CITY OF ATLANTIC BEACH
CITY COMMISSION MEETING
STAFF REPORT
AGENDA ITEM: Change Order No. 4 -Lifeguard Station
SUBMITTED BY: Don C. Ford
DATE: May 18, 1999
BACKGROUND:
Enclosed is Change Order No. 4 for the Lifeguard Station Project.
The attached memorandum explains the items in the change order. Please note
~"1 that this is a no cost to the City Change Order.
RECOMMENDATION: Approval of Change Order No. 4
ATTACHMENTS: Memorandum to David Thompson
REVIEWED BY CITY ~ ~ /;~~
(~
800 SEiv1INOLE ROAD
ATLA\TIC BEACH, FLORIDA 32233-5445
TELEPHONE (904) 247-5800
FAX (904) 247-5805
SUNCO~i 852-5800
MEMORANDUM
May 18, 1999
TO: David Thompson
FROM: Don C. Ford ~.~(~
RE: Lifeguard Station Change Order #4
Attached is Change Order #4 for the Lifeguard Station project. The changes
include structural additions to strengthen the wall system by using plywood on the
n interior as well as the exterior. This plywood replaces the sheetrock which is more
susceptible to damage from moisture.
Other Items include a window in the bathroom at no charge, smaller a/c unit, an
aluminum electric meter can which will outlast a metal can, additional strapping and red
head anchor bolts.
DCF/ph
Enclosure
' 04/29/99
~.
4.2
CHANGE ORDER FORM AND ACCOUNTING SUMMARY
CONTRACTOR'S NAME: Dowling Construction
ADDRESS: 241 Atlantic Blvd. #5 Neptune Beach, FL 32266
PHONE: 246-1833
FAX: 247-3147 ;°~ ~~ ~- ?y ~-~ n-,~
LIC #: CB0006834 ~-~. f' µ.,,., ~ ~ ~~
DATE:27Apri11999 ;~ij''+~~ 5 1999
City o. Atlantic Basch
OWNER'S NAME: City of Atlantic Beach Building and Zoning
ADDRESS: 800 Seminole Rd. Atlantic Beach, FL 32233
PROJECT ADDRESS: Oceanfront at Ahern Street Atlantic Beach, FL
CONSTRUCTION CHANGE ORDER # Four
I. GENERAL SCOPE OF WORK DESCRIPTION
Pursuant to the Construction Agreement between Contractor and Owner dated
15 September, 1999, Contractor agrees to perform the following as a change to
the original specifications and plans:
Cost:
1. Reframe west wall of bathroom to include vanity into bath. 200.
2. Add 2020 Marvin awning window to bathroom. NC.
3. Use'/~" CDX plywood on East-West interior walls for stiffness
Vs drywall. 500.
4. Upgrade stairwell roof system from "single ply" membrane to
Galvalume metal system with doubled wind resistance clips. 400.
5. Downgrade air conditioning system to smaller "package
system". (965.)
6. Supply aluminum meter can vs steel. 74.
7. Shift electrical panel box one stud bay South. 0.
8. Use 3/" plywood stair treads vs 2x12" PT pine. 0.
9. Add 8 additional First Floor wind resistance straps with redhead
anchors. 192.
10. Use 2x8"PT Stairwell Roof fascia with subfascia vs 2x4. 224.
Total: $1,025.
LUMP SUM PRICE FOR ALL WORK ABOVE: No charge
. +,
04/29/99- Lifeguard Tower-Dowling Construction 2 of 2
'` Additional time needed to complete project as a result of this Change Order: 10
Days.
ll. ACCOUNTING SUMMARY
A. Original Contract Amount: $7$.616•
B. Net Change by all prior Change Orders: $17.884.
C. Adjusted Gross Contract Amount prior to this Change Order: $6.500.
D. Amount of this Change Order: $QO
E. Adjusted Gross Contract Amount including this Change Order:
$96.500.
III. GENERAL CONDITIONS
~"
INCORPORATION
This Change Order, by agreement of Owner and Contractor, is incorporated by
reference into the Construction Agreement between Owner and Contractor. All
terms and conditions in the "General Conditions" section of the Construction
Agreement between Owner and Contractor apply to this Change Order.
I have read and understood the Change Order above, and {agree to all of its
terms.
Date David Thompson
City of Atlantic Beach
Date Heywood A Dowling
Dowling Construction