Exh 4DAGENDA ITEM #4D SEPTEMBER 25, 2000 CITY OF ATLANTIC BEACH CITY COMMISSION MEETING STAFF REPORT AGENDA ITEM: SUBMITTED BY: DATE: BACKGROUND: __ __ _ _ . Utility Improvements 2000; Projects 4A-4D Bid No. 99-0022 Robert S. Kosoy, Director of Public Works ~~ September 19, 2000 On September 13, 2000 bids were opened for Utility Improvements 2000, and only one of the three contractors who prequalified for the project, Gruhn May, Inc., submitted a bid. The bid compared to the engineer's estimate as follows: Engineer's Gruhn May's Estimate Bid A. Swales/Driveways on West 13~' Street B. Beach Avenue Water Main Improvements C. Sailfish and Plaza Water Main Improvement D. Levy Road Sidewalk Improvements Subtotal Construction Cost: 10% Contingency Grand Total $ 20,000 $ 37,395 $ 170,000 $ 388,456 $ 30,000 $ 38,612 $ 40,000 $ 46,920 $ 260,000 $ 511,383 $ 51,138 $ 260,000 $ 562,521 This single bid is significantly over the budget which was based on the .engineer's estimate. The greatest differential in item B was due to the very high price on the directional boring of the 8" water main on Beach Avenue. If the option is provided to the contractor to open cut Beach Avenue, prices could be reduced. BUDGET: Utility Improvements 2000 is a combination of several small projects totaling $290,000 for design and construction. Funds. are located in accounts as follows: 001-5002-541-6300 (Streets) $ 55,000 400-4001-533-6300 (AB Water) $ 185,000 130-5002-541-6300 (Gas Tax) $ 50,000 RECOMMENDATION: City staff recommends the Commission reject the bid and authorize staff to have the plans revised to allow_the .flexibility of rebidding either an open cut or directional boring on Beach Avenue, in order to reduce the cost of the most expensive bid item. ATTACHMENT: Bid by Gruhn May, Inc. REVIEWED BY CITY MANAGER: SUBMIT IN AGENDA ITEM #4D - - SEPTEMBER 25, 2000 TRIPLICATE BID FORM FOR UTILITY IMPROVEMENTS 2000 - PROJECTS 4A-4D -- FOR THE CITY OF ATLANTIC BEACH ATLANTIC BEACH, FLORIDA SUBMITTED BY: GRUHN MAY, INC. DATE: September 9, 2000 6897 Philips .Parkway Dr. N. - The undersigned, as Bidder, hereby declares that the only person or persons interested in the proposal as Principals is, or aze, named herein and that no other person that herein mentioned has any interest in this proposal or in the contract to be entered into; that this proposal is made without connection with any other person, company, or;parties making a bid or proposal; and that it is in all respects fair and in good faith, without collusion or fraud. The Bidder further declares that he has examined the site of the work and informed himself fully in regard to all conditions pertaining to the places where the work is to be done; that he has examined the plans and specifications for the work and contractual documents relative thereto, and has read all special provisions furnished prior to the opening of bids, that he has- satisfied himself relative to the work to be performed. The Bidder proposes and agrees, if this proposal is accepted, to contract with the City of Atlantic Beach, Florida in the form contract specified, to furnish all necessary materials, equipment, machinery tools, apparatus, means of transportation and labor necessary to complete the contract in full and complete in accordance with the shown, noted, described, and reasonable intended requirements of the plans and specifications. and contract documents to the full satisfaction on the contract with the City of Atlantic Beach, Florida, with_a definite understanding that no money will be allowed for extra work except as set forth in the attached general conditions and contract documents, as follows: Proposal Schedule Bidders must submit a bid price on each item as described below. Only one (1) contract will be awarded. All entries on the proposal must be typewritten or printed clearly and in ink. Bidders must insert extended total item prices computed from quantities and unit prices.. In case of errors in extensions, unit prices will govern. 20-121.00 BFU-1 AGENDA ITEM #4D '~ SEPTEMBER 25, 2000 .Project 4A'-West 13`i' Street -Drainage Improvements Item Est. Unit ' No. Base Bid Items Unit Quant. Price ($} Amount ($; 1. Construct 15" HDPE Pipe LF 200 $ 6 4 $ 12 , 8 0 0 2. Construct Endwalls ~ EA 6 $ 5 8 0 $ 3, 4 8 0 _. 3. Remove Concrete Driveway SY 286 $ 9 $ 2 , 5 7 4 4. Construct 5" Concrete Driveway SY 286. $ 31 $ S , 8 6 6 5. Sodding - St..Augustine Grass SY 350 $ 3.50 $ 1 , 225 6. Grading LS 1 $ 3 7 2 0 $ 3, 7 2 0 7. Remove and Replace Landscaping LS 1 $ 2 3 2 0 $ 2. 3 2 0 8. Additional Fill CY ~ 80 $ 10 $ 8 0 0 9. Remove Existing Piping LS 1 $ 1 ti 1 0 $ 1 ti 1 (1 . ~ : ~ Subtotal Project 4A - $ ~ 7 ~ ~ A 5.0 ~ Project 4B -Beach Avenue -Water Main Improvements Item Est. Unit No. Base Bid Items Unit Quant. Price ($) Amount ($) 1 Directional Drill 8-inch PVC DR 18 LF 2 310 $ $ Water Main 9 5 21 9, 4 5 0 2 Construct 6" PVC DR 18 Water Main LF 516 39 20, 124 3 Construct 6" PVC DR 25 Water LF Main 4 Construct 4" PVC DR 18 Water LF Main Connect New Water Main to 5' ~ Existing Water Main 18 $4 39 5 $ 180 $ 900 702 a. 4" x 4" Tapping Sleeve and Valve EA 2 $ 18 9 0 $ 3 , 7 8 0 6. 7. 8. b. 6" x 6" Tapping Sleeve and Valve Construct 6" Gate Valve Construct 8" Gate Valve ~ Construct 6"x 8" Reducer EA EA EA EA Z 8 6 1 $ $ $ $ 1 9 5 0 6 Z o 9 g ~ 5 5 0 $ $ $ $ 3, 9 0 0 4, 9 6 0 5 , 8 8 0 5 5 0 9. Construct 4"x 8" Reducer EA 1 $ 5 5 0 $ 5 5 0 10. Construct 4" Plug EA 5 $ g 8 0 $ 4, 9 0 0 11. Construct 6" Plug EA 1 $ 12 2 0 $ 1 , 2 2 0 12. Construct 3" Cap EA ' 2 $ g g 0 $ 1 9 6 0 13. Construct 4" 90° Bend EA 1 $ 7 4 0 $ , 7 4 0 14. 15. Construct 6" 90° Bend Construct 6" 22.5° Bend EA EA 6 2 $ $ 410 41 0 $ $ 2 , 4 6 0 g 2 p 16. Construct 6" 45° Bend 20121.00 - EA 6 BFU-2 $ 410 $ 2 , 4 6 0 Addendum No. l Page 2 AGENDA ITEM #4D '~ ~ SEPTEMBER 25, 2000 Project 4B -Beach Avenue Cont'd Item Est. Unit No. Base Bid Items Unit Quant. Price ($) Amount ($) 17. Construct 8"x 4" Tee EA 1 $ ..910 $ 910 - 18. Construct 8"x 6" Tee EA 6 $ 1.1.2 0 $ 1 12 0 19. Construct 6" Tee EA 1 $ 1 12 0 $ 1 12 0 Construct 8"x6" Tee w/ 20. Plugged Dead-End EA 6 $ 14 8 0 $ g, g g 0 21. Construct Fire Hydrant EA 6 $ 2 g g p $ 17 3 4 0 22 Construct 1" Single Service to Meter EA 29 $ 7 8 0 $ 2 2 , 6 2 0 (Long Side) 23 Construct 2" Double Service to Meter EA 10 $ (Long Side) g g 4 $ 9, 9 4 0 24. Construct 1" Single Service to Meter EA 14 $ $ (Short Side) 5 8 8 8, 2 3 2 Construct 1" Single Service to Meter/ 25. Relocate Existing Water Meter (Short EA 21 $ $ Side) 550 1 1 , 550 26. Water Meter Boxes EA 5 $ 7 ~ $ ~ ~ ~ 27. Water Meter EA 5 $ g 0 ~ $ 4 0 28 Construct 2" Temporary Sample EA 3 $ ~ $ Point 580 1 , 740 29. Remove Existing Fire Hydrant EA 1 $ 7 5 0 $ ~ S 0 30. Remove Concrete Sidewalk SY 20 $ 12 $ 2 4 0 31. Construct 4" Sidewalk SY 20 $ $ 3 6 7 2 0 32. Remove Concrete Driveway SY 207 $ 12 $ 2 , 4 8 4 33. Construct 5" Concrete Driveway SY 207 $ 47 $ g 729 34. Remove Brick Walk/ Parking Area SY 20 $ ~ 2 $ 2 4 0 35. Construct Brick WalklParking Area SY 20 $ ~ ~ $ 1 700 36. pavement Removal SY 240 $ g $ T 2 ,1 6 0 37. Paving Repair -Patches SY 240 $_ 4 5 $ 10 , 8 0 0 Subtotal Project 4B - $ 388.456 .-00 20121.00 - BFU-3 Addendum No. l Page 3 AGENDA ITEM #4D SEPTEMBER 25, 2000 ,~ Pro,~ect 4C -Sailfish and Plaza -Water Main Improvements Item Est. Unit No. Base Bid Items Unit Quant. Price ($) Amount ($) 1' Directional Drill 6-inch PVC DR 18 . _ _ __ __LF _ _ 53 $ 1°4p $ 7420.. _ _ Water Main 2. 6" PVC DR 18 Water Main LF _45 $ ~ 125 $ 5, 625 3. 4" D.I. Flg. Spool Pieces EA 4 $ 4 9 0 $ 1 , 9 6 0 4. 6" D.I. Flg. Spool Pieces EA 2 $ 5 8 0 $ 1 1 6 0 5. 4" Flg. Gate Valves EA 1 $ 5 9 0 $ 5 9 0 6. 6" Flg. Gate Valves EA 2 $ 6 4 5 $ ~ ~ ~ o ~ Connect New Water Main to Existing Water Main a . 6"x6" Tapping Sleeve and Valve EA 1 $ 2 410 ~ $ 2 , 4.10 8 6" Compound Sensus Meter w/ EA 1 $ $ Touch Read System 7 9 6 2 7, 9 6 2 9. 6"x4" Flg. Tee EA 2 $ 610 $ 1 , 2 2 0 10. 6" 90° Bend._ EA 2 $ 580 $ 1 ,160 11. 4" Flg. 90° Bend EA 2 $ 510 $ 1 , 0 2 0 12. 6" Plug EA 1 $ 590 $ 590 13. Remove Concrete Sidewalk.. SY 5 $ 22 ~ $ 1 10 14. Construct 4" Sidewalk SY 5 ~ 4 9 $ 2 4 5 15. Remove Existing Gate Valves EA 2 $ 4 0 0 $ 8 0 0 16. Remove Existing Meter and Delivery EA 1 $ $ to Owner 5 9 0 5 9 0 1 ~ Remove Existing Valve Box and $ Cover EA 1 g 0 0 $ 9 0 0 18. Construct New Pre-Cast Valve Box EA 1 $ $ ~ ~ o o 2 , 3 0 0 19 Construct New Halliday Access $ . Hatch EA 1 12 6 0 $ 1, 2 6 0 Subtotal Project 4C - $ 3 8 , 61 2.0 0 20-121.00 BFU-4 AGENDA ITEM #4D SEPTEMBER 25, 2000 ~, Protect 4D -Levy Road -Sidewalk Improvements Item Est. ~ ~ No. Base Bid Items Unit Quant. ~ YJnit Price ($) Amount ($) 1. Construct 4" .Sidewalk SY ~ 900 $ 3 ~ $ 3 3 , 3 0 0 2' Remove & Replace 3' Guard LF 25 $ 1 5 6 _ $ _ _ . _ _____ ___ 3, 9 0 0 Rail 3. Remove Fencing LF 30 $ 15 $ 4 5 0 4. Remove Concrete Block WaII LF l 0 $ 4 0 $ 4 0 0 5. Remove Concrete Walkway SY 10 $ 1 2 $ 1 2 0 6. Relocate Sign EA 1 ~ $ 15 0 $ 15 0 7. Construct 15 "_ HDPE Pipe LF 30 $ 5 0 $ 1 , 5 0 0 8. Construct Endwall EA 2 $ 5 8 0 $ 1, 1 b 0 9• Construct Handrails LF 36 $ 1 6 5 $ 5, 9 4 0 Subtotal Project 4D _ $ 4 6 , 9 2 0.0 0 Subtotal Base Bid Projects 4A thru 4D - $ 511 , 3 8 3.0 0 Construction Contingency (10% of Subtotal} - $ 51 ,13 8.3 0 Total Base Bid Items - $ 5 6 2 , 5 21 .3 0 BID SECURITY .... Accompanying this Bid is a certified or cashier's check or a bid bond in the amount of 5% made payable to the Owner which may be forfeited as liquidated damages if, in the event this. proposal is accepted, the undersigned fails to execute the Agreement and furnish and pay for the required performance and payment bonds for the Owner within 10 days after acceptance of the Bid; otherwise said certified or cashier's check. or bid bond will be returned to the undersigned. TIME The undersigned Bidder agrees to commence work within. 10 days after the date of written Notice to Proceed, and further agrees that completion of the work shall be .within 18 OCalendar days after written Notice to Proceed for the Base Bid. The Bidder agrees that this bid shall be good and may not be withdrawn for a period of 90 days after the opening of bids. The Bidder understands that the Owner reserves the right to reject all bids, and to waive informalities in the bid: The Bidder further proposes and agrees to commence work under his contract an a date to be specified in a written order of the Owner and shall complete all work thereunder. within the time schedule in the Form of Agreement. 20-121.00 BFU-5