%: $3,074.18
Total: $33,544.18 6