Loading...
Exh 8A] _ ll0 A abv a~w ~~ va a October 9, 2000 This Preliminary Engineering Report was commissioned by the Atlantic Beach City Commission as the second phase of a three part design effort to reduce the level of flooding that Atlantic Beach has been experiencing for over a decade. The first phase of the program developed very preliminary investigative data, including a logging and orderly collation of all existing documentation and complaints. This phase resulted in a letter report on the existing data, models, and a summary of the master concept stormwater options as seen at that time. The second phase, this Preliminary Engineering Phase, consists of additional data collection, detailed hydrologic and hydraulic modeling, and development of a final conceptplanandpartialpreliminaryengineeringdesigns/drawings. Very preliminary environmental and permitting efforts were also accomplished within this phase. Based on the results of this Preliminary Engineering Phase, the proposed plan consists of channeling stormwater runoff through the Core City utilizing inverted crown pavement, development of piped ocean outfall reversals, select water and sanitary sewer improvements, reconstruction of Sherry Drive with curb and gutter and including a piped drainage system to collect the Core City street runoff, channel cleaning/dredging of the Sherman Creek Canal from Howell Park to Puckett Creek, reconstruction of the culvert under 11~' Street, and installation of a tide control structure with aloes-flow draw down pump system at Water Treatment Plant No 2. The third phase of the design effort, Final Design, will develop fmal construction plans and specifications. This process will include final development of concept alternatives to back yard drainage, Town Center drainage, wetland mitigation, tidal control, and other relatively minor concept issues which have several options unresolved during the Preliminary Engineering Phase. Final Design will be developed in two phases: 1. An "early-out" design for the reconstruction of Sherry Drive to 24' pavement with curb & gutter. This is exactly the section designed under the ET&M design and existing St. johns River Water Management District (SJR.WMD) Atlantic Beach Stormwater Final Report Execufive Summary, Page 1 of 2 Agenda #8A October 9, 2000 permit, and will be constructed using this existing permit. Wetland impacts will be carefully avoided during this design in order to avoid any Army Corps of Engineers (ALOE) permit requirements. 2. As saon as the Sherry Drive design is completed and while it is being let to contract, all remaining design effort will be .commenced. This phase will involve modifying the existing SJRWNID permit to meet the new design, and re-submission of the ACOE permit, either in Nationwide format as previously submitted or in Individual permit format, depending on impacts and criteria of the Final Design. The current recommended improvements differ substantially from past engineering studies of this area, largely due to the following: • Compilation and coordination of existing data and complaints • Acquisition of specific additional data • Extensive field reconnaissance • Highly detailed hydrologic and hydraulic modeling • Input from Early Piety regarding tree impacts • Detailed input, from the City Commission, Stormwater Review Committee, Public Works, and from residents individually and at town meetings • Development of innovative concepts • The open mindedness ofthe City Commission, Stormwater Review Committee, and the Public Works Department to accept innovative ideas Throughout this document, figures and other related graphics have been inserted within each related section, but references to specific figure have been deleted from text due to compilation complexities. Additional informative data and graphics have been included within the Appendix. Readers are encouraged to ask questions. Atlantic Beach Stormwater Final Report Executive Summary, Page 2 of 2