Exh 8F 8F / r /~ f ~O AGENDA ITEM: DATE: SUBMITTED BY: STAFF REPORT CITY OF ATLANTIC BEACH CITY STAFF REPORT Technical Services Agreement for Core City Project, Phase A January 6, 2000 Jim Hanson, City BACKGROUND: At the December 14, 1999~neeting of the Mayor and Commission, Part A - "Preliminary Engineering Design Report" with Aikenhead & Odom was approved in the amount of $273.532.34. Additional services for sub- Consultants Giotto and Associates, Inc. and Ellis and Associates, Inc. were also approved in amounts not to exceed $72,292.00. The Technical Services Consulting Agreement with Aikenhead & Odom was not available for review and approval at that time. It is appropriate for the Mayor and Commission to also review and approve that Technical Services Agreement and authorize its execution. The proposal from Aikenhead & Odom for Part A - "Preliminary Engineering Design Report" will be attached to, and become a part of, the Technical Services Agreement. City Staff and the City Attorney have reviewed the Technical Services Agreement proposed by Aikenhead & Odom and have caused for several changes to this final version. It is now ready for approval by the Mayor and Commission. BUDGET: Funding for this engineering work is included in the Utility Revenue Bond Fund, 480-0000-533-6300, which has a remaining balance of $5,750,481.00. RECOMMENDATION: Authorize the Mayor to execute the Technical Services Consulting Agreement and Work Authorization No. 1 (Part A} with Aikenhead & Odom, Inc., in an amount of $272,219.34. ATTACHMENTS: Technical Consulting Services Agreement with Aikenhead & Odom, Inc. C1TY OF t~~rtCc 'yea c(- f'~vtu~c 800 SEMINOLE ROAD ATLANTIC BEACH, FLORIDA 32233-5445 TELEPHONE (904) 247-5800 FAX (904) 247-5805 SUNCOM 852-5800 Item 8-F The Technical Consulting Services Agreement with Aikenhead and Odom will be delivered on Friday, January 7th. niKEN~ c~ODOM,~~ CONSULTING ENGINEERS 5730 Bowden Road, Suite 200 Jacksonville, Florida 32216 Phone 904/636-5432 FAX 904/636-5433 January 4, 2000 FOR HAND DELIVERY JE4.NUARY 5 2000 AM Mr. Jim Hanson, City Manager City o~ Atlantic Beach 800 Seminole Road Atlantic Beach, Florida 32233 Re: City of Atlantic Beach CapitNl Improvements Project (Selva Lagoon Master Stormwater System, Select Core-City Street and Drainage System, and Select Core-City Water Distribution Systems) Professional Engineering Services, Final Design Phase, Part A Dear Mr. Hanson: Attached are two (2) original engineering proposals, signed by us, for the referenced Final Design Phase, Part A. I offer the following minor clarifications: 1. The final fee is slightly less than previously approved by the City Commission, since the reimbursables have been adjusted to reflect a decrease in the revised Scope of Work. 2. The bar-chart time graph now indicates acurrently-anticipated first meeting of the SRC, and a subsequent meeting with the Commission has been "posted" 2 weeks later to allow time for the SRC to prepare a report of their meeting and recommendations for the Commissioners review prior to our mc;eting with them. We have also moved the other two SRC and Commission meetings 1 week earlier and later respectively to indicate the approximate 2 week gap between these meetings. 3. We have indicated January 10, 2000 as the date of the agreement throughout. This is being hand-delivered early AM Wednesday, January 5, as requested. I trust all is iri order, but if you should have any questions, please call me at your earliest convenience. Sincerely, s r ~..% Neil Aikenhead, P.E. President Encl. (Two Signed Proposals) c: Bob Kosoy w/ Encl (Copy of Proposal) F:~PROJEC'CS~Ad-Bch-Strnwtr~Fee-ProposallFinal-Des~Submti-LV-3.aik. wpd TECHNICAL CONSULTING SERVICES AGREEMENT This TECIiNICAL CONSULTING SERVICES AGREEMENT ("Agreement") is entered into as of and made effective as of January 10, 2000, between City of Atlantic Beach, a political subdivision of the State of Florida (the "OWNER") and Aikenhead & Odom, Inc. (the "CONSULTANT"). On the terms and conditions hereinafter set forth, OWNER retains CONSULTANT and CONSULTANT accepts such retention to perform certain tasks, duties and services (hereinafter collectively referred to as "Services"). Unless expressly provided otherwise in writing, this Agreement shall govern only Services deemed in Exhibit A, "Scope of Services and Schedule". ARTICLE 1-TERM OF AGREEMENT 1.1 The Term of this Agreement shall begin on the date hereof. This Agreement shall be deemed a continuing contract within the meaning of Section 287.055, Florida Statues and such does not have a specific termination date, but is subject to termination as provided in Article 7. ARTICLE 2 -SCOPE OF SERVICES AND SCHEDULE 2.1 The general scope of CONSULTANTS obligations hereunder shall be to serve in a consultative capacity for OWNER and to perform the services necessary to accomplish the General Objectives and Tasks as set forth in Exhibit A. Exhibit A outlines the basic services and fee structure to be made a part of this Agreement. Specific tasks and services and corresponding fees shall be identified for each project and shall be authorized by the OWNER upon execution of an Addenda to the Agreement. 2.2 The only warranty or guarantee made by CONSULTANT in connection with the services performed hereunder is that the CONSULTANT will use that degree of care and skill ordinarily exercised under similar conditions by competent and reputable members of the profession practicing in the same or similar locality. No other warranty, expressed or implied, is made or intended by the consulting services or by furnishing oral or written reports. CONSULTANT shall be liable to OWNER for all work performed by sub-consultants retained by CONSULTANT as if such work had been performed directly by CONSULTANT and applying the foregoing standard. ARTICLE 3 -PAYMENT 3.1 Owner agrees to pay CONSULTANT, or cause CONSULTANT to be paid for Services rendered hereunder during the term of this Agreement, the Authorized Amount in accordance with the fee schedule, method of payment and other terms and conditions set forth herein and in Exhibit A attached hereto. With respect to any specific Addenda, the TOTAL COST identified therein shall be a not-to- exceed limit for CONSULTANT'S fees, direct costs and sub-consultant cost combined, unless otherwise specifically stated therein and CONSULTANT may not charge OWNER amounts in excess thereof, unless otherwise specifically stated therein. 3.2 For portions of the Services that are cost reimbursable, the CONSULTANT agrees to keep accurate records showing all charges and expenses incurred by the CONSULTANT. OWNER has the right upon reasonable notice, to audit (at any time up to one year after completio - ~p o-f a t 1 ~~ l`Vl~ -°~° - ~' expenses and disbursements made or incurred in connection with the Services to be ~_~~ ~~~.., ~~~~ performed and may examine any relevant records of the CONSULTANT. No examination of the records ~;~~ fQCf shall unreasonably delay or defer the obligation of OWNER to make payment of undisputed invoices from the CONSULTANT as provided herein, as long as such records are in order and accurately reflect the CONSULTANT'S actual costs incurred. 3.3 Payment is due from the OWNER upon receipt of invoice from CONSULTANT. OWNER shall make all payments in accordance with the Florida Prompt Payment Act. All requests for payment shall itemize and identify with specificity fees charged in accordance with the fee schedule in Exhibit A. Appropriate supporting documentation of sub-consultant costs and direct costs incurred external to the Agreement between City of Atlantic Beach & Aikenhead & Odom, Inc. January 10, 2000 Page 1 of 7 TECHNICAL CONSULTING SERVICES AGREEMENT CONSULTANT sufficient to meet OWNER's audit requirements shall be submitted with the appropriate invoice. ARTICLE 4 -CHANGES 4.1 This Agreement may be amended, altered or changed only in a written instrument signed by OWNER and CONSULTANT; provided however, that OWNER may reduce the Scope of Services herein without approval by CONSULTANT. ARTICLE 5 -LIMITATION OF LIABILITY 5.1 With respect to damages incurred by OWNER arising out of any error, omission or other \ professional negligence for which CONSULTANT is responsible hereunder pursuant to the standard ~~ ` referenced in Article 2.2 hereof, OWNER agrees that CONSULTANT'S liability shall be limited to - ~ $1,000,000.00 (one million). ~ ~ p $~ ARTICLE 6 -CONSTRUCTION REPRESENTATION ~ ~: ~~~~ 6.1 With respect to construction activities based upon designs and permits procured hereunder, d ~ ~~,c `=~f. OWNER agrees that CONSULTANT will not be expected to make exhaustive or continuous on-site ~ ; ~,~ , inspections but that periodic observations appropriate to the construction stage may be performed. It is ~ F ;, further agreed that CONSULTANT will not assume responsibility for the contractor's means, methods, F techniques, sequences or procedures of construction and it is understood that field services provided by CONSULTANT will not relieve the contractor of his responsibilities for performing the work in accordance with the plans and specifications. The words "supervision", "inspection", or "control", are used to mean periodic observations of the work and the conducting of tests by CONSULTANT to verify substantial compliance with the plans, specifications and design concepts. Continuous inspections by CONSULTANT does not mean CONSULTANT is observing placement of all materials. Full-time inspection means that an employee of CONSULTANT has been assigned for eight-hour days during regular business hours. 6.2 Should CONSULTANT provide periodic observations or monitoring services at the job site during construction, OWNER agrees that, in accordance with generally accepted construction practices, the contractor will be solely and completely responsible for working conditions on the job site, including safety of all persons and property during the performance of the work and compliance with OSHA regulations and that these requirements will apply continuously and not be limited to normal working hours. Any monitoring of the contractor's procedures conducted by CONSULTANT is not intended to include review of the adequacy of the contractor's safety measures in, on, adjacent to, or near the construction site. 6.3 With respect to construction activities based upon designs and permits procured hereunder, CONSULTANT shall provide appropriate certification to OWNER and all permitting agencies reflecting construction as built. Therefore, CONSULTANT shall be responsible for arranging and coordination inspections at intervals and frequencies sufficient to base such certification. CONSULTANT shall notify OWNER promptly regarding any material deviations from the design and/or permit in the construction. 6.4 All inspections services shall be identified by Addenda. ARTICLE 7 -TERMINATION 7.1 This Agreement or any Addenda hereunder may be terminated at any tim€~15y OWNER at its ~~~ convenience upon notice to CONSULTANT and in such event, CONSULTAhFT`will be paid for Services ,.,~,~ rendered prior to the termination but shall not be entitled to prospectieeFprofts on Services not performed. CONSULTANT shall have a reasonable amount of tim , e ceipf of termination notice, to terminate its ~~ ~I activities. OWNER agrees to pay CONSULTANT' reasona~l costs associated with such termination. Agreement between City of Atlantic Beac & Aikenhead & Odom, Inc. January 10, 2000 Page 2 of 7 TECHNICAL CONSULTING SERVICES AGREEMENT ARTICLE 8 -INSURANCE 8.1 CONSULTANT carries and will continue during the term of this Agreement to carry: Worker's Compensation/Employers' Liability, Commercial General Liability (including Contractual Liability and Completed Operations) and Business Automobile Liability, each as occurrence based policies in the amounts and on the terms set forth in Exhibit B, attached. CONSULTANT may provide the required coverage for these policies in combination of primary and umbrella or excess liability insurance policies. CONSULTANT also now carries and will continue during the Term of this Agreement to carry, Professional Liability Insurance on a claims-made basis in the amounts and on the terms set forth in Exhibit B, attached. _ _ _ _ - __ ARTICLE 9 -PERMITTING 9.1 The OWNER herein acknowledges that several ,=local, 'estate and federal environmental regulatory permits may be required ,`for the OWNER's project. The 'CONSULTANT will assist the OWNER in preparing these permits ~t the OWNER's directi ~i through appropriate Addenda.. However, the OWNER acknowledges that it as the responsi~ili f r submitting, taining and abiding by all required permits unless an Add da provides otharw' e. Furthermore, the OWN~~_ __hol~ ..`wx~ ~ ~CONSULTANT,~ harmless from~a y losses or liabilities from sucermitt g or re latory actin; .. .,~__m_,. _ _. __....~_~~.e_m _. _F ,, provided, the fore ing des not co shtute an indemni b the OWNER to the C SUL" ANT regard' t1' Y _. . ..._ any claims for Loss ilities ass rted against the CONSULTANT by third parties. ~ " ~,, __ . ARTICLE 10 -OWNERSHIP OF DOCUMENTS - ____ _ _ _ _ 10.1 All original documents, including, but not limited to drawings, specifications, reports, boring logs, field notes, laboratory tests data, calculations and estimates, prepared by CONSULTANT as instruments of service pursuant to this Agreement, shall upon completion become the property of the •• ••~,~,«. .R~~-srtc~t-ari-civi.uuicu~~ ut auy ua~uic ir:[IiIISiieu LO vw1VL"iC or vw1VBTt s-aget2tg°Or es~gneesr_i --pat~•~fe~r;•-~i~-b~~ed~~~an-"demand,a ~~il u _. , . - e t3'err- OWNER maker agrees that under no c cumstances :shall documents produced by CONSULTANT pursuant to this Agreement be used at any location or for any project not expressly provided for in this Agreement without the written permission of Aikenhead & Odom, Inc The OWNER shall have the right to obtain copies of all documents subject to payment for reaso able costs of reproduction. ARTICLE 11-MISCELLANEOUS ~ wh~c~ 11.1 Any notice required or permitted hereunder shall be deemed to have been duly given if the same shall have been sent via certified or registered mail (return receipt requested), or by any commercial express delivery or courier service (with receipt), with postage or other charges prepaid, in an envelope addressed to the party to whom notice is to be given, at the address shown below: ~._. If to CONSULTANT: ~ ~:,; If to OWNER: Attention: 'y T 1'~ ` Ili Attention: ~p~°''l~f ~~t~Y1 ~d~~ ~~ ~~ l~ ~~~~~ ~f, Agreement between City of Atlantic Beach & Aikenhead & Odom, Inc. January 10, 2000 Page 3 of 7 TECHNICAL CONSULTING SERVICES AGREEMENT 11.2 OWNER and CONSULTANT each binds itself, its successors and assigns to the other party of this Agreement and to the successors and assigns of such other part with respect to all covenents of this Agreement. Neither OWNER nor CONSULTANT shall assign this Agreement without the prior written consent of the other party. 11.3 This Agreement represents the entire and integrated Agreement between OWNER and CONSULTANT and supersedes all prior negotiations, representations or Agreements, either written or oral. This Agreement maybe amended only by written instrument si ed by both parties. ~~~~~~ 11.4 Causes of action between the parties to reement pertaining to acts or failures to act shall be deemed to have occurred and the applicable atuef limitations shall commence to run not later than (i) the date of substantial completion for acts or failures to act occurring prior to substantial completion of CONSULTANT's engineering services pursuant to the Agreement; (ii) the date of issuance of CONSULTANT'S fmal invoice for acts or failures to act occurring after subs antial completion of our engineering services pursuant to this Agreement. ~ ~- 11.5 Nothing contained in this Agreement shall create a contractual relationship with or a cause of action in favor of a third party against either OWNER and CONSULTANT. 11.6 This Agreement shall be governed in all respects by the laws of the State of Florida. 11.7 If any of the provisions contained in this AGREEMENT are held invalid, illegal, or unenforceable, such invalidity, illegality or unenforceability will not affect any other provision and this AGREEMENT will be constructed as if such invalid, illegal or unenforceable provisions had never been contained herein. 11.8 Any TOTAL COST provided in an Addenda under this Agreement and any invoicing there- -~"~ under are subject to adjustment to exclude any significant sums by which owner determines the same to have been increased due to inaccurate, incomplete, or non-current wage rates, direct costs and sub- Consultant costs; provided, OWNER shall make all such adjustments within one (1) year following the termination or completion of the Addenda services. 11.9 CONSULTANT warrants that it has not employed or retained any company or person, other than a bona fide employee working solely for CONSULTANT to solicit or secure this Agreement. IN WITNESS WHEREOF, the parties hereto have caused this Agreement to be executed individually or by their duly autho '~P~ ~f~ CONSUL,'~'~T:, 11 ~~ ]'~~~ f" ~ ~ OWNER: BY~ ~ ,~ ,_..~ ~~~ By: M. Neil Aikenhe~d, .E. ~ / i i~ President i / ~ n ATTEST: The Honorable John Meserve Mayor ATTEST: Agreement between City of Atlantic Beach & Aikenhead & Odom, Inc. January 10, 2000 Page 4 of 7 EXHIBIT A SCOPE OF SERVICES AND SCHEDULE In accordance with the terms of the Technical Consulting Services Agreement, COUNSULTAN`T agrees to perform the services necessary to accomplish the following Project Objectives: General Engineering in connection with improvements to the City of Atlantic Beach stormwater collection, water distribution and sewage collection system including facilities, planning, surveying, storm water management, geotechnical investigation, preliminary engineering design report, and general civil engineering matters related thereto. Each additional project task shall be authorized by Work Authorization to this agreement. The Work Authorization shall identify the scope of work, fee, and time schedule for each task. The following fee schedule shall be used as the Consultant's Standard Hourly Rates. These rates shall be adjusted on the anniversary date of the Agreement commensurate with the Consumer Price Index. PERSONEL BY DISCIPLINE BASE RATE OR FEE SCHEDULE Principal In Charge $177.93/hr. Chief Engineer $177.93/hr. Senior Engineer $ 95.01/hr. Engineer $ 57.88/hr. CADD Designer $ 41.39/hr. irect expenses, as herein provided and Sub-Consultants fees and expenses shall be billed at direct c~stl p 15%, provided that with respect to sub-Consultants, use the same shall be subject to prior appro~l by the O R through its PROJECT MANAGER. ~ ~°" With respect work performed under specific Work Authorization, all direct expens ,CONSULTANT'S fees and sub-Co ltants' cost billed to OWNER together shall not exceed the T AL COST identified in said Work Authoriz ti~on unless otherwise provided therein. Direct expenses are limi (LIST) long distance phone calls mobile telephone long distance facsimile mail express mail courier presentation material ~,~ mylar photos / photo copy reproduct~ blueline (/BA,,S-IS FOR COMPUTING PAYMENT} bil/led at direct costs,~lus 1'.. 5 0.~- « « « « « « « « « « « « .08 per page .15 per sq. ft. - and travel per diem shall be reimbursed on the same basis as is provided in Section Statutes. A _ __ 061, Agreement between City of Atlantic Beach & Aikenhead & Odom, Inc. January 10, 2000 Page 5 of 7 EXHIBIT B TECHNICAL CONSULTING AGREEMENT CONSULTANT'S INSURANCE TYPE OF COVERAGE MINIMUM LIMITS OF COVERAGE A. Worker's Compensation -Coverage A Employee's Liability -Coverage B B. Comprehensive General Liability (including Contractual Liability) C. Comprehensive Automobile Liability (Hired, and Non-owned Vehicles) Combined Single Limit D. Commercial Umbrella Statutory $1,000,000 per claim $2,000,000 aggregate $250,000 each $ 1,000,000 each occurrence $ 1,000,000 each occurrence $ 1,000,000 aggregate E. Professional Liability (on claims made basis) Retroactive Date 1/22/88 $1,000,000 END OF EXHIBIT B Agreement between City of Atlantic Beach & Aikenhead & Odom, Inc. January 10, 2000 Page 6 of 7 TRUTH-IN-NEGOTIATION CERTIFICATE COUNTY OF DUVAL STATE OF FLORIDA The undersigned M. NEIL AIKENHEAD, as President of Consultant, does hereby certify within the meaning of Section 287.055(5)(a}, Florida Statutes, under oath that the foregoing fee scheduled and direct cost rates are accurate, complete and current as of the effective date of the Agreement to whit is Certificate is attached. ~~ Dated this ~ day of January, 2000. M. NEIL AIKENHEAD The foregoing instrument was acknowledged before me on this _ day of January, 2000, by M. NEIL AIKENHEAD, who personally appeared before me at the time of notarization, and who is personally known to me or who has produced as identification and who did/did not take an oath. SWORN TO AND SUBSCRIBED before me on this c~~day of January, 2000. ~cYx-~^-~-- NOTARY PUBLIC, STATE O FLORIDA Commission No. C~~, ~ g 1 ~''~~ My Commission expires: `"'~ DO~WRA DENNEY i% 1 MY CQMMlaSlON # CC 8$1478 .~~~ bg_ EXPieiES: Nev 13, 2003 1-8043~NOTARY Flo. Notary Service & Bonding Co. Agreement between City of Atlantic Beach & Aikenhead & Odom, Inc. January 10, 2000 Page 7 of 7 TECHNICAL CONSULTING SERVICES AGREEMENT WORK AUTHORIZATION NO. 1 CITY OF ATLANTIC BEACH This WORK AUTHORIZATION, made and entered into this 10th day of January , 2000, by mutual ageement of the parties hereto, is made a part of the Technical Consulting Services Ageement dated January 10. 2000 by and between City of Atlantic Beach (OWNER) and Aikenhead & Odom, Inc. (CONSULTANT), and by being made a part of said ageement is therefore subject to the conditions and considerations contained herein, unless otherwise provided herein. This WORK AUTHORIZATION consists of providing engineering services described in this document, and exhibits, attached hereto. The maximum compensation authorized by this addendum is $272.219.34. Compensation for these services shall be in accordance with Exhibit "A" of the Technical Consulting Services Ageement for hourly rate estimated fees or in accordance with the Lump Sum Fee outlined in the attachment. IN WITNESS WHEREOF, the parties hereto have accepted, made and executed this WORK AUTHORIZATION upon the terms and conditions above stated on the day and year first above written. CONSULTANT: AIKENHEAD & ODOM, INC. By: M. Neil Aikenhead, P.E. President ATTEST ~ Name: ~/iC~~ ~~'ESc~~~ Trt e• - ~~.s~/vd Date: CITY OF ATLANTIC BEACH By: The Honorable John Meserve Mayor ATTEST Date: F:\PROJECTS\Atl-Bch-Stmwtr\workauth-signature.doc WORK AUTHORIZATION NO. 1 STORMWATER CAPITAL IMPROVEMENTS PROJECT SCOPE OF WORK For PRELIMINARY ENGINEERING DESIGN REPORT -PART A AIKENHEAD & ODOM Preliminary Aikenhead & Odom (A&O) will provide Engineering Design Services (Design) to the City of Atlantic Beach (City) for a Capital Improvements Project (Project) involving future Final Design of modifications to the existing City wide master stormwater system, select Core City street and drainage systems, and select Core City water distribution systems, all as detailed herein. Sanitary sewer system modifications/design will be accomplished by City forces independent of A&O effort, with the exception of sanitary sewer on 11~' and 12~' Streets, which will be included. The Project Approach Phase of this effort has been satisfactorily completed. The following scope details the effort to be accomplished under PartA -Preliminary Design Report I. PROJECT SCOPE Additional Elevation Data: A&O has coordinated with Ghiotto & Associates surveyors to obtain necessary additional topographic and channel-bottom information in critical areas of the existing Core City, Howell Park, and Selva Lagoon (around bridge within Selva Marina CC and in narrow areas of canal for cross-section evaluation) to complete the topographical information gathered in prior engineering and analysis efforts, including our Project Approach Phase data. This additional information will not duplicate any information already available. In addition, survey of new routes and sites will be required for the anticipated stormwater pumping stations and force mains. Preliminary information regarding these fees has been provided under separate cover, but the City will handle these services directly under a separate agreement. All necessary effort will be carefully coordinated by A&O with the surveyor under this scope to obtain maximum efficiency of this effort. All elevations will be "benched" to the same datum as the existing records. If unforeseen survey support is required during final design effort, these will also be directed to the City with no engineering overview costs associated. Additional Geotechnical Data: A&O has coordinated with a Ellis & Associates geotechnical services for assessment of the affected Core City streets to determine suitability of resurfacing or reconstruction, as well as structural and route geotechnical investigations services which will be required for the proposed design. This additional information will not duplicate anv information already available. Preliminary information regarding these fees has been provided under separate cover, but the City will handle these services directly under a separate agreement. All necessary effort will be carefully coordinated by A&O with the geotechnical firm under this scope to obtain maximum efficiency of this effort. If unforeseen geotechnical support is required during final design effort, these will be directed to the City with no engineering overview costs associated. Atlantic Beach Preliminary Engineering Design Report -Scope of Services Page 1 of 4 3. Environmental and Legal Efforts: Environmental and legal consultation is currently anticipated to be needed throughout the Final Design process in varying degrees for wetland delineation and environmental mitigation consultation. Preliminary information regarding these fees has been provided under separate cover, but the City will handle these services directly under a separate agreement. All necessary effort will be carefully coordinated by A&O with the environmental firm under this scope to obtain maximum efficiency of this effort. If unforeseen environmental support is required during final design effort, these fees will be directed to the City with no engineering overview costs associated. Phase One (and possible Phase Two) Environmental Audits, and any possible legal consultation regarding purchase of property or determination of "Waters of the State" issues relating to the environmental status of the Selva Lagoon will also be handled independently by the City on an "as-needed" basis. 4. Hydraulic/Hydrologic Modeling A&O will develop a detailed hydrologic model for the entire Selva Lagoon system using SWMM Vers 4.4. A&O will include all data, elevations, and flooding information obtained from prior engineering and analysis efforts, from our Project Approach Phase data, and from this Scope of Services. The new SWMM model will accommodate for stormwater storage capacity resulting from in street and in yard flooding known to occur. A&O will calibrate the model using elevation data obtained during the Project Approach Phase and historic records. The final model will provide definitive data regarding high water elevations within the Selva Lagoon system, ultimately including Core City streets, following input of proposed street improvements when determined. Final Concept Plan: A&O will run multiple alternative scenarios for pumps, tide control, sizes of major stormwater systems, and corresponding stage-storage alternatives on the new SWMM model and develop a preliminary version Final Concept Plan. This plan, developed initially for both a Phase One Construction and Phase Two Construction concept, will include alternatives for primary gravity piped systems as well as for pump and force main locations/sizes/capacities. Anticipated work within most Core City streets will be developed conceptually, based primarily on information from our Project Approach Phase. This work will include the following: a. Preliminary alternative scenarios for the Core City streets and drainage will be provided, based on all information available at this tune. All alternative scenarios will be run on the new model, and associated preliminary cost/benefit estimates will be developed for each alternative. b. A&O will develop plans sufficient for development of the various scenarios that will serve as the basis to develop realistic cost estimates. c. An updated preliminary cost estimate for both proposed construction phases will be developed at this time. d. The possibility of a single construction phase, depending on budget constraints and the cost/benefit alternatives, will be reviewed in detail at this time. e. A&O will meet with the SRC and the City Commission, at tunes to be mutually agreed upon, to review the Final Concept Plan. A&O will provide a presentation and verbal report to outline modifications to the Preliminary Concept Plan, present alternative analyses and cost/benefit information, and discuss the current cost estimate and its level of accuracy. Atlantic Beach Preliminary Engineering Design Report -Scope of Services Page 2 of 4 f. A&O will solicit agreement on a final set of alternatives, incorporate modifications to the Final Concept Plan as agreed upon, and obtain concurrence of the City Commission for a final version of the Final Concept Plan. g. Following City concurrence with the Final Concept Plan, A&O and City Public Works personnel will meet with SJRWMD technical staff to present the Final Concept Plan and discuss mitigation requirements, wetland restoration methodology proposed, and any other concept issues which may be associated with the Final Design effort for ultimate permitting with that agency. A&O will also coordinate with both SJRWMD and EPA regarding existing grant applications pending with those agencies, and will also investigate possible additional grant availability for the proposed Final Concept Plan. h. A&O will complete the Preliminary Engineering Report after acceptance of the final concept plan from the City. This report shall be the basis for the Final Design Development Process to commence. All data developed to date will be available in both hard and digital base for the City at this time. If elected by the City, A&O will negotiate fees for Part B (if not elected at the inception of Part A). The City may also elect to solicit Request for Proposals (RFP's) if desired or in the event the City and A&O cannot reach a negotiated agreement for services for Part B. II. PERMITTING All permitting will be accomplished under Part B services to be contracted at a later date. Preliminary coordination with Regulatory Agencies will be accomplished under Part A as described above. III. GEOTECHNICAL EXPLORATION Provide miscellaneous Geotechnical support as needed and authorized by the City project manager up to the budget amount shown in Exhibit E IV. TIl~~ SCHEDULE The total time allowed for this Work Authorization shall be 130 working days (5 days/wk) excluding time consumed by City Reviews. Upon Notice to Proceed for each task, consultant shall submit a detailed schedule for each task. V. MEETINGS/CONFERENCES TO BE ATTENDED BY THE CONSULTANT 1. One (1) Preliminary Meeting with City Commission. 2. One (1) Preliminary Meeting with Stormwater Review Committee (SRC). 3. Two (2) Additional Meetings with Stormwater Review Committee (SRC). 4. One (1) Interim Meeting with City Commission. 5. One (1) Final Meeting with City Commission. 6. One (1) Final Public Hearing. VI. ADDITIONAL REQUIREMENTS 1. All design criteria shall be based on the "Manual of Uniform Minimum standards for design, Construction and Maintenance for Streets and Highways, State of Florida", latest edition of the City of Jacksonville "City Standards", Florida Department of Transportation standards, and the American Association of State Highway and Transportation Officials Policies and Guidelines. Atlantic Beach Preliminary Engineering Design Report -Scope of Services Page 3 of 4 2. All drainage recommendations shall be based on City of Jacksonville City Standard Specifications and details and the regulations and policies of applicable jurisdictional permitting agencies. 3. Provide dialogue with utility companies as appropriate. 4. Plans shall be standard 24" x 36" Mylar or CADD Vellum Sheets with 22" x 34" inside borders, at scales approved by the City Project Manager to allow '/z size printing. 5. Specifications shall be on standard 8 '/z" x 11"paper. 6. The City shall be the owner of fmal documents. 7. The consultant shall take notes of all design/review meetings held with City and regulatory agencies. These notes shall be transcribed and furnished to the City Director of Public Works for concurrence as soon as practical after the date of the meeting. 8. In addition to project delivery requirements otherwise specified, the consultant shall deliver all final drawings to the City in electronic form using either a standard .dxf format and in layers prescribed by the City Project Manager. VII. NOTICE TO PROCEED No work on this project shall be performed until a contract has been executed and a Notice to Proceed is issued which specifically authorizes such work. "F:\PROJECTS\Atl-Bch-Stmwtr\scope of services - finaLrtF' Atlantic Beach Preliminary Engineering Design Report -Scope of Services Page 4 of 4 - • Uhf1U I 1 U ANIJ A55U1~ F'AC~E @2 EXHIBIT "E" ~.s~~~~~~ c~ AS'S~~~~ g.~s, I2~~. PRO.FESS)t?NAL SUR4'EYt~RS AND Mt1k'r~ERS One San Jnse Piarc, $uitE 33 Jac};sunci)le, Florida 3?257 (904) R86-0{)71 FAX (404) $$h-7174 NDVeFI.l~er 1,2, ~~~~ IuY'. ~vll ,~s7~C~AlI~Gd Ai~C~Ill2ead and ~CIOrlI, II1lC, 5?30 •T~owden R,©ad SUate X00 3ackso~nville, FL 32216 RE: Request for Surveying & l+~appiazg ~oposal Atlantic leach 5t4rmwater Final Design Dear Neil, We are pleased t4 submit this proposal for Professional Surveying aAd upping services on the al~ov~e referenced project, The scope of services regtaires signed and sealed togogzapl;tic surveys of various sites azad mates v~it1~ the .AtlarAtiC Beach area. These surveys shall show the following: above-ground utility indicgtars such as tfalves, risers, meters; laa~dBeaped areas; specircaen trees; tog elevations an aU. starna st~ctures ~.sch as headwalls, catcl^ bay a,racag with pipe size, ~.terial and invent elevations; top of sanitary manholes elevations alcrs~ with flawline elevations, size and material. We require the City of Atlar-tic Hem to forward aII lcacrwm contacts for each utility in each of tlae work areas_ Chiotto +~ Associates will then tasks arrangemments tQ forward qur drawings to each utility for their input an the location {~f their facilities. ~J'e will them apdate •the dr~wi~s per the mar~^.zps and subrnit t3~e final! dravarangs. Each ofthese sites will require aufficieint property line locatiaa in order to pre~sre dssca-agtions a#' each site for transfer of property rights to the City of ,A.tlantic Beach, signed and sealed drawings wall be required to accomparry each description. Uur deliverables shall include eiectaca~mic copies of the survey im a .DWG or .I3GPJ format. All vertical data shat! be tied to e~stitlg benchm$rks establis.~-d by others anal extended to the varia~s work sites. ?~acla site wwdl have a lacall assumed coordinate datum with peln9ar~.ent control paints set far fut-~re referenc:. Each of the sites wish their specd`ic requirements are descn"bed as follows: Pugpstatian 1 ~ 2 Site These two sites combine to measure appraxunazsly 40'x44`, located adjacent to the lagoon near the southerly end of Fleet L.sndii~.g, Survey shall show elevations su.$crent for design and wall exctezed to the edge of lagaan. Estimated Casts: X2,254,00 _ _ . _ _ _ ~~-.,,~U ~ ~ . ~ GHiUT TU AND A55UC PAGE 03 Page 2 of 5 Pumpstation 3 Site This site measures appzoxiazzately 75'x50' and zs located t 225 feet west of the west edge of tl~e lagoozz and t 800 feet 1`~'orth of the Golf Pro Shop. Surrey shall show su~cierrt elevations far design and will extend to the waters edge of the lagoon far a width of ~ 50 feet. From the photograph you forwarded, it appears the survey will need to Shaw trees, golf cant paths and possible other golf related features. l;stianated Costs: $2,520.00 golf Course fridge t4rea This survey requires location of the existing bridge crossing the Lagoon from the Club lE~ouse tQ Cite GolfPro Shop. It nraeasures t 50 feet ict width and t 200 feet in length, centered about the bridge. This survey shall show any visible utilities, the Bridge itself with deck and low member elevations, both sides of the toglbattozzt of bank of the lagoon along with an elevation profile, beginnia~g at natural grade and extending through the lagaosa to natural grade. It is anticipated et this titre that ago work wall be required for transfer of property raghts on this site. Estimated Costs: $7$5.4Q Fleet Landing Tide Crate 13.C. This area. measures approximately 15'x30' and is located at the west eattrance road into Fleet Landing. ~ detailed survey of the roadway, the t; iple box culvert anc3 twc~ cross-sections ug and dawn stream is anticipated at tPaas time. i<t is anticipated at this time that ma work will be required for transfer of property rights az~ tbas sate. Estirtnated costs: $785.0© Selva ItRarine Lawn This site is generally d.~sczibed as the warded area lying west of the west edge Qf the lagoon, ~d orth of Playa, East of Linlcside Drive and South of the westerly extension of County Club Lane. This site treasures f 2640 feet in tkte ~iortlz and South directions and varies front 250' to 400' in width. Thus survey will require: a} a detar~ed survey of the existing drainage pond lying t 300' North of Plaza; b} detailed lacatina of storrndrains and sanitary lines lying within tlxe Ea.~t~ly ane- 'half of Linkside Drive.; c) detailed survey of Eleventh Street up to the culvert crossing (but not iuacludiaag detailed i€tfaa~ation on the existing sewage Iift station adjacent thereto at the lagoozz; d) detailed survey of the easterly edge of asa existing drainage pond lying ~ 700 N©rth of Eleventh Street; e) location of the fences along the easterly portion of the tennis counts near the north _ . __ _ ~..~~..~ ~ ~ ~ ~ L~HIDTTO AhID AS50C PAGE 64 Page 3 of 5 survey Limits; f} cross-sectifln3 at 100' intervals, from the .centerline vfl,iz~kside Drive to the water's edge of the lagoon; g} cross-sections, at ] 00' intervals, from the westerly edge of tree Line to true water' s edge of `she lagoon for the area ~tvx ~ o: ?`.inkside ]rive. Estimated Costs: ~~,'~50.00 Far each of these sites, bench Loops wiIl be required to establish vertical control to the work area. The estimated cost to ea~tend vertical control through each flfthe sites listed above is X1,5.30.00. Tkte remaiztir~g work. consist of route Suzveys for the forcemain routes from, the proposed pump statio~zs. Each of the proposed routes must be clearly defined and approved by the City of Atzantic Beach, arad ,A~ikenhead ~ Jdom Inc. prior to the crew taking any measurements. Each of these routes will require sufficient property line location in order to prepare descxiptiatzs of each route for transfer of property rights to the City of Arlantac Beach. Signed atad seated drawings will be required tc~ accompany each desmiptiorn Each of these routes with. their specific requisernents are described as follows: F'umpstatioz~ I Forceanain ghis route is ~ 15` wide and ~ 900 feet long, exteadiaag ~tartheasterty and East £com the proposed pumpstativn toward a wetland area tyia-,g Nazth of Sevilla anal Southeasterly of Fleet Lauding. This survey will. require location of Y trees, several fences and Bross-sectiaxts far the length of the route. It is quite possila]e that several easements will be required for this route. Estimated Costs: $4,500.00 Pyanpststian 2 Farcprnairt 7Chis route Rs very similar in ~.ttta'~ wx e prc~p~sed Fo~.te ~'ar Puasaps~tagaa 1, oz~ty this Xaute is ~ ISaO L.F., with the northerly terminus being the westerly emrance to Fleet Landing. Estimated Costs: $6,650.00 DStaiaozt 3 Farcemain This route is quite different than others as it requires a goad effort identifying.existing property lines and right-of--way lines. This route runs along the North line of 5elva Linkside to Church Road (across Ivlaypart 1toad) to Dotaater Road and on to the first creek crossing near the Easterly edge ofDultan Island. Est%at~ated length is ~ 7540 L.F. A, partior~ of Church Road is not open (unimproved} and it is aa~txcipated that our survey will be used ts~ extend the roadway tbz-ough tF,is area_ Irstibnated Costs: X23,950.00 - -- •-~-- • - • , LiH1U E 1 U ANU A55U(; PAGE 05 T,'age 4 afr 5 Sea Tuzt1e inn/First Street ~raina~e Exte~zsion This rota 1iegitns near ttae Southezly end of tk~e Sea ~'urtle Enn Barking tat and runs north to First Street, the we~~t along Fia-st Street to 5he:?y Drive. Estimated length is ~ 1000 L.F. This survey wilA cvYer the width of tlae tight-of way ofFi€st Street and ~ 50 wide through the parl*ing tat, Estirnate3 ~©sts: 54,685.04 I have includes a list of our current hourly rates. I trust taws is the aziformatioan you need. If you have any questicsrs or eomtzzetzts, please ca11 zrte anytime. Sxncereiy, ` ~~ / 1'~1]i1~3 ~. ~7h1t1#to clciacs~gSeners~a&nholconab.ptopasai.wpd --- •---- ~ - ~ - urtiU ~ ~ U ANl1 A55UC; PAGE 05 Page 4 of 5 Sea Turtle InniFust Street Ihaina~e Extension This route begins Hess tote Southerly end of the Sea ~'uztle Fruz parking lot Psld nuts north to First . Stree'~, ~h~rl west along First Street to Sherry Drive. Estimated length is ~ 1Q00 L.F. This survey will cvser the width of the tight-of way ©f First Street snd -~ 5a wide through the parking lot, ' _ Estizx~ated COStS: $4,685.00 I have includes a list of our current hourly rates. I trust this is the information you need. If you hsve any questions or eominents, please call ms anytime. Sincerely, • •. Philip T~. Gluotto c~ocelptagJctras~a,&oholoomb.yroposai.wpd - ---- -~•~~ i~u~ooorl~v GHIUTTD AND AS50C GHIO~'T'O & .ASSOCIATES, INC. CURRENT HOURLY RATES November 12, I999 3 Man P'ie:d Cruvv 5720.04/8 hour day 4 Maw Yield Crew X800.44/8 hour day Survey T8Cf1T1tC1an/~,~Spper $4S.O411~0Ur Professior~a~ Survey & Mapper $65.00/I:Tour PAGE 00 Page 5 of 5 Janua Februa March A rii Ma June Jul Task Name Start Finish 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 PART A -Prelimina En ineerin ort Re Jan 11 Jul 10 ry g g p ® Notice to Proceed From City Jan 11 Jan 11 Data Collection Jan 11 Feb 7 , . Survey Data Collection Jan 11 Feb 7 Geotechnical Data Collection Jan 11 Feb 7 Hydraulic Modeling Jan 25 May 15 Preliminary Model Development Jan 25 Apr 3 :::::: :::::::::::::::::::::::::::::::::::::::: :::::::::::::::::::::::::::::::::;: ; ; ; Model Calibration Apr 4 May 1 Final Model Development May 2 May 15 Preliminary Engineering Report Apr 4 Jul 10 Preliminary Alternatives Development Apr 4 'May 15 ~ ~ ~ : ;:;:; :::::::::::::::::::::::::::. :::::::::: Preliminary Cost Estimate Preparation May 16 May 22 ~ ~ ~ ~ • .•.•.• Final Concept Plan Development May 23 Jun 19 Preliminary Engineering Report Development Jun 20 Jul 10 Meetings Jan 14 Jul 10 ; Stormwater(SRC) Meetings Jan 14 Jun 13 p~ SRC Meeting 1 Jan 14 ' Jan 14 SRC Meeting 2 May 16 May 16 SRC Meeting 3 Jun 13 ' Jun 13 ~ ; City Commission Meetings Jan 27 'Jun 26 Preliminary Commission Presentation Jan 27 Jan 27 • 1/27 Interim Commission Workshop May 29 May 29 ~ ~ ~ 5/29 Final Commission Presentation Jun 26 Jun 26 ~ ~ • 6/28 Public Hearings Jul 10 Jul 10 7H0 Final Public Hearing Jul 10 Jui 10 ~ ~ ~ ~ 7h0 Part B -Final Design Development Jul 11 Ju124 ...... . Project: 12-6-99 Part A Schedule Date:Jan4 Task Split Progress ;E_iaEEEpEpEEiE_c Ei Milestone Summary ~~~~~~~~~~..~..~ ~ Rolled Up Task • ^ Rolled Up Split , , Rolled Up Milestone O Rolled Up Progress - ----- External Tasks ~-TT-' ,,-. Project Summary Page 1 CONTRACT FEE SUMMARY CITY OF ATLANTIC BEACH, FLORIDA 1. Project 2. Proposal Number Atlantic Beach Stormwater - Part A Prelimina Desi n Re ort 3. Name of Consultant 4. Date of Proposal Aikenhead & Odom, Inc. 06-Dec-99 :.::~~ '4.F'~`~..1~~.......~ A:BO .::RE L~..T~ ::: ~. ~ .~ :' '~ :~~~:'~'~':':':':':' :':':':':':':'~'~~:'~'~'~~:':':~:•:':':': 5. Direct Labor Hourly Estimated Estimated Rate . Hours Cost TOTAL Principal In Charge $ 60.10 68 $ 4,086.80 Chief Engineer $ 60.10 519 $ 31,191.90 Senior Engineer $ 32.09 622 $ 19,959.98 Engineer $ 19.55 864 $ 16,891.20 CADD Desi ner $ 13.98 1382 $ 19,320.36 TOTAL DIRECT LABOR $ 26.47 3455 $ 91,450.24 6. Overhead (Combined Fringe Benefit & Administrative) Overhead Rate 162 % x Total Direct Labor $ 148,149.00 7. SUBTOTAL: Labor + Overhead (Items 5 & 6) $ 239,599.24 8. PROFIT: Labor Related Costs (Item x 13% $ 31,148.00 PART III -OTHER COSTS 9. Miscellaneous Direct Costs Transportation $ 120.00 Original Reproducibles $ 544.50 Reproduction $ 677.60 Shipping $ 130.00 Other $ 0.00 MISCELLANEOUS DIRECT COSTS SUB-TOTAL $ 1,472.10 10. SUBCONTRACTS (Lump Sum) SUB-CONTRACT SUB-TOTAL $0.00 ~~`~~~'l~':~'T;A~~C)laV.~F~~C~11~~~M..~.II~... ~tems..~ ..~ ..8 ..9..a~c~ ..1I~ ..... ... ~'~~ 2:19..4 . 11. SUBCONSULTANTS (Reimbursable Costs -Limiting Amount) SUB-TOTAL REIMBURSABLES $ - PART IV -SUMMARY TOTAL AMOUNT OF CONTRACT (Lum Sum Plus Reimbursables $272,219.34 MANHOUR SUMMARY CONSULTANT: AIKENHEAD & ODOM, INC. RFP NO.: Prepared: November 1999 NAME OF PROJECT: Atlantic Beach Stormwater FROM: TO: ACTIVITY Principal In Char a Chief En ineer Senior En ineer En ineer CADD Desi ner Total Manhour s 2% 15% 18% 25% 40% 1.0 ADDITIONAL ELEVATION DATA COLLECTION Coordination With Surveyor 0 4 4 6 10 24 2.0 ADDITIONAL GEOTECHNICAL DATA COLLECTION Coordination With Geotech 0 4 4 6 10 24 3.0 ENVIRONMENTAL and LEGAL EFFORTS Coordination on Environmental Issues 5 36 43 60 96 240 4.0 HYDRAULIC /HYDROLOGIC MODELING Input of Final Data 3 24 29 40 64 160 Development of Hydrologic Model 10 75 90 125 200 500 5.0 FINAL CONCEPT PLAN Development of Final Concept Plan 3 24 29 40 64 160 Workshop and Coordination Meetings with SRC (3 me 2 18 22 30 48 120 Presentations & Meetings with City Commission (3 me 2 16 20 27 43 108 Final Town Meetings (1 meeting) 2 13 15 21 33 84 Coordination with SJRWMD and EPA 1 6 7 10 16 40 Drainage Design 5 36 43 60 96 240 Hydraulic Design 3 24 29 40 64 160 Preliminary Cost Estimates 1 10 12 16 26 65 6.0 FINAL PLANS PREPARATION (Preliminary Plans Only) Preliminary Drainage Plans Preparation 4 27 32 45 72 180 Preliminary Pump Station /Force Main Plans Preparati 6 46 55 77 123 307 Preliminary Roadway Plans Preparation 19 142 171 237 379 948 7.0 PERMITTING Permit Preparation /Submittal /Coordination 2 14 17 24 38 95 TOTAL MANHOURS 68 519 622 864 1382 3455 MISCELLANEOUS DIRECT COST CONSULTANT: AIKENHEAD & ODOM, INC. RFP NO.: Prepared: November 1999 NAME OF PROJECT: Atlantic Beach Stormwater FROM: TO: ITEM DESCRIPTION ITEM COMMENTS TOTAL Drafting Medium: (Mylar Original Reproducibles) 121 Sheets @ $4.50 Per Sheet = $544.50 Reproduction (Blue Line & Sepias) Plots 8 1/2" x 11" Phase I (30%) # of Sets : 5 121 605 500 Phase II (60%) # of Sets : 121 0 Sheets Phase III (90%) # of Sets : 121 0 Sheets Phase IV (100%) # of Sets : 121 0 Sheets Bidding # of Sets : 121 0 Sheets Total Sheets 605 605 0 Cost: Plots 605 Sheets @ $ 1..00 = $605.00 11 "x 17" 605 Sheets @ $ 0.12 = $72.60 8 1/2" x 11" 0 Sheets @ $ 0.05 = $0.00 $677.60 Travel From: [Consultant Office Location] To Project: # Trips Transport. 1.0 x 30 miles x $0.30 per mile* To City Hall: # Trips Transport. 4 x 20 miles x $0.30 per mile* To Other Agency: # Trips Transport. 1 x 20 miles x $0.30 permile* $120.00 Other (Specify) Shipping $130.00 TOTAL COST $1,472.10 ROADWAY PLAl~_ _'REPARATION CONSULTANT: AIKENHEAD & ODOM, INC. RFP NO.: Prepared: November. 1999 NAME OF PROJECT: Atlantic Beach Stormwater FROM: Tn ITEM SCALE UNIT NO. OF UNITS NO. OF SHEETS M-H PER UNIT TOTAL MANHOURS '' COMMENTS Key Map, Index & Standards Sheet 0 0 0.00 0.00 Typical Section and Notes Sheet 0 0 0.00 0.00 Summary of Quantities Sheet 0 0 0.00 0.00 Summary of Temp. Erosion Cntrl Sheet 0 0 0.00 0.00 Plan & Profile 1 "=40' Sheet 82 82 8.00 656.00 Preliminary Plan Intersection Details Sheet 0 0 0.00 0.00 Intersection Profiles Sheet 0 0 0.00 0.00 Ditch /Canal Regrading 1 "=40' Sheet 4 4 12.00 48.00 Preliminary Plan Regrading Details Sheet 0 0 0.00 0.00 Misc. Constr. Details Sheet 0 0 0.00 0.00 Water Details Sheet 0 0 0.00 0.00 Sanitary Sewer Details Sheet 0 0 0.00 0.00 Stormwater Pollution Prevention Sheet 0 0 0.00 0.00 Erosion & Sediment Control Sheet 2 2 82.00 164.00 Preliminary Plan Maintenance of Traffic Sheet 0 0 0.00 0.00 Cross Sections Section 1.56 0 0.00 0.00 Quantity Calculations L.S. 1 0 24.00 24.00 Preliminary Plan SpecificationsBid Manual L.S. 1 0 0.00 0.00 Cost Estimates Each 2 0 16.00 32.00 Preliminary Plan Pavement Design L.S. 1 0 0.00 0.00 Preconstruction Public Meeting Each 1 0 0.00 0.00 Meetings -Site & City Each 3 0 8.00 24.00 Preliminary Plan ROADWAY PLANS TOTALS 253 88 948.00 DRAINAGE PLAl~ . 'REPARATION CONSULTANT: AIKENHEAD & ODOM, INC. RFP NO.: Prepared: November, 1999 NAME OF PROJECT: Atlantic Beach Stormwater FROM: TO: ITEM SCALE UNIT NO. OF UNITS NO. OF SHEETS M-H PER UNIT TOTAL MANHOURS COMMENTS Drainage Map Sheet 1 1 16.00 16.00 Preliminary Plan Supplementary Drain. Map Sheet 4 4 16.00 64.00 Preliminary Plan Design -Major X-Drains Each 0 0 0.00 0.00 Drainage Struct. -Rural Sheet 0 0 0.00 0.00 Drainage Struct. -Urban Sheet 100 0 1.00 100.00 Preliminary Plan Summary of Drainage Structures Sheet 0 0 0.00 0.00 Misc. Drainage Details Sheet 0 0 0.00 0.00 Sherman Canal Plan & Profile Sheet 0 0 0.00 0.00 DRAINAGE TOTALS 105 5 180.00 PUMP STATION ~ JRCE MAIN PLANS CONSULTANT: AIKENHEAD & ODOM, INC. NAME OF PROJECT: Atlantic Beach Stormwater RFP NO.: FROM: Prepared: November, 1999 TO: ITEM SCALE UNIT NO. OF UNITS NO. OF SHEETS M-H PER UNIT TOTAL MANHOURS COMMENT No. 1 & 2 Site Plan Sheet 1 1 8.00 8.00 Preliminary Plan No. 1 & 2 section & Details Sheet 2 2 8.00 16.00 Preliminary Plan No. 1 & 2 stud. Details (elect) Sheet 0 0 0.00 0.00 No. 1 & 2 misc. site details Sheet 0 0 0.00 0.00 No. 1 Forcemain Plan & Profile Sheet 2 2 12.00 24.00 Preliminary Plan No. 2 forcemain Plan & Profile 1 "=20' Sheet 4 4 12.00 48.00 Preliminary Plan No 2 site plan Sheet 1 1 8.00 8.00 Preliminary Plan No . 3 section & details Sheet 2 2 8.00 16.00 Preliminary Plan No. 3 std. Details (elect) Sheet 0 0 0.00 0.00 No. 3 misc. details Sheet 0 0 0.00 0.00 No. 3 Suction Lines plan & profil e Sheet 1 1 8.00 8.00 Preliminary Plan No. 3 forcemain plan & profile Sheet 15 15 12.00 180.00 Preliminary Plan PUMP STATION /FORCE MAIN PLANS PREPARATION 28 28 308.00 PERMITTING AND . , VIRONMENTAL CONSULTANT: AIKENHEAD & ODOM, INC. NAME OF PROJECT: Atlantic Beach Stormwater RFP NO.: FROM: Prepared: November, 1999 Tn~ ITEM SCALE UNIT NO. OF UNITS NO. OF SHEETS M-H PER UNIT TOTAL MANHOURS COMMENTS Permit Prep. and Coordination SJRWMD - MSSW Permit Project 1 0 16.00 16.00 Preliminary Negotiations SJRWMD -Dredge/Fill Permit Project ( 0 16.00 16.00 Preliminary Negotiations Fla. Dept. of Environ. Protection Project 0 0 0.00 0.00 Fla. Dept. of Natural Resources Project 0 0 0.00 0.00 Corps of Engineers Project 1 0 0.00 0.00 Fla. Dept. of Transportation Project l 0 0.00 0.00 City Clearing Permit Project 1 0 0.00 0.00 NPDES Project ] 4 0.00 0.00 Wetland Staking (Admin.) Project 1 0 24.00 24.00 Preliminary Wetlan Delineations Mitigation Design (Admin.) Project 1 0 40.00 40.00 Preliminary Design PERMITTING AND ENVIRONMENTAL TOTALS 8.00 4.00 96.00