Exh 3A,~ A ,_z~.-ao January 19, 2000 MEMORANDUM TO:` The Honorable Mayor And Members of the City Commission FROM: Jim Hanson City Manager Subject: Follow -up items from Commission meetings Elimination of Bump at MaYport Road -Plaza Drive Intersection: In a recent City Commission meeting, the question was raised about the cost of eliminating the bump in the road at the intersection of Mayport Road and Plaza Drive. The estimated cost to lower the city's 10 inch water line is $50,000.00. Additionally, there is a Bell South duct bank and possibly a Media One cable line. We do not have estimated costs for the relocation of these but it is possible that each may be required to absorb the cost if the City were to proceed with this project. This issue was considered in the eazly 90's during the construction of Section H roads, but was not done at the time because of the estimated cost. Public Works staff will present a brief presentation on this at the Commission meeting.