Exh 4DAGENDA ITEM 4D
MARCH 11, 2002
CITY OF ATLANTIC BEACH
CITY COMMISSION MEETING
STAFF REPORT
AGENDA ITEM: Sewer Improvements in the Donner Road Area
Bid No. 0102-7
SUBMITTED BY: Donna Kaluzniak, Utility Directq~
.DATE: February 27, 2002
BACKGROUND: Rehabilitation of deteriorated sewer mains to prevent infiltration and inflow
was recommended in the City's Sewer Master Plan. The area near Donner Road has had
excessive flows during periods of heavy rainfall, and sewer system rehabilitation was budgeted for
this year. The project consists of rehabilitating approximately 13001ineaz feet. of sewer main,
replacing services and lining manholes- Acceptable rehabilitation methods were cured-in-place
piping and pipebursting.
A Mandatory Pre-Bid Meeting was held on February 7, 2002, and two bids were received on
February 20, 2002. The bids were as follows:
Contractor Gruhn May, Inc. Insituform Technologies,
Inc.
Construction Method Pi eburstin Cured-In-Place Pi in
Bid Price $126,699.10 $98,681.00
A bid analysis was performed, and the low bidder meeting all requirements was Insituform
Technologies, Inc. in the amount of$98,681.
BUDGET: A total of $180,000 was budgeted for this work in the Sewer Collection Account
No. 4I0-5506-535-6300.
RECOMMENDATION: Awazd the contract for Sewer Improvements in the Donner Road
Area to Insituform Technologies, Inc. in the amount of $98,681.
ATTACHMENTS: 1. Bid tabulation for Bid No. 0102-7
2. Bid analysis
REVIEWED BY CITY MANAGER: ~ .X~
City of Atlantic Beach
SEWER IMPROVEMENTS IN THE DONNER ROAD AREA
February 20, 2002
ID #0102-7 3:00 PM
Re uired Documents Gruhn May Insituform
X X
ri final Insurance Certificate X X
id Bond in the amount of 5% X X
hree co ies of bid forms and re uired documents X X
worn statement on Public Entit Crimes X X
i ned co of Document Re uirement Checklist X X
ocumentation of recei t of an addenda X X
Mobilization- Lum Sum $1,100.00 $1,100.00
Install cured in lace i in in existin Sanita Sewer OR Re lace i e usin Pi eburstin Method
.
10" 375 LF total cost $23,250.00 $15,750.00
.
. 8" 900 LF total cost $54,000.00 $32,400.00
Re lace existin services, includin cleanout
.
6" Service in 8 " or 10" i e-7 each-total cost $14,980.00 $23,450.00
. Install Manhole liner in existin manhole
6-8' dee -11 each-total cost $9,625.00 $14,300.00
8-10' dee -1 each total cost $1,125.00 $1,500.00
. Tree Protection/Lum Sum $1.00 $110.00
. Sitework, inlcudin b ass um in /Lum Sum $11,100.00 $1,100.00
SUBTOTAL (Items 1-6) $115,181.00 $89,710.00
Ten ercent (10% Contin enc of Subtotal $11,518.10 $8,971.00
Total Base Bid Items 1-6) Ius 10% contin enc
$126,699.10 $98,681.00.
Award of Bid based on Department Analysis and Commission Approval
~~
~d
x~
M
F+
N
O
O ~
N
BID ANALYSIS --SEWER IMPROVEMENTS IN THE DONNER ROAD AREA
CITY BID NUMBER 0102-7
GRUHN MAY, INC. INSIT UFORM
ITEM EST. QTY. UNITS UNIT PRICE AMOUNT UNIT PRICE AMOUNT
1 Mobilization 1 LS $1,100.00 $1,100.00 $1,100.00 $1,100.00
2 Install cured in place piping in existing
sanitary sewer pipe or replace pipe
using pipebursting method
a. 10" 375 LF $62.00 $23,250.00 $42.00 $15,750.00
b. 8" 900 LF $60.00 $54,000.00 $36.00 $32,400.00
3 Replace existing services, including.
cleanouts
a. 6" service in 8" or 10" pipe 7 EA $2,140.00 $14,980.00 $3,350.00 $23,450.00
4 Install manhole liner, in existing
manhole.
a. 6-8'deep 11 EA $875.00 $9,625.00 $1,300.00 $14,300.00
b. 8-10'deep 1 EA $1,125.00 $1,125.00 $1,500.00 $1,500.00
5 Tree protection 1 LS $1.00 $1.00 $110.00 $110.00
6 Sitework including b ass pumping 1 LS $11,100.00 $11,100.00 $1,100.00 $1,100.00
SUB-TOTAL (ITEMS 1-6) $115,181.00 $89,710.00
0.1 TEN PERCENT (10%) CONTINGENCY OF SUBTOTAL $11,518.10 $8,971.00
TOTAL BASE BID ITEMS 1-6 PLUS 10% CONTENGENCY $126,699.10 $98,681.00