Loading...
Exh 4DAGENDA ITEM #4D SEPTEMBER 23, 2002 CITY OF ATLANTIC BEACH CITY COMMISSION MEETING STAFF REPORT AGENDA ITEM: Piping Modifications at Wastewater Treatment Plant No. 1 Bid No. 0102-24 SUBMITTED BY: Donna Kaluzniak, CEP, Utility Director 4~'~// DATE: September 13, 2002 ~~ BACKGROUND: This project includes piping replacements and modifications at Wastewater Treatment Plant #1, located at 1100 Sandpiper Lane. The work consists of replacing deteriorated air lines, upgrading some of the on-site reuse piping, and extending an existing return sludge line. Invitations were sent to numerous vendors, and five contractors submitted approved prequalification packages. Only one contractor, W. W. Gay Mechanical Contractors, Inc. attended the mandatory pre-bid meeting and submitted a bid. The total base bid for the project was $84,500, plus a ten percent contingency of $8,450 for a total of $92,950. BUDGET: A total of $95,000 was budgeted for this project in the Sewer Treatment Fund under account number 410-5508-535-6300. RECOMMENDATION: Award the Piping Modifications at Wastewater Treatment Plant No. I to W. W. Gay Mechanical Contractor, Inc. in the amount of $92,950. ATTACHMENTS: 1. 2. Bid Tabulation Form Bid Analysis REVIEWED BY CITY AGENDA ITEM#4D SEPTEMBER 23, 2002 Piping Modification at Wastewater Plant No. Bid No. 0102-24 Bid Analysis 9/13/2002 Item No. Description Quanti Units Unit Cost Extended Cos 1 Mobilization 1 LS $5,840.00 $5,840.00 2 Site Work 1 LS $8,490.00 $8,490.00 3.a. SS 14" Air Line 160 LF $156.00 $24,960.00 3.b. SS 14" 45 de .Bends 3 EA $1,039.00 $3,117.00 3.c. Reducer 14" X 8" SS/DI 1 EA $917.00 $917.00 4.a. DI Force Main 6" 300 LF $68.75 .$20,625.00 4.b. DI Force Main 6" 45 de . 2 EA $339.00 $678.00 4.c. DI Wet Ta 6 X 18 1 EA $1,668.00 $1,668.00 4.d. As halt Pavin Re air 135 LF $67.00 $9,045.00 S.a. 4" Galv. Reuse Pipin 135 LF $34.80 $4,698.00 S.b. 4" Ball Valve 1 EA $645.00 $645.00 5.c. 2" Ball Valve 1 EA $87.00 $87.00 5.d. 2" Gate Valve 2 EA $87.00 $174.00 5.e. 2" Pressure Relief Valve 1 EA $120.00 $120.00 5.f. 2" Rubber Hose 200 LF $8.00 $1,600.00 5. Fountain nozzle 2 EA $918.00 $1,836.00 Total Base Bid $84,500.00 10% Contin enc $8,450.00 Total Cost $92,950.00 CITY OF ATLANTIC BEACH PIPING MODIFICATIONS AT WASTEWATER TREATMENT PLANT #1 September 4, 2002 BID #0102-24 3:00 PM WW GAY MECHANICAL CONTRACTORS Required Documents X Submission in Triplicate X Bid Bond (5%) X Original Insurance Certificates X Signed Copy of Document Requirements Checklist Completed W-9 Form. X Drug Free Workplace Form X Statement on Public Entity Crimes X Acknowledgment of Receipt of Addenda X Trench Safety Affidavit X ~. ~: ,~ ,p . TOTAL BASE BID (Items 1-5): $84;500.00 Ten Percent (10%) contingency fund $8,450.00 TOTAL BASE BID (Items 1-5) PLUS 10% CONTINGENCY: $92,950.00 Bid award based on Department Analysis and Commission Approval b~ y~ ~z d ~a xy N .~~ W r1 N ~k od N