Exh 4A PUBLIC WORKS4 O 1 PUBLIC WORKS PROJECT STATUS REPORT ((D) =DESIGN ENGINEER, DEPARTMENT (CE&I) =CONSTRUCTION ENGINEER (C) =CONTRACTOR PROJECT DESCRIPTION PROJECT NO. STATUS ON 3/3/00 1. Village of Mayport D) =USCG & JEA Force-main installation and tie in for Coast Guard Station has been completed. CE&I) = JEA & Public Works Mobilization started for collection system improvements. Began installation of master Design -100% complete C) =Petticoat Contracting - to USCG wetwell on 8/20/99. The lift station is 80% complete, installation of sanitary sewer is Constn~ction - 40% complete tatton (C) =United Brothers -North of USCG 50%compplete, water is 35% complete, and the force main is 50% complete. Roadway work is 75% complete Station . 2. Core City Stormwater Project CORE99 (D) =Original by England Thims & Stormwater & Water -Commission authorized A & O to complete a ppreliminary esi n on 12 t4 99 and a th ri d ti f th t 1/10/00 A SRC Stormlvater & Water - Preliminary Desig» 10% , YVfiller Revised Preliminary Design by The g u o ze execu on o e con ract on . n meeting was held on 1/13/00. A & O met with Mr. Phillips and Mr. Posch regarding locations of field elevations for model calibration. Another SRC meeting was held on complete. R-A-M Professional Group 2/23/00. Sewer -Sewer televising crew mobilized 9/17/99, work is 100% complete, Sewer -Design 90% complete Re-design by Aikenhead & Odom for stormwater & water significant amount of infiltration discovered, with approximately 70% from laterals and 30% from main lines Smoke testin was com leted D c mb 8 1999 M t , Sewer design by Public Works. C =Vid I i d . g p e e er , , os problems noted were broken or uncapped cleanouts. Two direct connections between ( ) eo n ustr al Services, Inc. (for the storm and sewer systems were found, and a few possible cracked laterals. Letters sewer televising) Florida Rural Water Assoc (For were sent to residents notifying of problems, encountered from smoke testing. Public W k h i d d d li . or s as rev ewe tapes an reports, an is assemb ng specifications and plans. smoke testing) (CE&I) =Public Works 3, Wonderwood Connector Utility (D) =The R-A-M Professional Group, Construction began on 7/12/99. Began installation of water main 9/17/99. Health Relocation Inc. Dept. clearances received and services connected on section of line at intersection of CE&I = JTA, JEA & Public Works ~ Wonderwood Road and AlA, Mallard Cove, and Wonderwood Lane. Began Design -100% complete C) _ Superior Construction Co. installation of 6-inch water main at Apollo Drive. Construction - 25% complete 4. 1999 Water Line Improvements Project -Non-CDBG (D)) Smith & Gillespie Engineers, Inc. (C$&p =Public Works Commission awarded bid to Gruhn May, Inc. to construct entire Non-CDBG roject, i l di ll lt 7/26/99 P i f nc ng a u a ernates, on . reconstruet on con erence was held 8/4/99, and (Water Line Installation and (C) = Gruhn May, Inc. Notice to Proceed was issued 8/23/99. Installation of 6-inch water main on Park Replacement-Various Terrace West to Country Club Lane to Seminole Road is complete and new services Locations) connected. Installation of water line on East Coast & 12~' Street complete by 11/19/99, Design -100% complete Health Dept, clearance received, currently connecting services. Completed installing 6-inch water line on Lewis Street Cavalla Road and Mayport Terrace services , , connected. Water lines on Robert Street, Shangri-La and Jackson Road installed, Construction - 60% complete awaiting Health Dept. clearance. . 5. 1999 Stormwater Improvements Project (stormwater improvements at various ((D =Smith & Gillespie Engineers, Inc. (C~=Petticoat Contracting, Inc. (C &I) =P bli k W Bid awarded to Petticoat Contracting, Inc. by Commission on 10/11/99, Budget Ordinance approved 10/25/99. Notice to Proceed issued for 11/1/99. Contractor bili d locations) u c or s mo ze 11/15/99. Installation of drainage lines on Donner Road, Pine Street, Seminole Road and Palm Ave. completed. Installed new drainage structures and tide Design -100 % comp/ete gate at Aquatic Drive. Installed sidewalk on Donner Road. Began excavation for retention pond at Public Works yard. Construction - SO% complete 6. Buccaneer Wastewater ((D)) = Eder Engineering Influent structure and installation of influent line and four manholes completed. Grit Treatment Plant Expansion. (C) = Meadors Construction Co. removal structure and master wetwell have been constructed. New transformer pad, (C &I) =Gannett Fleming Engineering main electrical feed conduit and other conduit stub outs have been installed. New Design -100% complete generator installed, load tested, and inspected by RESD. Painting of two additional tanks approved by Commission on 10/25/99. Force main tie-in made on 11/10/99 Constnrction - 80% complete . Chlorine Contact Chamber bypassed on 11/30/99, has been inspected and will need total sandblast and repaint on interior. Hightower Geotechnical completed underpinning of operations building on 12/16/99. Com leted effluent piping from tanks x f t ti SBR 3 C l d 9 °~ f e cepp ~ or connec ons to , ompp ete 5 o underground piping. Installed etI]uent umps. 90% of piping to be removed has been removed. Startup of f t d d S~BR l E d i irs secon an comp ete . qualizat on tank in process of being rehabilitated. 7. Atlantic Beach and Buccaneer CE&I~ Public Works ~ Commission approved engineering contract on 4/12/99, to include cost/benefit Sewer System Improvements. D) e & Jenson analysis of Shangri La lift station abandonment. Cost/benefit analysis of Shangri La lift station abandonment i d 5/21 /99 100% d i l h b Design -100% complete rece ve on . es gn p ans ave een submitted. On hold until completion of Sewer Master Plan. 8. Town Center D =Glen Mitchell & Assoc. ~C~ = ABBA Construction Construction began on 7/28/98. Roadway work completed on Atlantic Blvd. by 10/15/99. On November 1, 1999 the City Commission voted not to include additional Design -100 % complete work on Ocean Blvd. Construction underway on Ocean Blvd. between Atlantic Blvd. and Ahern St. Gruhn May replaced sewer line on Ocean from Atlantic Blvd. to Ahern Constnrction - 80% complete St. by 2/10/00. 9. Widening of Atlantic Blvd. B id (D) = H.W. Lochner, Inc. FDOT Received partial preliminary plans for review on 4/29/99, and advised on 5/5/99 that r ge no utilities are affected. Geotechnical work underway on 8/13/99. Public Works received 100% plans on 12/22/99; plans under review. Two ponds will be constructed Design -100% complete by JTA, but not shown on bid plans. 10. Mayport Flyover (D) =Pittman, l?3artenstein & Assoc. Bid for construction was awarded to Superior Contracting on 10!27/99. Pittman, FloyverDesign -100% JTA Connelly & Wicker for Atl. Beach Hartenstein, Inc. completed utility design for JEA improvements. Received 100% plans on 12/7/99. Staff reviewed for utility conflicts and sent comments to JTA. complete C) =Superior Construction Co. ~C &I) =Public Works Construction began on 1/7/00 on the existing overpass, approaches and median of Atlantic Blvd. Contracted with Connelly & Wicker on 2/24/00 to design relocation of Utility Design - <S% complete water line to accomodate for conflicts. Constnrction - S% complete 11. Sewer Master Plan •! (D) =Smith & Gillespie Engineers, Inc. Authorization to negotiate with Smith & Gillespie Engineers was approved by. Commission on 11/8/99 contract a ro Cit ed b C i i 1PO/00 P S% complete. y , pp v y omm ss on . rotect "kickoff meeting" held 1114/00 Engineer and technicians are performin lift station , g pumpdown tests and assembling information for UI analysis. 12. Utility Improvements 2000 (D)=Gee & Jenson Request for Proposals for engineering design advertised on 11/14/99 received 8 Design <S% complete. , proposals on 12/17/99. City Commission authorized staff to negotiate with Gee and Jenson on 1/10/00 and relimi l b i d 1/2 / i , p nary proposa su m tte on 00. C 7 ty Commission approved contract with Gee & Jenson on 2/14/00. 13. CDBG Project -Manhole rehabilitation in Donner (D)=Public Works Request for Proposals for engineering design advertised on 11 /14/99, received 8 l 12/1 /9 i Subdivision proposa s on 7 9. C ty Commission authorized staff to negotiate with Gee and Jenson on 1/10/00, and preliminary propposal submitted on 1/27/00. During negotiations determined desi n wo ld b l t d b Ci ff o Design -<S/o complete , g u e comp e e y ty sta . 14. Effluent Structure Repairs (D) = Nadeem Zebouni, Inc. and Public W k Engineering evaluation, specification development underway. Received plans and Design -complete or s specifications on 12/20/99. Modifications to plans complete and resubmitted by 1/17/00. 15, Milling & Paving (D) = Universal Engineering Sciences (Geotechnical) Geotechnical report completed on 10/28/99. Bid specifications completed, and bids advertised 2/20/00. Geotechnical -100% complete Public Works (specifications) Design Specifications - 100% complete 16. Walkways/Handrails on AB WWTP i d (D) =Jim Gilliam and Public Works Division Director met with designer on 12/17/99 to determine scope and price for han ra ls design work. Design underway as of 1/3/00. Design - 90% complete ' 17. Replacement of Hydroppneumatic Tank at Water P (D) =Public Works Specifications completed 2/29/00. Bids to be advertised 3/5/00. lant #4 Design - 100% complete