Exh 8C AGENDA ITEM #8C SEPTEMBER 22, 2003 ' CITY OF ATLANTIC BEACH CITY COMMISSION MEETING STAFF' REPORT AGENDA ITEMr Change Order #11 SUBMITTED BY: Robert S. Kosoy, P.E. Director of Public Works DATE: September 12,2003 :BACKGROUND: Additional work on Ahern,1 ~, 2°d and .Sherry Drive, as described. in the attached Change Order, required that items #1, 6, 7 and 8 be .added to the contract. Items #2, 3, 4 and: describe over-runs at various locations throughout the contract, and further refinement of quantities as we near the conclusion of the project. Note that items #4 and 5 are credits. The'total far Change Order #11, as summarized in the attached documents, is $61,609.20, with a total of 12 days added to the contract, and a grand total of 98 days added thru Change. Order #11. We will have expended 80% of the contingencywith this Change Order. This percentage tracks well with the money spent through estimated monthly payments through August 31, 2003, which are 97% of the total project funds. (At'the time' of this report, we are awaiting :the monthly invoice through. August.) The. Contractor is planning to complete theproject by early Fall, and hopefully. receive. all of the. incentive. BUDGET:: The original contingency amount, as approved by the Commission is $627,623.09: The eleven change orders will reduce the contingency by $499,720.:84 to $127,902.25. RECOMMENDATION: Approve Change Order #11. " ATTACHMENTS: Two signed originals (one to be signed and returned to Contractor) of Change Order#11 with Item Summary.Sheets (6 pages total)... REVIEWED BY CITY MANAGER: - AGENDA ITEM #8C .SEPTEMBER 22, 2003 Atlantic Beach Core City Improvements Project Petticoat Contracting, Inc. Change Order #11 Summary Item Description Qty Unit Price Extension Days 1" ` Sewer Laterals on 2nd Street 5 EA $496.00 $2,480.00 2 2"' S" Concrete Driveway Overrun ' 250 SY $44.00 $11,000.00 0 3'~ Sod Overrun 3000 SY $5.40 $16,200.00 2 4'~ Water Services (Credit Adjustment) (5) EA $544.00 -$2,720.00 0 5 CO 8(Credit Adjustment) (1) LS $580.74 -$580.74 0 6 Sherry Drive Rework:.. ` 6 Curb & Gutter (R & R) 375 LF $17.00. $6,375.00 Sidewalk (R & R) - 140 SY ` $31.00 $4,340.00: 4 ,~ Sidewalk 76 SY $25:00 $1,900.00 Adjust Manhole 6 EA $500.00 $3,000.00 Adjust:Curb Inlet 2 EA $750:00 $1,500.00 Adjust.Inlet 3 EA $500.00 $1,500.00 'Adjust Conflict Box 3 EA $1,100.00 $3,300.00 7 Ahern Street; Rework 1 Curb- & Gutter (R & R) 140 LF $.17.00 $2,350.00 8 1st Street Rework 1 Remove Pavement 1 LS $1,800,00 $1,800.00 Rework.Base 445, SY $3.50 $1,557:50 w 1-1/4" Type III Asphalt 445 SY $4.00 $3.,780:00 '~ Based on Original Contract Item Subtotal: $55,811.76 General Conditions and Bond on Original Items: at 12.8%: $5,797.44 Total: $61,609.20 12 __ ,, ,„~~, .r ~ ~ „L ~~~ ., _. ___ _ ,, :AGENDA ITEM #8C SEPTEMBER 22, 2043 Change Order-No. 11 Item. Summary Sheet No. Description 1. Sewer Laterals on 2"d Street: Replace 5 sewer service laterals in conflict with the proposed drainage.. Direct costs shown. are extended from unit. prices established in the bid. documents, or costs for similar work approved under previous change orders. Total Cost: $2,480.00 Days Added: 2 2. 5" Concrete Driveway Overrun: Additional driveway required to complete the project. Additional replacement was required throughout the project to harmonize new street grades with existing private property grades. Direct costs shown are extended from unit prices established in the bid documents, or costs for similar work approved underprevious change orders. Total Cost: $11,000.00 Days Added: 0 3. Sod Overrun: Contracf plans only required the Contractorto place a 2' strip of sod along each.. sidestreet. Additional regarding to harrnonize grades along residential property necessitated ' the use. of more sod throughout the. project. bisect costs shown are extended from unit prices - established in the bid documents, or costs forsimilar work approved- under previous change orders. Total Cost: $16,200.00 Days Added: 2 . 4. Water Services (CreditAdjustment): Additional water services were added under previous change orders, 5 were not installed dUe to actual field requirements. Direct costs shown are extended.-from unit prices established in the. bid documents, oncosts for similar work approved under previous change orders:. Total Cast: $-2,720.00 bays Added: 0 5. Adjustment for C0 8: (Credit Adjustment): An error was discovered: in the General Conditions calculation on Change Order 8. Total Cost: $-580.74 Days Added: 0 6. Sherry Drive Rework::Various Items wilt be added to correct deficiencies. on Sherry Drive :.including; sidewalk revisions to improve pedestrian safety at the intersections; adjusting manholes to improve ride, and modifying curb return grades to improve drainage. Direct costs shown are extended from unit prices established in the bid documents, or-costs'for similar work approved under previous change orders. Total Cost: $12,915.00 Days Added: 6 7`. Ahern Street Rework: 120' of curb needs to be replaced in order to match grades on Sherry Drive grades to improve drainage. Direct costs shown are extended from unit prices established in the bid documents,. or costs forsimilar work approved under previous change orders. .Total Cost: $2,380.00 - Days Added: 1 - __ __ II' I I AGENDA ITEM #3C - SEPTEMBER 22, 2003 City of Atlantic Beach Construction Change Order Change Order Noc 11 Date: 9-Sep-03 Description of Project: Core City Improvements Project Name of Contractor: Petticoat Contractina~l~ Contractor's Address: 11025 Bl asius Rd ,..,aacksonville FL ~~~~a Bid No.: 0102-13 Original ContractAmount: $ 4,184,153.91 Original Contingency Previous Change Orders: $ 438,111..64: Amount: $ 627,623.09 Change OrderNo.: 11 $ 61,609.20 Less Total CA: To Date: $ (499,720.84) Revised Contract Total thru C.O. No.: 11 ` $ 4,683,874:75 Remaining Contingency: $ 127,902.25 Original Contract Time: ~Q Davs Contract Time:Added thru C.O. No.: 11 1QQ D~t~ Revised Contract Time : ,t~Q Davs Projected Completed Date: r- 4 In oompliance.with the Geheral Conditions of the above the referehced contract, PETTICOAT. CONTRACTING, LNC. a.nd THE CITY DF ATLANTIC. BEACH do both hereby. agree: thaf PETTICOAT CONTRACTING, INC. shall make the following changes, additions or deletions to the work specified in the specifications and plans. "See attached'summary The cost of the changes. under this Change Orderwill increase the initial Contract in the amount of: $ 61:,609.20 PETTICOAT. CONTRACTING, INC. `: Petticoat Contracting, lnc. Date Title ......CITY OF ATLANTIC BEACH City .Manager Date ~, I IiI